Kairos Power CEO Mike Laufer discusses iterative nuclear development, vertical integration, and Hermes 2 timeline
Summary
Kairos Power CEO Mike Laufer and host Brennan Moore discuss the company's vertically integrated business model, which mimics early SpaceX by manufacturing equipment, integrating systems, and operating plants. They highlight the KPFHR reactor technology using fluoride salt and solid TRISO fuel, noting its near-atmospheric pressure operation allows for safer, faster iteration. The speakers emphasize the importance of Engineering Test Units (ETUs) as training exercises to gain holistic lifecycle experience and reduce risk before commercial deployment. They outline the path to Hermes 2, targeting operations by 2030, and discuss scaling strategies that prioritize standardization over further architectural changes to achieve cost competitiveness.
Key takeaways
- 1 Found it in 2016. About 10 years ago, over 600 employees spread across Alameda, California, the headquarters, Albuquerque, New Mexico, the manufacturing hub, and Oak Ridge, Tennessee, the deployment hub.
Brennan Moore · 1:43
- 2 The KPFHR reactor uses fluoride salt coolant and solid TRISO fuel, operates at near-atmospheric pressure, and has a commercial plant size of 150 MWe (two reactors, one turbine).
Brennan Moore · 2:05
- 3 Kairos has received up to $578 million in DOE funding, split between $303 million in the ARTP program and $275 million announced for Hermes 2.
Brennan Moore · 3:49
- 4 Our outlet temperature for our reactor is 650 centigrade.
Unidentified speaker (speaker_0) · 13:16
Episode sections
- 0:00 – 1:42
Kairos Overview and Business Model
Brennan Moore introduces Kairos Power as a vertically integrated company that manufactures equipment, integrates systems, and operates its first plant. He highlights their iterative 'build, learn, repeat' philosophy, modeled after early SpaceX, and notes their status as a closely watched advanced nuclear name.
- 1:42 – 6:55
Company Profile and Partnerships
Moore outlines Kairos' founding in 2016, 600+ employees across California, New Mexico, and Tennessee, and its KPFHR reactor technology using fluoride salt and TRISO fuel. He lists partners including Google, TVA, Samsung C&T, and BWXT, and mentions DOE funding of up to $578 million.
- 6:55 – 12:49
Technology Origins and SpaceX Analogy
CEO Mike Laufer explains the company's formation from university research and its deliberate adoption of the early SpaceX model of iterative testing and vertical integration. He notes that high temperature and low pressure allow for safer, faster iteration on non-safety-critical components.
- 12:49 – 19:39
Manufacturing Advantages of Low Pressure
Laufer details how operating at near-atmospheric pressure allows for thinner reactor vessels, avoiding the need for specialized heavy forging facilities. This enables in-house manufacturing, faster supply chain qualification, and reduced regulatory audit burdens compared to high-pressure designs.
- 19:39 – 25:02
Solid Fuel vs. Liquid Salt Chemistry
Laufer contrasts Kairos' solid TRISO fuel in molten salt with liquid-fuel MSR designs. He argues that solid fuel simplifies chemistry by keeping radioactive material contained, allowing for significant non-safety system changes (like adding a turbine) with minimal regulatory review.
- 25:02 – 30:10
Vertical Integration in Fuel Production
Laufer discusses the high cost of TRISO fuel and Kairos' strategy of vertically integrating fuel production equipment. By building their own manufacturing tools, they aim to drive down costs through continuous processes and quality control, partnering with BWXT for scale.
- 30:10 – 31:36
Demonstration Projects and Hermes 2
Moore highlights Kairos' history of building full-scale hardware (ETU 1-3, Hermes 1) to de-risk technology before Hermes 2. Laufer begins to explain how these iterative loops of planning, designing, building, and testing reduce risk and validate the commercial design.
- 31:36 – 34:47
Iterative Learning and ETU Experience
Speaker_0 explains that the nuclear industry's long cycles and risk aversion hinder innovation, leading to fragmented experience. Kairos adopted an iterative approach similar to early SpaceX, using Engineering Test Units (ETUs) as training exercises to gain holistic lifecycle experience and learn from mistakes before building commercial plants.
- 34:47 – 37:59
Standardization vs. Innovation and Cost Control
The speaker discusses the tension between iterating on designs and standardizing for cost reduction. He notes that while innovation is necessary early on, locking in a standardized design is crucial for subsequent units to achieve economies of scale, a balance learned from SpaceX and South Korean nuclear best practices.
- 37:59 – 40:43
Vertical Integration and Control
Kairos positions itself as a manufacturer, integrator, and owner-operator rather than just a technology licensor. This vertical integration allows Kairos to control the project execution, manage interfaces, and capture the learning curve benefits, contrasting with models that offload development risk to EPCs or utilities.
- 40:43 – 44:02
Hermes 2 and Parallel Project Execution
The next five years focus on completing Hermes 2 while simultaneously preparing the next 450 MW site. The speaker emphasizes that overlapping construction phases is necessary to retain workforce knowledge and supply chain momentum, avoiding the atrophy that would occur if they waited for one project to finish before starting the next.
- 44:02 – 46:00
Capacity Constraints and 2035 Timeline
Speaker_0 warns that the period leading up to 2035 will stretch Kairos thin due to the need to build out supply chains and manage multiple projects. He states that post-2035 growth will be primarily limited by capital and human capacity, requiring careful balance between hyperscaler demands and investor expectations for rapid ramp-up.
- 46:00 – 47:21
Hermes 2 as First Grid-Scale Advanced Reactor
Brennan Moore asks if Hermes 2 will be the first commercial advanced reactor online in the US. Speaker_0 agrees, with the caveat that it will be the first 'grid-scale' advanced reactor, distinguishing it from smaller micro-reactors which may come online sooner but lack the scalability required by industrial customers and utilities.
- 47:21 – 1:21:59
Albuquerque Manufacturing Hub
The Albuquerque facility, over 180,000 square feet, serves as a microcosm for manufacturing reactor systems, fuel, and salt. It includes machining, welding, and fuel production capabilities, having evolved to take ownership of key components like graphite and vessels to ensure integration and scheduling.
Assets discussed
| Asset | Kind | Stance | Context |
|---|---|---|---|
| SpaceX | private company | bullish | Like over over ten years ago. And it's you know, everyone now is calling themselves the SpaceX of nuclear. It's on my nuclear bingo card. |
| AlphabetGOOGL | equity | neutral | Because the the first 500 megawatts through the development agreement with Google, I mean, how many how many development agreements are out there with real off-takers? |
“Stance” is how the speakers talked about the asset, not a recommendation.
Claims worth verifying
Kairos Power was founded in 2016.
Unidentified speaker (UNKNOWN) ·1:42
How to verify: Check Kairos Power corporate history on their website or SEC filings for founding date. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Primary sourceKairos has over 600 employees spread across Alameda, CA; Albuquerque, NM; and Oak Ridge, TN.
Unidentified speaker (UNKNOWN) ·1:42
How to verify: Review Kairos Power 'About Us' page or recent press releases for employee count and locations. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Kairos received the first Gen 4 reactor NRC construction permit in 2023.
Brennan Moore ·2:25
How to verify: Search U.S. Nuclear Regulatory Commission (NRC) press releases or docket documents for 'Kairos Power Construction Permit' issued in 2023. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Kairos has a development agreement with Google to deploy up to 500 MWe by 2035.
Unidentified speaker (UNKNOWN) ·2:50
How to verify: Review press releases from Google and Kairos Power regarding the nuclear partnership agreement. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Samsung C&T invested up to $100 million in cash and in-kind services.
Brennan Moore ·3:10
How to verify: Review Kairos Power press releases or SEC filings (if applicable) detailing the Samsung C&T investment terms. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Primary sourceKairos received up to $578 million in DOE funding ($303 million initial, $275 million for Hermes 2).
Brennan Moore ·3:49
How to verify: Check U.S. Department of Energy ARTP program award announcements and press releases for the specific funding amounts. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Hermes 2 is targeted for operations as early as 2030.
Brennan Moore ·4:09
How to verify: Review Kairos Power project timelines or NRC licensing documents for Hermes 2 operational targets. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Kairos' reactor outlet temperature is 650 degrees Celsius.
Unidentified speaker (speaker_0) ·13:16
How to verify: Check Kairos Power technical specifications or NRC safety analysis reports for the design outlet temperature. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Kairos has received construction permits for both Hermes 1 and Hermes 2.
Unidentified speaker (speaker_0) ·22:55
How to verify: Search NRC docket documents for 'Kairos Power' to confirm the issuance of construction permits for both units. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
The nuclear industry has limited full lifecycle experience because there are few success stories of going through the entire process, leading to fragmented expertise.
Unidentified speaker (speaker_0) ·31:36
How to verify: Review industry reports on nuclear project lifecycles and historical data on successful nuclear plant completions vs. cancellations/delays. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Kairos spent approximately $20 million on ETU 1, which was not for NRC compliance but for internal learning.
Unidentified speaker (speaker_0) ·36:55
How to verify: Check Kairos Power press releases or investor presentations from the ETU 1 completion period for cost disclosures. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Primary sourceHermes 2 is nominally expected to cost around $1 billion.
Unidentified speaker (UNKNOWN) ·37:19
How to verify: Review Kairos Power's public filings, investor decks, or news articles detailing the estimated cost of the Hermes 2 project. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Primary sourceKairos is building its first power-producing plant, Hermes 2, in Oak Ridge, Tennessee.
Unidentified speaker (speaker_0) ·40:43
How to verify: Verify via Kairos Power's official website, SEC filings (if any), or press releases regarding site selection and construction permits. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Primary sourceHermes 2 is expected to be the first grid-scale advanced reactor online in the US.
Brennan Moore ·46:00
How to verify: Compare construction timelines and licensing status of Hermes 2 against other advanced nuclear projects (e.g., TerraPower Natrium, X-energy) using NRC docket information. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
The Albuquerque facility is over 180,000 square feet.
Brennan Moore ·47:21
How to verify: Verify via Kairos Power's facility tours, press releases, or local commercial real estate records for the Albuquerque site. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
South Korean firms are best-in-class for following nuclear best practices.
Unidentified speaker (UNKNOWN) ·34:55
How to verify: Review industry analyses or reports from organizations like the World Nuclear Association or OECD/NEA comparing nuclear construction efficiency by country. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Kairos has a development agreement with Google for the first 500 MW build-out through 2035.
Brennan Moore ·45:09
How to verify: Check Google's official announcements or Kairos Power press releases regarding the partnership and off-take agreement. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
ETU 1 contained 14 tons of salt.
Unidentified speaker (speaker_0) ·33:11
How to verify: Review technical specifications or press releases from Kairos Power detailing the ETU 1 design parameters. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Primary sourceWestinghouse's AP1000 is the only domestic large-scale reactor design on the menu today.
Brennan Moore ·1:03:29
How to verify: Review NRC licensing status of US nuclear reactors; verify if any other large-scale (gigawatt-class) designs have received final construction permits or are under construction. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Kairos reactor size is 75 MW, similar to New Scale's 70-77 MW.
Brennan Moore ·1:04:30
How to verify: Check Kairos Power's technical fact sheets or NRC licensing documents for Hermes 1/2 design specifications; compare with New Scale Energy's public disclosures. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Hermes 2 is Kairos's first power-producing plant in Oak Ridge, Tennessee, on pace to be the first grid-scale advanced reactor online in the US.
Unidentified speaker (UNKNOWN) ·1:05:11
How to verify: Review Kairos Power's official website announcements or NRC construction permit filings for the Oak Ridge site. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Primary sourceKairos plans to evaluate a 'Rev 2' of the system architecture approximately 10 years out.
Unidentified speaker (speaker_0) ·1:06:23
How to verify: Cross-reference with Kairos Power's long-term roadmap presentations or investor day materials. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
The 50-100 MW sizing is validated by customers for data centers, and 150-600 MW suits utility grid operators.
Unidentified speaker (speaker_0) ·1:07:03
How to verify: Check Kairos Power's customer partnership announcements (e.g., with Google) and utility grid operator statements on demand for 300 MW increments. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
The NRC is developing a new Part 57 framework for low-consequence reactors.
Unidentified speaker (speaker_0) ·1:12:01
How to verify: Search NRC.gov for 'Part 57' or 'low consequence reactors' to find draft regulatory guides or framework documents. For recent events, verify 2026-08-23 through 2026-11-23. Use another period only when the speaker explicitly names it.
Do your own research
- Verify Kairos Power's employee count and founding date via their corporate website or SEC filings if publicly traded.
- Check the U.S. Department of Energy ARTP press releases for the specific $578 million funding award details.
- Review NRC Construction Permit applications for KPFHR reactor specifications, including the 650°C outlet temperature.
- Search for press releases from Google and TVA regarding the 500 MWe and 50 MWe partnership agreements.
- Examine NRC inspection reports or Kairos Power's quality assurance program descriptions to understand the audit scope for vertical integration.
- Look for counter-arguments regarding the economic viability of small modular reactors versus gigawatt-scale light water reactors.
- Verify the timeline for Hermes 2 operations against NRC licensing milestones and construction progress reports.
Full transcriptexpand
0:00Unidentified speaker (speaker_0): So Kairos is not just the technology provider. We're the manufacturer of equipment. We're the integrator of a lot of systems that are coming together. We're the owner operator of the first plat. So we have a lot more control over the project. Iterating.
0:14Brennan Moore: Build, learn, repeat. Build, learn, repeat.
0:17Unidentified speaker (UNKNOWN): You
0:17Brennan Moore: know, Kairos fits that mold better than anyone I've seen in the space.
0:22Unidentified speaker (speaker_0): Building that credibility has been key. And so the philosophy has always been well, whatever you see. at the surface should look better when you dive. The deeper you dive in, the better things should
0:31Unidentified speaker (UNKNOWN): look.
0:36Brennan Moore: Welcome to another episode of the Nuclear Investing Podcast. I'm your host, Brennan Moore. Today I'm sitting down with Mike Loffer, co founder and CEO of Kairos Power. This one is a real treat. Full disclosure those of you who know me know I'm a big fan and personally an investor in Kairos. This is the exact sort of thing that my firm, Nuclear Capital Partners, has been formed to invest in. Now, one thing, if you usually just listen, I highly encourage you to watch this one on YouTube or Spotify. We have footage throughout, and you really have to see what Kairos is building. It's truly impressive, and you have to see it to appreciate it. Here's my conversation with Mike Loffer. Welcome to the show, man. Honor to have you on.
1:17Unidentified speaker (speaker_0): It's great to be here, Brennan. I'm excited.
1:19Brennan Moore: Yeah, it it's been so great getting to know you and your team and seeing what you're building. And you know, there's so much to cover. I'm gonna try, Mike, to fly through the Cairo story in three or four minutes and give us an overview and then you plug in any holes and correct me at the end, okay? Cause Because I think that'll allow us. We could spend thirty 30 minutes just giving the overview, and I think that'll allow us. to really hop in on some of the details of the story. That works
1:41Unidentified speaker (speaker_0): that works well.
1:42Unidentified speaker (UNKNOWN): A little
1:43Brennan Moore: bit of a lightning round. Okay, Kairos in four minutes. Here we go. Found it in 2016. About 10 years ago, over 600 employees spread across Alameda, California, the headquarters, Albuquerque, New Mexico, the manufacturing hub, and Oak Ridge, Tennessee, the deployment hub. Kairos' reactor, the KPFHR, Kairos PowerFund. power fluoride salt, cooled high-temperature reactor.
2:05Unidentified speaker (UNKNOWN): Its
2:05Brennan Moore: coolant is fluoride salt, a type of molten salt, fuel halut using solid triso. The reactor operates at near atmospheric pressure, which we'll talk about in a bit. Commercial reactor size, 75 megawatts electric. Plant size 150 megawatt electric, which is two reactors, one turbine. What sets Kairos apart? Well, there's a lot of things on the regulatory front commercial, vertical integration, DOE funding. Let's get into it. On the regulatory side, Kairos had the first Gen 4 reactor to receive an NRC construction permit in 2023.
2:40Unidentified speaker (UNKNOWN): On
2:41Brennan Moore: the commercial side, their partners include Google, the Tennessee Valley Authority, TBA, Samsung CT, BWXT, among many others.
2:50Unidentified speaker (UNKNOWN): They have
2:50Brennan Moore: a development agreement with Google to deploy up to 500 megawatts by 2035 to power Google's data centers. They have a power purchase agreement with the Tennessee Valley Authority for the first 50 megawatts of the Google agreement. And this was the first U.S. utility PPA signed to buy power from Gen 4 reactor. Samsung CT, a construction partner, recently invested up to $100 a hundred million dollars in cash and end-kind services. BWXT, collaborating on commercial triso fuel. KPOMata Utility Alliance. This is Kairos and leading North American Utilities, AEP, Bruce Power, Constellation, Dominion Energy, Entergy, Southern Company, and TVA. Vertical Integration, Critical Kairos is manufacturing their own reactor vessels and modules. Graphite. molten salt coolant, triso fuel pebbles, and many other things. And the idea here is to control cost in deployment timelines. They really need to do as much of this as they can in-house. DOE funding. Kairos has received up to $578 million in DOE funding. That was an initial, initial $303 million in milestone-based funding through to the ARTP program. And recently, an additional $277. $275 million announced for Hermes 2. Now, what is Hermes 2? Hermes 2 is Kairos' first
4:09commercial scale reactor targeted for operations as early as 2030, and the power generated by Hermes 2 goes towards the 50 megawatt power purchase agreement with TBA. Kairos has done in-house demonstration projects, engineering test units 1, one, 2, two, 3, three, and Hermes 1. One. More on that later. Their investors include Google, Google Ventures, Samsung CT, DCVC, and Nuclear Capital Partners. One of the most impressive organizations you will see in the space,
4:41Unidentified speaker (UNKNOWN): and
4:41Brennan Moore: one of the quietest. Mike, I love this about how you built it into the DNA or of the organization. We're going gonna to do it first and talk about it later. Mike, fill in the whole holes. What did I miss? Did I get anything wrong or did I miss anything? Off to you.
4:55Unidentified speaker (speaker_0): Well, Brennan, you um you you make it sound a lot like Sunshine and Roses, but behind that is uh 10 years of incredibly hard work from the entire Kairos team. And that focus, I think, is what what sets us apart or at least differentiates us from many in the space, which is which thankfully is crowded. A lot of people are trying. things, but what we're doing is hard. And we've had our heads down trying to do it the way that we think is the right way, and that makes sense to us. And through that process, we've learned a tremendous amount. And I, if you kind of boil it all down, in the early days of Kairos, you know, we were trying to figure a lot of things out about how to do things differently in the nuclear space. And we didn't know if there were even answers to a lot of those questions. And so before we even got to the point. of saying we have a product, I said over and over again, what we're really trying to build is credibility. A lot of excitement, a lot of momentum in the space, but credibility takes a long time and a lot of hard work to earn and unfortunately can be lost very quickly. And so that's what we need in the space in order to deliver. And uh everything kind of boils down to how do we how do we maintain that credibility of actually being able to deliver anything. Because from my perspective, when you translate kind of the need, the demand, which is there, and kind of the challenges of executing and growing and scaling, it's really easy to get out over your skis in this one. And so we've been really
6:15focused on doing it the way that we think makes sense and being able to adapt and be agile. And I'm glad that there are some newcomers who are trying to do it in in the similar way, but proud of the record we've put together. And we've got a 10 years of hard work at this and um, you know, what I think looks like a running start as far as we're concerned.
6:34Unidentified speaker (UNKNOWN): Yeah,
6:35Brennan Moore: that's another thing I I love and respect so much, Mike, is just the honesty. You know, it's like no one said this is gonna be easy. And you're you're very upfront and honest about that. I wanna go back to the early days, 10 plus years ago, when this project was being developed by MIT in partnership. with UC Berkeley and Wisconsin. What made you and your co-founders, Ed Blanford and Perry Peterson at the time, fall in love with this specific technology?
7:00Unidentified speaker (speaker_0): Yeah, so it was it was not a given that this was going to spin out of, you know, was a really exciting period in terms of university progress. Um there was sort of a whole cohort of grad students, I was among them, um, working on this technology. And so sort of doing exciting things that I would say is not really in the normal realm of what what grad students get to do, but we're I'm thankful that we had support from DOE to to ask some of those tough questions. There are two things that I think were really impactful that kind of led to the formation of Kairos. And they were sort of neither of them were a given. The first one was Ed Perr and I were were very close to students to try and find useful analogies in other complex technology fields to find examples of how we might incorporate lessons to do nuclear power in a different way. And over and over again, we we kept coming back to SpaceX as not a perfect model, but probably the most instructive model. SpaceX of 2002 to 2005. 2012 is a is very different than the
8:04Unidentified speaker (UNKNOWN): SpaceX.
8:06Brennan Moore: You are early.
8:06Unidentified speaker (speaker_0): People need to realize that this is a period where, you know, in 2004, they had not successfully launched a rocket, and no one really believed that it was possible for a scrappy startup essentially to do this. This was what governments did, not what startup companies were able to do.
8:23Unidentified speaker (UNKNOWN): So
8:23Unidentified speaker (speaker_0): there was a lot of disbelief that they could even do it at all. And the analogies for the nuclear industry to the aerospace industry are kind of scarily close in terms of complex technology, relatively small volumes, and kind of you really high or unique quality standards. So you're kind of set up for very similar cost paradigm. So we were studying that in real time. And frankly, kind of when we were looking at
8:49Unidentified speaker (UNKNOWN): you know
8:50Unidentified speaker (speaker_0): what the crop of nuclear startups were doing in like the 2010 time frame, it was clear that no one was even attempting to do what we thought was so important to just kind of doing it differently the way that we'd observed from the SpaceX experience. And if anything was clear, is that that that was not going to just magically happen by itself. It takes a deliberate effort to make these things happen. And it's a it's incredible. incredibly hard, you know, it's a huge amount of work. That's sort of not lost on us. The other was a recognition that the technology itself was going to be enabling of a lot of the ideas that we were trying to take from the SpaceX model. So, in particular, the idea of doing a lot of testing and actually getting real live experience with the systems was going. to be important. And that was possible because of an insight that we could really leverage kind of the unique combination of the fuel that you mentioned, the triso coated particle fuel, which is incredibly robust, combining that with the salt coolants, which are is a great high temperature, low pressure coolant. coolants. So you have a low pressure system, which means your vessels are going to be a lot thinner than the thick vessel. vessels that we need for high pressure systems. But the salt is also a backup barrier. So like the safety of our system is
10:09largely defined by that combination, which means that a lot of other things in the system are just not important to safety. And so that means that we can do a lot of iteration, testing, development work on things that are not relevant to safety. Those mean that we can change those parts of the design. as we go through those cycles. And that was sort of the key difference is that the regulatory overlay on nuclear is just very different from what it is for aerospace. And it was clear to us that we had to get this right from the beginning. We had the benefit of having a lot of good connections to people involved early on in the SpaceX experience, including people like Tom Mueller, who led their rocket development. And he said straight out that if space SpaceX had to do what they did for human space flight for cargo, you know, the overlay of the requirements for safety, which are totally appropriate, would not have worked. Right. So so understanding how to bridge that gap was
11:04Unidentified speaker (UNKNOWN): a
11:04Unidentified speaker (speaker_0): challenge we knew we had to mount from the beginning. We started engaging with the NRC back in 2018 and started really developing a lot of credibility behind the safety case. which unlocked the economic potential. So, like those were two things that were kind of converging. And then the availability of kind of committed patient capital has allowed Kairos to grow and focus in a pretty unique way. It puts us in a very fortunate position. Now, 10 years in, we've taken a lot of risk off the table, and we look at kind of partners that we're bringing on board like right now, like Samsung. CNT, BWXT, these are not newcomers in the nuclear space. These are really capable, established players. We understand how we fit into the value chain. And when they come in and they do a deep dive into what we've done, I said building that credibility has been key. And so the philosophy has always been: well, whatever you see at the surface should look better when you dive. The deeper you dive in, the better things should look. And so it's nice to get some um recognition from that from the partners that we're bringing in. But there's still a lot to go. And you know, we've built a solid foundation, but there's still much work to be done.
12:13Brennan Moore: The deeper you dive, the better things should look. It's hard to build it that way, right? Well, yeah, you definitely have to be thoughtful about a lot of things. Hey, let's go back real quick. So high temperature, higher temperature and atmospheric. pressure is a great combination in the design itself. I think the the high temperature is broadly understood that there's other use cases of industrial heat and other things you can do the higher the temperature you go. Help us understand at a high level the the additional benefits to atmospheric pressure from a manufacturing standpoint and why that's such an edge relative to the traditional designs that exist in the US from a manufacturing standpoint.
12:49Unidentified speaker (speaker_0): We're going to dive deep right away here into kind of complexities around supply chain, which is
12:55Brennan Moore: Okay, let's do it.
12:56Unidentified speaker (speaker_0): Something we people in the nuclear field love to love to dive into. High temperature, low pressure is a great combination to work from kind of a from a fundamental technology perspective. High temperature allows you to drive higher efficiency. So you you kind of get more efficiency, more energy out of your fuel if you're driving a higher efficiency. And then you can also use that heat for various kind of industrial applications. Our outlet temperature for our reactor is 650 centigrade. Electricity is our primary market, but the technology itself is could be expanded naturally into different secondary markets. And processed seed is one that's really hard to kind of get off of fossil fuels. And our technology is one that, you know. could enable a lot of opportunity there. Low pressure is also really attractive, and that's sort of what's unique about our system and the use of triso fuel there. In contrast, most reactors that are using this foo form, which is very robust and it's great in a lot of different reactors, but they're using it with helium
13:56high pressure gas, which has some nice qualities. But dealing with high pressure means that you're dealing with really really thick vessels. And you also have to, if you have fuel pebble fuel, these like golf ball size,
14:08Unidentified speaker (UNKNOWN): you
14:09Unidentified speaker (speaker_0): know, graphite and fuel pebbles that are going through the system, they're larger in the gas reactors. They have to go through that pressure boundary to go in and out of the system as you're kind of recirculating through. So there's a lot of operational complexity around dealing with a pressure barrier and just making sure that things don't leak. And then also when you go through kind of the quality and qualification, that pressure boundary, it's actually not really important to the safety, but for us, being able to go with thin wall components opens up a lot of opportunities on the manufacturing side. And that's kind of the other, you know, iterative testing and building things is a great takeaway from the SpaceX experience. The value of vertical integration and in in-house house manufacturing is just so crucial to that early success that we see as the right model to follow. And for us, being able to do that with a low pressure system, it just significantly reduces the potential hazards in those development tests. It allows us to push the system harder and do it in a like a safe environment that's non-nuclear and just reduces the hazard level significantly. And then also just in terms of manufacturing. there are only a few facilities in the world that can make the really thick forgings that are needed for the high-pressure nuclear reactors. I actually saw some of those facilities in South Korea last week. They're amazing, but my reaction is I'm really
15:28thankful that we don't need those. That's
15:31Unidentified speaker (UNKNOWN): sort of my honest
15:32Unidentified speaker (speaker_0): reaction.
15:33Unidentified speaker (UNKNOWN): Glad I don't have to wait
15:34Unidentified speaker (speaker_2): on one of these.
15:35Unidentified speaker (speaker_0): And just dealing with with much smaller components, it opens up a lot of opportunity that I don't think would be available if we had a different technology. So that's everyone in the nuclear space can talk about why they think their technology is great and why they think other technologies have challenges. The reality is that there's good and bad with every nuclear technology, and you have to make the choices. What is sort of unique, and I do idea this thought experiment sort of all the time, our technology is really compatible with this process. And so the tests that we've built, and we can dive into some of these. Some of the explicit goals there are to test the supply chain. And it's, I like to say internally, these are non-nuclear systems. And so a supplier or vendor that can provide what we need for that system, we don't know for sure whether they can make the leap to the nuclear system. But if they can't deliver what we need for the non-nuclear system, there's no way they can deliver what we need for the nuclear system. So it's actually because we're dealing with kind of a new operating regime with high temperature and the salt environment, it allows us to actually filter out a lot of suppliers that are not able to do what we need very quickly. One of the other things that we've learned as we build out kind of the manufacturing capability, it's it sort of it reinforces the value of having these capabilities on the team. So you don't do it all at once. You make decisions about what are the
16:54high value parts of the system that we want to do. So we decided to do graphite machining very early. And then the team kind of learns, well, now this is something we're not dealing with the vendor. They're gonna have to do a lot of tooling. What are we gonna do with change orders if we change the design? It's like, no, we say, I know, I know, I know the person who is going gonna to do this, this tooling, this machining I can go talk to them and say, well, if I wanted to change these things, how hard would that be? And you know, would that delay things and say, yes or no? And like it makes the engineering process like more pure to some degree, rather than like a contractual battle about who's gonna pay for the change orders. And that is I didn't realize that 10 years ago in this process that that was what the value is, but the vendor relationship, like they're they're ones that obviously work out really well. And we have great partners that we continue to work with and are really thankful for. But a lot of what engineering is is actually defining out specifications that protect you in contracting space. So you can say if you didn't follow these specs, you pay for not me, right? And when you just if you're dealing with kairos and kairos on both sides of that equation, it doesn't matter. right? Kairos
18:04Unidentified speaker (UNKNOWN): is
18:04Unidentified speaker (speaker_0): responsible
18:04Unidentified speaker (UNKNOWN): for it. So
18:05Unidentified speaker (speaker_0): it's like it's a that wasn't obvious that that was going to be so much of the benefit from the strategy beyond just the fact that if we get it right, we can control costs much more significantly. We have the infrastructure to do the qualification testing, and then we have efficiencies of our quality programs. program. So we don't have to go out and audit
18:25Unidentified speaker (UNKNOWN): a
18:26Unidentified speaker (speaker_0): huge network. of suppliers and make sure that they are all are following the same quality program. The NRC can come audit our quality program, basically come to Kairos and see almost everything that they need. And they're just a few select vendors, mostly actually raw material providers that they need to go see. So like that's been one of the surprise. Like we've learned about how this process plays out and the efficiencies that we gain from the strategy, but the core tenets of it were there from the beginning. There's just a lot of nuance and like learning that we've had along the way about what it means. And
18:58Unidentified speaker (UNKNOWN): you
18:58Unidentified speaker (speaker_0): know in the space there's a lot of work. The details really matter. And I know that we we don't want to dive down and into all the weeds in the podcast, but having when I say the deeper you dive, the better it should look like those details really matter and you can get hung up on so many little things here that just having that broad base of coverage has been so helpful.
19:19Brennan Moore: Yeah, I want to get into vertical integration in a bit and and all the the full scope of everything that you guys are doing. And also, in my mind, you're really trading CapEx now in exchange for control, which to your point, that control goes a long way for a lot of different reasons. Let's close the loop on fuel first. So the one interesting part of your design. you know, you hear molten salt reactors, but you guys have, you guys are using solid fuel
19:43Unidentified speaker (UNKNOWN): in
19:44Brennan Moore: a molten salt design. Explain in non-technical high level terms, why does that simplify the chemistry of the design itself and why did you go that route to use solid fuel instead of the some of your peers are using fuel that's dissolved into salt, right? So it's very complicated from a a chemistry standpoint. Talk us through that. before we move on.
20:04Unidentified speaker (speaker_0): We have to be very thoughtful about where we take on risk and where we don't want to take on risk. So Brendan, you're exactly right. The uh the salts that we're using were originally developed and explored back in the 1950s and 1960s for reactors that had the uranium actually dissolved into the salt. And so there is no solid fuel. There's no like fuel rod or fuel. pellet or pebble. It's just the uranium is in there. It splits apart, generates energy. It also generates half the periodic table. And so when you're looking at the chemistry in the system, you're dealing with most of the periodic table is in there and is in the salt. That's going to create a much, a much more complex chemical environment. Tremendously, you know, the scientists that were working on this back, mostly in Oak Ridge, Tennessee. figured out a lot of really brilliant ways to manage this. You have to use some specific high-nickel alloys to kind of have more corrosion resistance in the system. What's attractive about those systems is that they're almost like a the chemist reactor. So because you're dealing with a solution, you can do a lot of really fancy things and creative
21:11things by taking things out and putting things in that you can do can't when you have like solid fuel that's stuck in the system. So they are very elegant reactor designs that can do all kinds of creative things. The problem is that those are the those are not the things we're trying to solve for today to get more nuclear power out into the system. We're really trying to solve for cost. And those systems, what they do is,
21:35Unidentified speaker (UNKNOWN): you
21:36Unidentified speaker (speaker_0): know, you can do creative things, but they have you have radioactive. material, your fuel is basically going around your whole circuit. And so the footprint of the things that you have to contain is actually much bigger than even the current conventional reactors. And so for us, we like the salt as a backup barrier. You know, we kind of joke that the tests that they ran back in the 60s are sort of like our reactors with totally failed fuel. So it's like a it's like a severe. accident test, and it was okay, right? So we sort of have have run that experiment and it was okay. In c in the case of our system, we use the most robust fuel, but we combine it with this backup barrier. And for us, that keeps we have to just have to deal with like the normal kind of corrosion products in the salt, but we get rid of the PRAC Pyrrhic table, we get rid of the fuel moving around the whole system. It allows us to shrink dramatically the area of the plant where the fuel is and what is important to safety and allows us to be more innovative and creative and develop new new approaches for the rest of the system significantly without triggering large regulatory reviews. So Hermes one 1 to Hermes two 2 is probably the best example. So we took Hermes one, 1, which we have construction permits for both. It's basically the
22:55construction permits were issued for the same reactor design, but Hermes 1 was basically just dumping heat to the atmosphere. It wasn't doing anything useful with the heat.
23:05Brennan Moore: Non-electricity producing
23:07Unidentified speaker (UNKNOWN): Hermes
23:08Unidentified speaker (speaker_0): 2 in the application is connected to uh a steam system that's basically generating electricity like conventional power. plants. The difference from the NRC's perspective, all those changes were actually pretty large changes in the plant. None of them affected anything that was safety related in the plant. So actually, the only the review was really around do these new systems do anything that's bad to the things that we care about for safety? The determination was no. And so that review time got reduced significantly between the two and kind of validated the point. that, yeah, there really is only this limited set of things that are important. And the really significant point is the fundamental story doesn't change for the smaller reactors to our commercial scale reactors. And so we've scaled up Hermes 2 to be at that commercial scale and basically form the basis of our standardized design. But the safety case is going to look the same because the consequences of these reactors are so low. It opens up a lot of unique opportunities. So, like that interplay is really important. That opportunity is not available with the liquid fuel reactors using the salts, and actually, I think it is uniquely available to Kairos, probably amongst all of the reactor uh vendors and technologies out there.
24:21Brennan Moore: Yeah, it makes a ton of sense. I mean, many of the advanced designs are using triso, especially the micros. And to your point, I think it's because guys are essentially able to check the safety box out of the gate and worry about other problems. I mean, I joke that triso is the most sophisticated and expensive ping-pong balls in the world. You call them golf balls, but it's it's amazing how much is trapped inside of these balls, if you will. And there's there's lots of debate around cost. I mean, that's the debate with triso is not about safety, it's about cost. And you know, the DOE's actually called Triso the most robust fuel on earth. And so I I I think you guys ultimately decided that the safety benefits outweigh the cost. Is that fair?
25:02Unidentified speaker (speaker_0): That's fair. And and to be transparent, when we were thinking about what these reactors might look like, it was not obvious that we would go the route that we did. There was an argument which was legitimate was if triso is expensive, can you leverage the qualities of the salt to allow for,
25:21Unidentified speaker (UNKNOWN): you
25:21Unidentified speaker (speaker_0): know, basically lower quality triso fuel and to lower the cost of triso? And we decided no, we want high quality fuel. We want to take advantage of that. But there are a lot of levers, and the you know, I think one of the things that's been exciting is
25:35Unidentified speaker (UNKNOWN): the
25:35Unidentified speaker (speaker_0): approach that we've taken on the reactor side has translated. really well to other aspects of the technology as well. So we're doing a lot of iteration on the fuel side as well. Some of that comes out of necessity, right? Like we needed 30,000 machine graphite pebbles for our first large-scale non-nuclear engineering test unit. Turns out it's sort of expensive to buy 30,000 machine graphite pebbles.
26:04Unidentified speaker (UNKNOWN): balls. I can't imagine.
26:06Unidentified speaker (speaker_0): The team was tasked then, all right, well, we have quotes on what it costs to buy it. Let's look at what it would take to put the equipment in and install and like and basically do it ourselves. It made sense to do it that way. Um, and then it just became very clear that controlling the quality of the fuel and being able to drive down. the costs from historic triso production processes was going to be really important. And these are not secrets. Like people know generally what the things you need to do to reduce the cost of triso. You want to have a more continuous process. You want to take out some of it can be very labor-intensive intensive to do clean out of equipment for certain parts of the process. Like these are these are known because we're not. the only ones making this triso. What we've done is that we've designed process equipment that enables us to have all these levers. And this is this is what's valuable about the combination with BWXT. They have the experience making triso at scale, but they don't have equipment that has the flexibility that we have our own. And you
27:11Unidentified speaker (UNKNOWN): know
27:11Unidentified speaker (speaker_0): surprises pop up. We talked about vertical integration on the reactor side. We've actually been leveraging that to make a lot of the equipment that we're using for triso. So we're actually vertically integrated not just on the reactor side. We also have a lot of vertical integration on the equipment that we're using to make triso itself. And so like there's value in being able to control and design equipment that's exactly what we need, but then also drive down costs in the infrastructure as well in ways. that were not would not have been obvious at the beginning, but sort of make sense because we have a lot of these flexible machining and kind of modular build capabilities that have kind of come along. And so we look at kind of where we are in fuel. Again, we've taken the philosophy of start small, do your iterations, do your testings, get your learning, and then scale up. And so we're doing that in Albuquerque with basically not with the Halo fuel. We're getting the experience to make triso to make pebbles. But all of that is informing the optimization for the commercial facility. There's real investment there. Like there's tens of millions of dollars of investment in that infrastructure. And the general response is I want to skip that. I want to go straight to the big thing. Um,
28:22Unidentified speaker (UNKNOWN): but I'm
28:23Unidentified speaker (speaker_0): confident that we have saved at least that much and probably a whole lot more on the future facility by working out all those kinks and being able to work through the optimizations there. It's just it is a different approach of doing the staging in that way. It wasn't clear at the beginning that that process was going to be as valuable across the board, but we knew it was going to be ness necessary for the reactors. It also turns out to be really important for fuel and for salt as well, which are sort of our major product of. verticals.
28:51Brennan Moore: Okay, Mike, we'll close the loop on the fuel side. I want to go back to SpaceX. Because as you said earlier, you guys were modeling after after SpaceX before SpaceX was really a thing. Like over over ten years ago. And it's you know, everyone now is calling themselves the SpaceX of nuclear. It's on my nuclear bingo card. I'm creating a nuclear bingo card of it. iterative development and modular. And you know, like SpaceX is on the card. Okay. But here's what it actually means to me. And I want to draw the parallels to Kairos. So iterative development, the SpaceX model, building for first principles, challenging industry norms, a mission-driven founder with long-term vision and passion. This is very important.
29:38Unidentified speaker (UNKNOWN): So
29:38Brennan Moore: the the parallel from your views on this to how Elon has approached it. Vertical integration, which we're already talking about. And then lastly, iterating. Build, learn, repeat, build, learn, repeat.
29:50Unidentified speaker (UNKNOWN): You
29:50Brennan Moore: know, Kairos fits that mold better than anyone I've seen in the space. And the part really, this is what I think is important to understand: the part that most people skip, it's not because they don't want to skip them. It's because of capital and time, but it's the last two. Okay, so they skip vertical integration because it's too capital intensive. You hear this phrase: we're going with the capital light model or going to be the licensing model. So it's really hard to build this stuff that's to source the patient capital to build this stuff on the front end, to serve a useful life of 40, 60, 80, 100 years of a nuclear facility. And then the issue. iteration piece, it's not by choice. Everyone wants to iterate. You know, everyone wants to build, learn, repeat. But the model, because of time, compressed time in the market right now is we're going to iterate on commercial reactors.
30:38Unidentified speaker (UNKNOWN): You
30:38Brennan Moore: know, because it takes several years and significant funding to be able to iterate. And what you guys have done, I mean, you guys have been building intentional, full-scaled hardware for years, right? I mean, you have your demonstration projects, engineering test units, as I mentioned earlier, number one, number two, number three. You poured concrete on Hermes One. Walk them, walk us through. I mean, we don't have to go into the specifics of each, but walk us through holistically what was the purpose of these projects, these internal demonstration projects, and how did these collectively gear you guys up for Hermes 2? your first commercial reactor?
31:17Unidentified speaker (speaker_0): I think one of the most important, and there is a great slide that we have tried to understand, which basically shows a big iteration loop of plan, design, build test, representing the conventional cycle and smaller loops below it. What was clear early on about that process is that. the nuclear cycle was just so long and so expensive was that you you layer in a lot of process and investment protection and risk protection, which is rational, but it's just it's there and it actually makes it much harder to do the innovative thing. And the sad part for nuclear technology is that the people who have the full life cycle experience is so limited because we just have so few success stories of going through that whole process. What you find is that like nuclear experience tends to be concentrated for different parts of the process. And they've been doing like the same thing over and over again, but you lose like you lose. the holistic vision of that whole cycle. And so from our perspective, we went back and forth a lot about the literal analogy. If SpaceX did a Falcon One,
32:36which was a small rocket before they did the Falcon 9, which was their their workhorse, the the big money-making engine for the for the company for cargo and then for human launch. Do we have to do small nuclear first? And like the story has evolved as we've decided through kind of different iterations along the way. But for the non nuclear, like big scale systems that we were building out, it was clear a lot of the value was, and I'm gonna say it was a training exercise for the Kairos team Um, to a large degree to test whether we could do this. And some of the lessons that we got out of that process were not the things that we expected, right? So one, the team went through that whole design, build, operate, and decommission life cycle for you know ETU one, which had 14 tons of salt in it. We ran for, you know, about six months of different testing activities before we before we shut it down. The world's biggest fly test. and we did a lot, like a huge number of firsts on that system. And the whole team got that life cycle. And like when we go back on it, we had like PhDs who were doing night shifts in the
33:51operation because it was who's gonna be the best, you know, best person we have on hand to do these. And you know, we weren't setting up necessarily a full-scale operations organization. We have that now, but it was very much like a learning experience around the way. And like, what do we need for the next one to go through there? So we now have a team that's gone through that life cycle once. We're about to start up the second engineering test unit in Albuquerque. It looks very different from the first one. Um, it looks much closer to what our actual nuclear build system. And all those lessons kind of come along for the ride. Having an organization. I say, I say I like to say this as well. Like Kairos, if nothing else, is an organization that is being built to learn. And that statement has a lot of value. Like we need that in order to do the work that we're doing right now, because we need to learn really fast. But where it really delivers is everyone talks about that learning curve, right? Like how you go from your first of a kind cost to your nth of a kind cost. That doesn't magically happen. And I um it you
34:55Unidentified speaker (UNKNOWN): have to build
34:55Unidentified speaker (speaker_0): you have to build out a team and a set of partners who are actually capable of doing that. And there are a whole set of best practices from the nuclear industry as well about how you can do that well and how it can you can do that poorly. The South Koreans are best in class right now in the world on following. those best practices. And so when we go engage with Samsung CNT, we look very different from the from the types of projects that they have done for nuclear, but we speak a lot of the same language about best practices for and I'm going to say this is going to sound like a paradox. We're talking a lot about iteration, but once you get to that first reactor, you want to standardize design and just do the same thing over and over. and over again. So, how do you allow for that innovation and then you lock it in? This is what I'm fearful for, like this is what I'm nervous about about others in the space. They're kind of going straight to that big design without going through all these loops along the way. There's no way that that first plant is going to be the optimized design. And so when you go to change things, you run the risk of introducing like new firsts first-of-a-kind of a kind. risks into the next build, or do I just live with what I have and try and do it better the next time? That's not an easy decision. We've sort of been through tough decisions on our end as well. Is do we, because when you do that, you're gonna
36:15lose schedule, it's gonna take longer to do it. You introduce more costs, risk, your costs will probably go up before they come down. And you know, for us, building that, building that learning organization. is absolutely essential. But you have to do a lot of work and you need iterations at the right scale. You need investors who understand the value of that process. We got a lot of confusion. Like when we were showing people the first engineering test unit, almost everyone, so you're doing this for the NRC, right? Because why would you do something this big that is not for the NRC? Like, no, no, we're not doing it for the NRC. NRZ. We're doing it for these reasons, and they're mostly internal lessons that Kairos is learning.
36:55Unidentified speaker (UNKNOWN): And
36:56Unidentified speaker (speaker_0): it was like we got a lot of strange looks. Like, why would you
36:58Unidentified speaker (UNKNOWN): put
36:59Unidentified speaker (speaker_0): twenty million dollars into a full facility to do that if you're not if you don't have to like do meet NRC requirements? So it was it was very confusing. But when we look at the scale of the investments for commercial plans, plants, the value, the return on that that twenty $20 million investment for ETU1 is tremendous. And
37:19Unidentified speaker (UNKNOWN): I
37:19Unidentified speaker (speaker_0): wish I could run, like, have like a precise like we saved X dollars by doing this. Um, there's no way of running the counterfactual experiment of how much more it would have cost. But when we look at kind of scales for commercial facilities, nominally kind of a billion dollars for Hermes 2, that's pretty expensive for a facility, but it's less expensive. than doing three or four of them at the same site and bringing that cat and getting all those lessons in before you move to the next one. Then we move to the next 450 megawatts. Then we have a standardized design, we're doing the same things over and over and over again. This is the lesson we've taken from both the combination from SpaceX and the best practices of As nuclear, a fuse them together. And to me, this is controlling destiny is really important. important here. And by integrating all of this, Kairos is not just, you know, we talked about other business models, and there are definitely a wide range of business models in the space. For us, when investors, you included, look look
38:19at look at us, you kind of see the full spectrum of things that need to happen. And you can have two reactions, both are true. One is, wow, that's a lot. You guys have to do a huge amount of stuff to make this possible. The other is the recognition that we're actually being honest and transparent about all the things that are needed. And you know, we're in control. So Kairos is not just the technology provider. We're the manufacturer of equipment. We're the integrator of a lot of systems that are coming together. We're the owner-operator of the first plat. So we have a lot of
38:50Unidentified speaker (UNKNOWN): things that we're going to do.
38:51Unidentified speaker (speaker_0): more control over the project than I think many of our peers do in the space. And I think we're the only ones at sort of the grid utility scale that are doing it in this way. And it's then going back, it's possible because of some of the fundamental choices we made about the technology that enable this, but it's a huge amount of work, right? The general assumption
39:14Unidentified speaker (UNKNOWN): is that the problem is that the problem is that
39:15Unidentified speaker (speaker_0): others can take this work. We can pass it off to an EPC. We can build out a supply chain that are going to do the development work and kind of come along with us along the way. Maybe that will work, but interfaces are messy. And the more interfaces you have, the more the harder it is to execute and coordinate. Kairos has cut out a huge number of those interfaces, but as a consequence a lot of that falls on us. And so it's a lot more transparent. A lot of what you see is there. I think with others in the space, those costs for the first five projects need to be picked up by someone else. And you need to have confidence that they're going to come in and they're going to provide the project financing. And for us, it's kind of all on the table. But the benefit is that it allows us to be more efficient overall in terms of getting to grid scale demonstration. Um and it gives Kairos a lot more control in the process than we need that control to make sure that we're successful. Um that's that's a core tenant of what we believe.
40:13Brennan Moore: It's gonna be a big advantage not doing all this for the first time on Hermes too.
40:18Unidentified speaker (UNKNOWN): So
40:18Brennan Moore: bridging there now that you're really nearing the end of these demonstration projects, what do the next five years look like as you guys are gearing up? for Hermes 2? I mean, uh, it's presumably that that is the core focus. But also, you said you're finishing up ETU 2. And so is it really finishing the demonstration projects, bridging to Hermes 2, or is are there some things that are all happening at the same time as well along the way over the next five years?
40:43Unidentified speaker (speaker_0): When I say, you know, what we're doing is hard, it gets harder as we keep
40:48Unidentified speaker (UNKNOWN): going. Um
40:50Unidentified speaker (speaker_0): a lot of that kind of comes into play in the next five to seven years. We have an incredible team. People are dedicated, they work really hard, right? Like they do all the things that we ask of them and they push um they push to do more, which is which is necessary. The challenge is that when we're trying to do multiple things at once, you're carrying a lot of you're carrying a lot of lot of balls. and keeping everything moving together becomes kind of the major execution challenge. So Hermes 2 is the most important. In many ways, it sort of is the Falcon 9 analogy for us. It is the system that proves our commercial product. We can go through the entire delivery process. We know exactly what the costs are. We have the standardized complete design. We can extract extrapolate from there. The problem is that we can't complete the project and then start on the next one. We because then we have all this manufacturing capability, all the people, all the knowledge is just sitting there. It's going to atrophy. So we need to make sure that that knowledge flows directly into the next projects, which is why our agreement with Google is so important and for. from my perspective, has been thoughtfully structured to enable that transition. So we have to make sure that the build, and it's
42:10not even the whole life cycle of build, right? So we're gonna start like we're doing excavation now in site prep now for Hermes 2. We're gonna start the foundation construction next year. We can't wait for the the three years of construction to be done before we start the next projects. We want to have that knowledge. from the phases of construction flow to the next phases. So we need to have things moving on the next project overlapping. And so that's actually it's a deviation from kind of an ideal case. If you look at like software, let's call that like the you know, the the easiest example in terms of like the iterative process, which you know, agile and a lot of agile development approach for software, you run the cycle. you see how it works, you can go like you get your data very quickly generally from those types of tests. For us, we're not getting that return data. So we need to overlap builds, like the build sequence needs to be continuous. So we just need to be building, building, building, building and keeping all of all of that machinery moving uh in the process. So in the next five years, we need to complete construction of Hermes. 2, get it up and running and operational, and go through the starter process. We also need to have fast following for the next 450 megawatt site for us for the next six reactors. It needs to come like fast
43:29following. So we're working hard to get that lined up right now. Carrying those two projects in parallel is not going to be easy. And so when I kind of look at the high level, and as we've kind of engaged with you and other investors and understanding how we're going to build the financing bridges that are going to be necessary for these next phases, it becomes clear that that overlap puts a lot of puts a lot in there. Um, but it it provides a lot of value and a lot of opportunity because we have
44:02Unidentified speaker (UNKNOWN): a
44:02Unidentified speaker (speaker_0): certain number, we can build out a supply chain that makes sense for that scale and then grow up. The other thing is that we have to keep our promises about what we're going to deliver in check because we're going to very quickly end up in a place where we are capacity limited, particularly if we're talking about the 2035 time period. And so we have to be very direct and honest about how much we can actually deliver and what we're enabling at the stage. And so I can be very bullish about what we're talking about post-2035 because we have all the building blocks. And then I think it's going to be primarily capital and human capacity limited at how much we could actually do and grow and scale. But how much we put in the bucket before 2035 twenty thirty five is going to stretch us thin. And we have to be very thoughtful to make sure we don't get overstretched. That's a hard line to bridge with the hyperscalers who are demanding power now as soon as possible, with investors who say we need to see, you know, the biggest ramp cur commercial ramp up as fast as possible. And finding the right balance between that is um is definitely not easy.
45:09Brennan Moore: The benefit is you have visibility and a commercial partner supporting your first five 500 hundred. megawatt build-out through 2035. Because the the first 500 megawatts through the development agreement with Google, I mean, how many how many development agreements are out there with real off-takers? Yeah. So like that that is also uh a really compelling part of what you guys have. And your point is well taken. I mean, you can't just build everything from for Hermes 2 and stop. And that these we'll we'll talk a bit more about the vertical integration piece in a bit, but yeah, the challenges with all this upfront CapEx is those facilities need to keep moving. So yeah, it'll be interesting how this plays out. Mike, I want to transition to your hubs. We're gonna show Albuquerque and we're gonna show Oak Ridge. Before we do, I'm gonna going to make a statement. I'm curious if you agree or disagree or somewhere in the middle. here, that Hermes 2 will be the first commercial advanced reactor online in the US. Agree or disagree?
46:10Unidentified speaker (speaker_0): I'll add one more caveat. So yes, but I'll say
46:13Unidentified speaker (UNKNOWN): grid scale. I'll
46:14Unidentified speaker (speaker_0): say I'll say grid scale. It's an important caveat. And I think the market needs scalability. Um, and we feel quite strongly that there are different opportunities in nuclear space. There's more than enough demand. Um, but when we we start to see kind of what can work kind of the 50 to 100 is kind of the entry point to grid scale, um, that's really what industrial customers are looking for, what the hyperscalers are looking for, the utilities and the grid operators are looking for, that is the sweet spot there. And I'd say we've got the best shot. I'll caveat it that way. Um maybe a little bit more than more than you were expecting, but I think it's important.
46:55Brennan Moore: Yeah, the one megawatt micros, the smaller micro guys have there's a lot better chance that you see one of those online sooner than grid scale. So that's a great distinction. Okay, Mike, let's go into the hubs. So this is where you just have to see it. I I've already mentioned this before. You really need to see everything that kind of. Kairos is building. So we're gonna show this on screen. And I'll talk over it as well. But you really can't understand everything that Kairos is building, both in Albuquerque and in Oak Ridge, Tennessee, without seeing it. So what you guys have built alone in Albuquerque, I think it's over 180,000 square feet of manufacturing capacity and growing. There's reactor components being manufactured, modular systems, fuel production equipment, molten salt coolant.
47:46Unidentified speaker (UNKNOWN): You
47:46Brennan Moore: know, you show your manufacturing facility with machining, welding, water jet cutting. You're producing key graphite components. The triso fuel lab is there. I mean, this, like I said, you really have to see it to appreciate it. This is where your engineering test units. one and engineering test units two are done. Mike, talk us through Albuquerque in your own words, of everything that's going on there.
48:10Unidentified speaker (speaker_0): Yeah, so Albuquerque, it has grown and I think now has a pretty well-defined scope. But the best way of thinking about it, it is it sort of is the microcosm of all the major pieces that need to come together for delivering the reactor. With the major exception of the civil infrastructure construction. So we have kind of our three verticals are reactor systems, fuel, and salt. And we have essentially the minimum viable supply chain of each of those components demonstrated at scale in Albuquerque, including coming together for the kind of the full-scale integrated testing with the engineering test units. We didn't know exactly what that was going to look like. And so we've sort of built out and added capabilities as they've they presented as being really important. And so we knew from the first engineering test unit, Graphite was going to be really important for scheduling and for
49:10integration of design. So that was one of the first big things that we put in. We knew for the second engineering test unit that we had to take ownership over vessels. And so we used the high base space where ETU was located, it has a divider wall. And that facility was built to move around the ETU vessel. So it also happens to be the most convenient place for us to do vessel work. We have a lot of investment in welding, and we were thinking about putting these systems together and putting that. under Kairos umbrella and air quality programs is really important. And so, and we also like we integrate the facilities. So the facilities are linked. So you're we we we skip kind of are skipping over Alameda. We have smaller facilities here. A lot of the early ideas for components kind of come together and are tested here, and then they're scaled up in the Albuquerque facilities. facility. So really kind of it's where. things come together.
50:04Brennan Moore: Something different and equally impressive being built in Oak Ridge, Tennessee. So 185 acres campus, former it shows a former DOE Uranium Enrichment site, which is really interesting. It's where you're building engineering test unit three, the foundation of Hermes One, 1, the Hermes Two 2 deployment, which you can see the T TVA VA power lines in the background. The construction approach here is unbelievable. I mean, you have a concrete batch plant on site. You have 3D printed molds for concrete. You're doing pre-cast concrete construction. Recently announced the Newcamp Workforce Initiative. Mike, talk us through Oak Ridge in your own words. What did I miss?
50:44Unidentified speaker (speaker_0): Yeah, so if Albuquerque is really where um the manufacturing and you know the testing is coming together. Tennessee is sort of taking things to the next level in terms of really being a unique hub for nuclear construction and operations. And so the facilities that we have there are really geared towards gaining cost certainty around and confidence in different construction approaches, overlaying quality, and really being a test bed. And I think this has been one of the genuine surprises. in the process. Not that this was going to be a really important part of the puzzle, figuring out how to do the construction and the concrete and the integration. We know that civil costs are going to be a big factor of any nuclear facility, but being able to actually apply and grow and expand the iterator iterative philosophy even to kind of the the construction, the civil scale, was not something that we necessarily. expected, but may not be surpr you know, may not be totally surprising looking back in in retrospect. So what we found is a lot of the civil construction in particular, it does have repetitive processes. And so being able to
51:55demonstrate and do the same thing over and over again, um, you can get a lot of that learning by doing it once or twice before you go in and put putting in the in the system. And the common approach is you're just going to do the first of a kind kind of learning in actual build. But we found like we there's a lot of overlap. So we Hermes One Foundation is the first one, nuclear safety-related foundation that used drill piers. A totally common construction practice. But how are you going to do the quality inspections for it? Well, we had a whole bunch of drill piers that we did for the ETU. ETU3 facility and the modular skid integration facility in Tennessee. We were able to use that to pilot. We did a you know a 50-second peer one, one just for practice. And these are things that fit in with our philosophy. Uh, you know, they do add time, they do add some cost, but what you save by having that confidence is really kind of covering those gaps. And then looking forward. Oak Ridge is sort of a unique hub for kind of nuclear talent, nuclear labor. Building off of that, having that kind of flow in really provides us like a hub for regional deployment and on construction operations. And we look to partnerships with University of Tennessee for operations and we look for our broader partnerships with local community, including Oak Ridge
53:14High School. when we're looking at building out the labor pool and the talent force. Um, there's just tremendous opportunity there. And Oak Ridge, Tennessee is a unique place uh in terms of the level of knowledge that the community has for nuclear. Um, I was out there and you have you have campaign signs for city council. They've got a little symbol of the atom on them, right? It's it's just a it's a unique place and and it's tremendous, but the credit to our team. what we're doing is we're having just a good open communication and we're we're delivering on what we say. And that's sort of the thing that matters. People want to know what jobs are coming, what opportunities are gonna be there. And so we really believe that there's a lot of opportunity there and we want to build things in that region and grow there. So we see a lot of opportunity, not just at the site at Oak Ridge, but when we look at the future commercial projects. in my view, the closer they are to Oak Ridge, Tennessee, the better, because we
54:06Unidentified speaker (UNKNOWN): can
54:06Unidentified speaker (speaker_0): go back to those best practices on nuclear construction that we're we're applying to our projects and being able to apply it. It depends on people, it depends on infrastructure. We're setting that all up there and doing the iterative process. So there's a lot of learning that's being embedded in the team that's there. It's it's still relatively small, but it's definitely it's definitely growing.
54:27Brennan Moore: Well, Tennessee has made it clear that they are open for business for nuclear, which is such an important box to check. So on the footprint, I mean, you guys on the West Coast, HQ and Alameda, more central Albuquerque manufacturing, Oak Ridge deployment. Do you find it helpful or challenging at times to be spread across the country from from west to east?
54:47Unidentified speaker (speaker_0): The honest answer is a perfect world. It'd be great if there was be one location where we could put everything. That would make life easier. It would make plane travel a smaller part of all of our lives, which which we would all appreciate. The unfortunate reality is that that there is no single location where it makes sense. So I think defining clear visions for and roles for each of the spaces and then how they interface. And
55:11Unidentified speaker (UNKNOWN): you
55:11Unidentified speaker (speaker_0): know during the pandemic we got a lot better at using kind of the video integration. So when we do startup operations for ETU too, we've got kind of remote control rooms with all the data here in Alameda. We've got we're setting up a one of those in Tennessee. So the responsible engineers who are kind of overseeing the testing of their systems,
55:33Unidentified speaker (UNKNOWN): they
55:33Unidentified speaker (speaker_0): don't have to sit in the Albuquerque control room. They can sit here, they can see all that the they day. actually Actually, can access. the data on their laptop wherever they are as long as they have a secure connection. So we have the ability to have tremendous access. And so we got flexible,
55:49Unidentified speaker (UNKNOWN): but
55:49Unidentified speaker (speaker_0): we realized that a lot of that benefit that we got from the virtual was cashing in on the investment that we made on the FaceTime before the pandemic. And so having people flow back and forth, seeing the manufacturing, happening for their systems, being there for the testing, understanding it, like that all builds the personal connections that are really important. And it's not always fun or easy going back and forth, but it's it's absolutely necessary. And each site has a distinct role in the overall picture, which is important as well. But building a cohesive, kind of unified, kind of one Kairos between all the sites. is something we put a lot of effort into just building the right culture behind all of the sites.
56:31Brennan Moore: Yeah, and different talent at the different hubs too, I think is important. Mike, let's talk about the business model. So licensing versus integrated, you know, there's there's different approaches here. You know, the and the licensing model really being
56:47Unidentified speaker (UNKNOWN): you
56:47Brennan Moore: get a reactor design licensed, you license that to a builder, you collect the licensing fee, maybe you sell fuel over the life of the project. You know, it's not right, not wrong, not different. You know, the pitch is that this is a capital light model. Little capex at the parent level with the builder basically carrying the the build risk and the capex risk. But does capital light also mean control light? I'm asking you a rhetorical question because we already talked about this. So I guess the real question is how do you control deployment timelines and cost if you're not responsible for building the actual project?
57:24Unidentified speaker (UNKNOWN): You
57:24Brennan Moore: know, that that's something I ask myself all the time. Like it seems rosy and interesting, but how do you actually control both of those critical variables if you're not responsible for building the thing?
57:35Unidentified speaker (speaker_0): The honest answer is that the vendor of the technology is not in control of the project execution or schedule. That falls to ultimately the owner. And so they're the ones who are going to be they're responsible for the financing. So they're responsible for the money. And they're going to therefore take ownership over the project risk and make sure that they have the controls in place and the authorities and management that makes them comfortable, right? That's the historical model, and that's that's the reality. In Kairos' case, utilities are are needless to say, you know, by mandate and often by by regulation and law, they have to serve the interests of the service territories and the populations that they serve. They have to do it in an economically efficient way, which makes them conservative. So it's not it's not their fault. It's just the way that they're forced to be and how they have to think and operate. So what they're going to do in terms of first of a kind build is i is just going to be very slow and very,
58:35very cautious. In our case, we we recognize that, you know, there are going to be learnings in the first builds that are going to be important. We want to face those kind of head on with open eyes. For us, to go through a conventional utility process, you sort of have to put on the best-looking appearance that the project doesn't have risk. And that's because in many cases they can't take on that risk. Now, the hyperscalers have changed that because they see unique value and they need the capacity. And in most cases, are willing to pay higher rates for the attributes that they can get from nuclear. But they're still, it's going to come down to who controls uh the first string. strings on those first projects. For us, Kairos is doing that for Hermes too. That's a substantial amount of investment capital that's required for that project. But when we look at it, we have to look at kind of what's necessary, how long is it going to take, how much investment is going to require to get to grid scale demonstration. And I would argue
59:35because you can see a lot of that in the Kairos model, we
59:38Unidentified speaker (UNKNOWN): would
59:39Unidentified speaker (speaker_0): make the case that we have both the fastest and the most capital efficient pathway to that grid scale demonstration. Now, that doesn't mean it's it's the cheapest from the perspective of the nuclear vendor. But when you look at all the costs all in, who's going to put up a couple of billion dollars for the first multi-unit projects and take on that risk versus us where we are saying we're going to do a single Hermes 2 demonstration unit. and that will serve as the reference design for the nuclear island for our topical plants, get that standardized design in place, and then do it over and over and over again. And ultimately, we control that destiny. It means we have to be thoughtful about when we go fast and when we need to take a little bit of time to make sure we're doing it right. Um, But Kairos is in control of that that schedule. And so we can we can make deliberate. choices along the way about where we may want to be a little bit more conservative or where we may want to be a little bit more aggressive because the cost-saving opportunities make a lot of sense.
1:00:38Brennan Moore: I imagine it's a delicate balance constantly between what you build internally and what you partner on. You know, and I like you guys that did a very thorough analysis all the way through the the value chain of what you're gonna do in house and what you're gonna partner on. And I'm sure that's ongoing as as well as
1:00:57Unidentified speaker (UNKNOWN): And maybe the
1:00:57Unidentified speaker (speaker_0): the surprise twist, we spent a lot of time early on talking about SpaceX. I mentioned that they're diff they're a different company now than they were twenty years ago. That's true because they're doing all the stuff with like data centers and and infrastructure, but they're also a different rocket company now than they were twenty 20 years ago. And when you have such, and sort of Apple sort of falls into this mold too, when you have such capability and knowledge over the design and the supply chain, you don't need, you actually don't need to do as much of it in in later stages as you may have had to do early on. And so SpaceX has a much broader supply chain on the rocket side now than they used to. But they because they have the capability to pull anything in-house, it gives them a lot of leverage and that they can really keep costs down. And they know exactly how much it should cost and they can control margins and they they have full visibility, right? So you can do things in a different way later on in the process. What Kairos is doing
1:01:57is say we need to take ownership over a lot of scope and a lot of supply chain, a lot of manufacturing. now. Otherwise, we might lose control over the project execution, and we don't want to do that. We want to keep keep everything on track. This is what we have to do. But in doing that, we also see what are the high value, higher margin parts of it. So, what is going to be the core business of Kairos in 10 years is going to be a subset of the things that we're doing now versus saying we're just going to have to continue to scale everything up forever. And my perspective is that there's going to be a lot of capital investment in scaling up all of the infrastructure needed to deliver a lot of reactors. We have to create the demand in the market and demonstrate that we can deliver. I I'd rather that Kairos has a smaller piece of a much bigger pie than own, you know, the entirety of a of a smaller pie. That's a much better outcome. for Kairos, for investors, for the market, in terms of being able to get more out there. It's a very, it's a very relevant analogy that we think about a lot. So how do we create the biggest, the biggest pie? And Kairos is going to get a good chunk of it, but there's plenty to share. And I think that is definitely true.
1:03:09Brennan Moore: The market has made it clear the benchmark is commercial deployment. The benchmark is who's going to get to commercial deployment. the fastest. And so, you know, balancing that along the way. Mike, I know you I know we're we're running out of time. I want to hit sizing real quick and I want to hit the regulatory path before we wrap up. So I'm going to start with sizing. You know, many argue that we need to build as many large scale reactors or large reactors as possible. And the only domestic large design on the menu today is Westinghouse. Westinghouse's AP 1000. And so I I've said for a while, innovation really needs to make its way to the gigawatt scale facilities. So, you know, let's look at your plant, for example. Like we'll show a rendering of the Hermes 2 plant. To me, it looks like a basketball stadium. You know, it's like a it's like a very big, sophisticated basketball stadium. And so the question is to get to a gigawatt, do you build, you just build several of these. let's call them basketball stadiums, side by side?
1:04:06Unidentified speaker (UNKNOWN): Or
1:04:06Brennan Moore: do you eventually get to where you just build a massive football stadium with more centralized facilities under one roof? What is the real vision for Kairos on that front? Is it's is it really better to keep building these smaller plants and just build more of them? And maybe eventually you're sharing one turbine with more reactors? Or to ultimately innovate up the size curve towards
1:04:29Unidentified speaker (UNKNOWN): a
1:04:30Brennan Moore: Kairos 1000 over time, or a gigawatt-size Kairos facility.
1:04:35Unidentified speaker (speaker_0): The answer can evolve over time. So I think where we are right now, this is a very distinct choice that we've made. Our reactor size in terms of power output is pretty much the same as New Scales. Like we're 75, they're 70. 77. The difference in the architecture is putting a lot of reactors into one large building is a very different, it's a very different construction project for the infrastructure. And so we've made a choice for the early deployment. One reactor per building is going to be the most efficient way to scale
1:05:11Unidentified speaker (UNKNOWN): the
1:05:11Unidentified speaker (speaker_0): learning that we get from Hermes 2
1:05:13Unidentified speaker (UNKNOWN): to
1:05:13Unidentified speaker (speaker_0): a standardized design. build that nuclear island. Like the building is the building looks a little bit larger and maybe is not telling. Part of that is in order to standardize the design, we don't put anything substantial underground. Right. So in other designs, a lot of stuff ends up underground. And so the footprint of what you see above ground may look smaller. In our case,
1:05:37Unidentified speaker (UNKNOWN): in
1:05:37Unidentified speaker (speaker_0): order to standardize a design that can work across multiple sites, you do that by keeping everything above the foundation the same. And then the foundation design may change based on the local site geology. But keeping that standard design, that's going to be the really efficient way. And then the actual nuclear part of the system is actually pretty small relative to the overall footprint of the the building right now. And there are a number of reasons of factors about kind of why. we have to account for space right now. And you know, no one ever really says, you know, I regret making it a little bit bigger in terms of access and maintenance. So there are a variety of things that play in there. But being able to standardize and execute that nuclear island over and over again, I do think that there's a point in the future, probably about 10 years out from now, where you know we do have to take a look. Have we learned enough about the delivery and the design and the execution where we can go to kind of a Rev 2 of the system? And the issue is that when you change the architecture, you change that, you introduce, you basically will go and introduce a lot of first-of-a-kind
1:06:43new costs into the system. Landing at a good price point and coming down the learning curve at our scale is good. We know. we have validation on the customer side that this 50 to 100 megawatt sizing is a great increment in terms of balancing scale, how demand grows for large industrial facilities, including data centers, like and the availability. So you you're not taking off and setting up backup like backup power and availability. It all works well for optimization at that scale for the customer. The sort of 150 to 600 megawatt range increment for the site is a great scaling for utilities. Grid operators love like 300 megawatt increments at a time.
1:07:26Unidentified speaker (UNKNOWN): A
1:07:27Unidentified speaker (speaker_0): gigawatt coming off the system is a big demand that has to be met. And so there's value in that. It just has to be cost effective in terms of the cost per megawatt. And I think time will tell. what the right pathway is going to be. But again, I think because Kairos is the central hub and the owner of so much of the architecture, particularly for the nuclear island, we have visibility into what the cost drivers are. And we know what are the levers we're trying to pull right now. We also what are the levers that we want to save for the future because we either don't know enough or we have to we don't have the bandwidth to address them right now. And being thoughtful about that is going to be,
1:08:07Unidentified speaker (UNKNOWN): you
1:08:07Unidentified speaker (speaker_0): know, those decisions are not always easy. I mentioned the learning curve as being key and Kairos is being an organization that's meant to learn. Their learning curve is cruel because it's totally agnostic about all of the the sweat, blood, and tears that it takes
1:08:22Unidentified speaker (UNKNOWN): to to actually
1:08:23Unidentified speaker (speaker_0): learn. All it cares about are the dollars, right? And and like like it's so much work to actually realize that we have general vision about kind of what the major storyline is going to look like, but the actual learning is going to come from individual engineers in the field and teams working together, being like, how are we going to do this better? How are we going to execute better and drive out cost and schedule from the system? It's a lot of hours, a lot of time, a lot of a lot of patience to be able to actually realize that. And part of what is both central but also maybe a little bit scary about the iterative approach is, and I believe this very deeply, you don't know all the lessons you're gonna learn as you go through the process. If you did, you wouldn't have to do the iterations in the first place. And so you have to realize as a world where we're gonna learn we may learn things that we did not anticipate, and we may have to make adjustments along the way based on that learning. And that can be a little bit scary, but you know, when we balance everything, that's actually central is that we have to be eyes wide open and be able to balance what's a what's a good opportunity and risk that we want to address now and what can we save for later.
1:09:38Unidentified speaker (UNKNOWN): Yeah.
1:09:38Brennan Moore: well it it's a great bridge to the regulatory side. And we'll close with this topic. The re NRC and the DOE pilot program is you know, that's you guys pretty much you're a 10-year-old company. You basically went down the NRC path from the beginning. And I think that's had a lot of positives for Kairos, and I'm sure it's also created some challenges. But a lot of decisions along the way were geared towards want to have a commercial reactor, grid scale reaction. reactor, we need to get a permit from the NRC and ultimately an operating license from the NRC. I'm curious, so if you were starting Kairos under the twenty twenty five executive orders and the new DOE framework, what would you have done differently? Like what's what's one thing top of mind? I not the whole playbook. Like what's one thing top of mind that you guys would have done differently had you had the renewed support that came out in the last year and a half. from the EOs.
1:10:28Unidentified speaker (speaker_0): We have a bias towards scale. And I think that the NRC pathway, having a pathway through the NRC is going to be really important. And people are working on this to be able to use data from facilities and have that. Like there's thought behind this. And DOE has a lot of experience regulating nuclear facilities. So they have they do have a lot of capability there. Our thoughts, like when you when you actually go up to larger scale systems, it's not obvious that DOE is going to be better or faster in any way than NRC. For smaller systems, yes. I think it's a lot and it's a lot more analogous to the types of facility that DOE has a lot of experience with. And they manage those facilities exceptionally well. For us, I think
1:11:13Unidentified speaker (UNKNOWN): there
1:11:14Unidentified speaker (speaker_0): probably are areas that we would have pushed harder on, basically saying maybe we can maybe we can move the regulatory expectations a little bit in terms of being appropriate. There's a lot of conservatism that that is put into the process. And maybe maybe we would have pushed back on some some of those conservatisms early on that we just kind of laired in and said we're going gonna to have to live with this right now and we can fight those we can fight those battles another day. They're not worth it right now. I will say that our approach has always been there isn't there is actually a flexible NRC licensing regime that applies for reactors that are smaller, but that have lower risk profiles. It's just used for tests and research reactors, not for commercial power reactors. So
1:12:00Unidentified speaker (UNKNOWN): by
1:12:01Unidentified speaker (speaker_0): following that pathway for Hermes 1 and Hermes 2, we've actually been sort of setting the groundwork for everything that we would expect to include for the commercial licenses. And right now, what the NRC is doing for new frameworks for low consequence reactors, which they're calling the Part 57 framework, it's a new pathway. It actually is very familiar to us because it looks a lot like what we've been doing for Hermes 1 and Hermes 2. So we actually the pressure on the NRC to reflect on where it's adding value and where it can be more efficient in its process has benefited from, I think, the high quality technical content that Kairos has been working with the NRC for the last eight years on and getting them comfortable with this that, yeah, we we can do things in a more efficient way. Reactors with lower consequences can be put in different frameworks. framework. I think we've set the stage. And so, you know, I
1:12:54Unidentified speaker (UNKNOWN): people
1:12:54Unidentified speaker (speaker_0): ask like, what do I worry about most? You know, there basically four things that I think are always going to drive our critical path. It's how long it takes to design and build the systems, making fuel, making salt, and going through NRC licensing. I go through a whole day worrying about each of them, probably a little bit, you know, and and it's, you know well, does depending on what hour is, you know, where my where
1:13:17Unidentified speaker (UNKNOWN): where
1:13:17Unidentified speaker (speaker_0): my concern is the highest. But most of the time these days, the NRC is not actually top of the list in terms of my concern for critical path. I think that we have a responsibility on other factors to do it right. And I think we can now look at 12 to 18 month review times on the NRC side as being very achievable. And when we fit that into the construction schedule, it lines up and it gives us not a lot of time. There's there's there's never a lot of margin on on the schedules here. But saying that, you know, three or four years ago, even, you know, the idea that we could expect a 12 to 18 month review would have gotten a lot of people saying, no, you gotta do two years would have been aggressive and you have to put in contingency there. So we can definitely go in now and I think say, yeah, we're we're less concerned about the NRC being a barrier. Part of that is is because of the pressure on them to reform their process and be more efficient in their reviews. But a lot of it is basically building off the foundation of all the topic reports that we have approved, which is going to set the stage for easier reviews as well. It's like kind of getting chapters approved and like different parts of the process approved before you actually go in. with your
1:14:27final answer. I think there's been a lot of progress. I think the NRC is often like the target of a lot of like animosity. And ironically, I find myself in a position actually defending the NRC a lot more these days than I would have expected. But the staff there, they have a very hard job to do. People need to appreciate that. They have to make decisions about what they feel is meeting the requirements for being. safe. And they take that role very seriously. And people should not treat that as a light responsibility when you have to be the person who signs off on saying whether something's going to be safe or not. That's a tremendous responsibility. What we've tried to do is to make it easier by presenting a case that is technically strong and makes make sense, and it's paved the way for a lot of opportunity that you don't have to do things the way that you used to just. because that's how they've always done.
1:15:16Brennan Moore: The DOE has played a huge role. And the pilot program, it was it was helpful and it was very important. I think one thing to that I I like to try to make clear and clear up is the perception, the public perception, including in a lot of the venture community, is that the leaders did the pilot program and the winners of the pilot program went critical.
1:15:35Unidentified speaker (UNKNOWN): You
1:15:35Brennan Moore: know, so you have Antares, Balor, Bowler, Deployable, Alo, Ok. Oaklo Isotopes so far, I think a few more in the pipeline that went critical. And it was it was great, great for the industry, great initiative. It's important to understand though, there's a lot of notable names that didn't participate. I mean, Kairos, BWXT, G Vernova, Holtec, TerraPower, Westinghouse, X Energy. I mean, all these guys, these are big names. You know, like these are bellwether bellweather names. already on the path to commercialization through the NRC. And that the NRC requirements not going away. So I think it's it's really helpful framing and just tying it back to the iteration. I mean, we talked about engineering test units one, two, three, Hermes one, you guys have done. I mean, it sounds like Kairos has effectively been running its own pilot programs internally for years. Is that is that fair to say?
1:16:26Unidentified speaker (speaker_0): We've been doing sort of our version of it. I mean I think
1:16:29Unidentified speaker (UNKNOWN): Yeah,
1:16:29Brennan Moore: exactly. A little more tailored, right? Like a little more tailored versions.
1:16:32Unidentified speaker (speaker_0): And not to always go back, but like if we go back to the SpaceX, I I think that
1:16:37Unidentified speaker (UNKNOWN): the
1:16:37Unidentified speaker (speaker_0): DUE pilot program is really meant to act as an accelerator for companies in earlier parts of their life cycle. And I think it it it can be effective there. So going all the all the way in here, it's like, how do you get to Falcon One faster, right? Is sort of the analogy. But Falcon One, you know, the fourth attempt in 2006 to human space flight in 2020, that's 14 years. That's a that's a long time. And like for nuclear, we have to build that bridge with the regulatory overlay on top of it.
1:17:13Unidentified speaker (UNKNOWN): And
1:17:14Unidentified speaker (speaker_0): scaling is not easy. I think that's just something that that needs to be acknowledged. It's not impossible, but going to larger systems introduces new complexity. But you have to, you have to find that balance of how big do you need to go. And as I like to point out, economies of scale are very real, right? Like building a large gigawatt-scale gigawatt scale light water reactor is almost always going to be more economically efficient. than building a small light water reactor. You're sort of in your lane on the technology. And if we can deliver 300 megawatt light water reactors at the same dollar per megawatt hour as a gigawatt scale plant, the engineers and the team that pull off that deserve huge amounts of credit. Like
1:17:58Unidentified speaker (UNKNOWN): that is
1:17:59Unidentified speaker (speaker_0): like fight fighting the economies of scale is a constant battle. We're dealing with like we have a different technology, so we're sort of in a different lane. But when you go to smaller size, you're gonna get killed by the civil infrastructure costs first. Yeah.
1:18:14Unidentified speaker (UNKNOWN): And then
1:18:14Unidentified speaker (speaker_0): as you go down really small, the fuel costs are just gonna become really dry. And then as you go really small, like the megawatt scale, operations and maintenance and staffing are just going to like you have to have really compelling stories. about how you're going to drive all those down really significantly. It's easier to like there's always the for us, there's even that pressure. And I sort of used to joke that you know the right scale for Kairos was always like the overlap of the smallest reactor that a customer would buy and the biggest reactor that we were confident we could deliver. I'll I'll note that it's not guaranteed that that's overlapping. Um right. So right now we have that. It really is this sort of 75 megawatt reactor, 150 megawatt power block of two reactors, and sort of a 450 megawatt scale site as sort of it's the sweet spot for everybody in this process and for scaling up on the US grid. That's what the system needs. And we're very focused on trying to deliver that as quickly as possible. The NRC is going to have to be a part of that process. And bringing them along for the ride is going to be easier than trying to either fight them from the beginning or say we'll deal with them later. That's been a part
1:19:24Unidentified speaker (UNKNOWN): of our
1:19:24Unidentified speaker (speaker_0): philosophy all along.
1:19:26Brennan Moore: Certainly. Well Mike, this has been a lot of fun. Mid-2030s, 2035. What does success look like for Kairos? Hermes2's Army Two's online. All the Google facilities are online. What does success look like for Kairos? And time's flying. We're getting there. I
1:19:41Unidentified speaker (UNKNOWN): know it's
1:19:41Unidentified speaker (speaker_0): not it's
1:19:42Unidentified speaker (UNKNOWN): not that
1:19:42Unidentified speaker (speaker_0): far away. It's like right around
1:19:43Unidentified speaker (UNKNOWN): the
1:19:43Unidentified speaker (speaker_0): corner, practically speaking. No, twenty thirty-five success is basically we have completed multiple early sites. We've got probably a gigawatt or so on the grid. We have a couple of gigawatts of projects under construction in the pipeline, and we're basically building building. building. And that includes all the infrastructure, supply chain, scaling it up. But we know what our costs are. We know that we're cost competitive in the US. And we're actually starting to think about expanding or we're already in the works of expanding to secondary markets like international deployments and processing. And and at that point we know what the unit cell needs to look like. We just need to build the Lego over and over again.
1:20:25Unidentified speaker (UNKNOWN): That's
1:20:26Unidentified speaker (speaker_0): that's that's the dream.
1:20:27Brennan Moore: Well, it's gonna be fun to track, man. Final question. I love to ask people, especially as busy as you are, how you keep going? What's one thing that you do consistently to keep your mind and body sharp? As it is so demanding, your your daily schedule right now, I imagine. What is one thing you do consistently or try to do consistently?
1:20:47Unidentified speaker (speaker_0): Family and Kairos are sort of the only things that really exist in my life. Um, so there's not really time for anything else. Being outside is really healthy. So it makes me sad when we lose that uh that hour of light in the afternoon with the daylight savings time. So being outside is always a good thing. Getting out for walks, you know, skiing in the winter, being outside as much as possible is uh it's good for the soul.
1:21:10Brennan Moore: I love it, man. Well, sincerely, thank you so much for the time, Mike. This was educational. and a lot of fun. And good luck, man.
1:21:18Unidentified speaker (UNKNOWN): Thanks,
1:21:19Unidentified speaker (speaker_0): Brennan. It's been great.
1:21:21Unidentified speaker (UNKNOWN): Thank
1:21:21Brennan Moore: you for joining another episode of the Nuclear Investing Podcast. Be sure to like, subscribe, and follow. And if you got something out of this one, share it with someone trying to understand nuclear energy. See you next time. Brennan
1:21:32Unidentified speaker (speaker_2): Moore is the founder and managing partner of Nuclear Capital Partners. All opinions expressed by Brennan and podcast guests are solely their own opinions and do not reflect the opinion of Nuclear. capital partners. This podcast is for informational purposes only and should not be relied upon as a basis for investment decisions. Nothing in this podcast is an offer to sell or a solicitation of an offer to buy any security. Nuclear capital partners, its affiliates, and investors may hold positions in companies discussed on this podcast.