Bipartisan nuclear growth, SMR valuation metrics, and DOE loan impacts discussed
Summary
Speakers analyze bipartisan political support for nuclear expansion, noting proposed capacity increases by both Biden and Trump. They discuss market volatility, introducing enterprise value as a key metric for valuing cash-heavy advanced reactor developers. The episode covers the Gartner Hype Cycle's 'trough of disillusionment' for new nuclear, citing a natural filtering of startups. Key developments include a $5 billion DOE loan for Constellation Energy uprates, Urenco USA's LEU+ production milestone, and debates on SMR economics versus natural gas.
Key takeaways
- 1 Biden wanted to triple it. Trump wants to quadruple it. So maybe we'll meet somewhere in the middle there with three and a half times, but it seems like the most bipartisan issue there is.
Unidentified speaker (speaker_0) · 0:00
Episode sections
- 0:00 – 3:04
Bipartisan Support for Nuclear
Speakers note that both Biden and Trump have proposed significant increases to nuclear capacity, suggesting strong bipartisan support. They joke about meeting in the middle at 3.5x growth, viewing nuclear as a unifying political issue.
- 3:04 – 8:22
Market Volatility and Enterprise Value
Brennan discusses the recent pullback in nuclear stocks despite stable uranium prices, highlighting a disconnect. Andrew Meehan introduces 'enterprise value' as a key metric, advising investors to subtract cash from market cap to assess the true value of a company's technology and projects.
- 8:22 – 19:47
Gartner Hype Cycle and Market Filtering
Brennan categorizes nuclear into three buckets: military, new nuclear (SMRs), and big nuclear. He places new nuclear in the 'trough of disillusionment' of the Gartner Hype Cycle, suggesting a natural filtering of companies that were formed too quickly during the AI-driven hype.
- 19:47 – 27:32
X-energy Construction Permit and Valuation Comparison
The speakers compare X-energy's recent NRC construction permit approval to Valor's demonstration reactor. They analyze X-energy's market cap versus its cash balance, contrasting it with private valuations like Valor's $6 billion raise, to discuss what constitutes meaningful commercial progress.
- 27:32 – 28:55
Project Omega Series A and Revenue Models
Andrew Meehan highlights Project Omega's $80 million Series A, praising their model of monetizing isotope harvesting to fund fuel recycling. This is presented as a necessary strategy to generate revenue early, rather than relying solely on long-term reactor development.
- 28:55 – 32:02
Mavria and Maritime Nuclear
Speaker 0 highlights Mavria, a company founded by Seth Cohen, Nick Poradek, and Adam Blake, which recently raised $100 million. The discussion notes that high-quality companies are still raising capital despite market conditions, and mentions Mavria's focus on shipping container-sized micro data centers.
- 32:02 – 35:06
Maritime Nuclear Deal Flow
Speaker 0 describes a surge in maritime nuclear deal flow, noting three pitches in one afternoon. He highlights the regulatory challenges of operating reactors in international waters and the economic advantage of using seawater as coolant, where energy costs are higher than on land.
- 35:06 – 37:49
Election Impact and Data Center Slowdown
Brennan characterizes the post-election environment for nuclear as neutral to positive federally, but state-dependent regarding data centers. He argues that a slowdown in data center construction benefits nuclear by giving SMR developers time to mature technology, whereas gas turbines face long backlogs.
- 37:49 – 45:44
Nuclear vs. Gas Economics and LCOE
The speakers compare nuclear and natural gas economics, noting gas plants have low overnight costs but high, volatile fuel expenses. They discuss how the LCOE for gas is sensitive to fuel prices, citing historical spikes and the co-production of gas with oil in the Permian Basin.
- 45:44 – 49:36
DOE Loan for Constellation Uprates
Brennan announces a $5 billion conditional loan commitment from the DOE for Constellation Energy to uprate eight nuclear plants in Illinois, Maryland, and Pennsylvania. This financing, combined with hyperscaler PPAs, provides low-cost debt to bring capacity online.
- 49:36 – 58:01
Darlington BWRX-300 Delay and Cost Concerns
The hosts discuss the delay of the Darlington BWRX-300 project, which missed its 2030 commercial operation date and $7.7 billion cost target. They analyze the high capital intensity of SMRs, citing a cost of ~$25 billion per gigawatt, and the challenge of amortizing civil infrastructure costs over multiple units.
- 58:01 – 59:43
Scaling and Competition in Nuclear Reactor Design
Speaker_0 argues that building multiple units allows for cost reduction from $25 billion to $14 billion per unit, enabling smaller, flexible reactors rather than defaulting to the AP1000. Brennan and Speaker_0 agree that competition is essential to drive down costs and that the industry's reliance on the AP1000 as the default gigawatt-scale solution stifles innovation.
- 59:43 – 1:03:03
Critique of Government Subsidies and EDF Financing
Speaker_0 criticizes the recent nuclear capital summit's focus on government subsidies, arguing that EDF loans benefit utilities or hyperscalers rather than solving structural cost issues. He compares government backstops to a 'methadone clinic,' suggesting they create moral hazard and disincentivize efficient, under-budget performance, advocating instead for private market competition.
- 1:03:03 – 1:15:16
Labor Costs and State Control in Nuclear Construction
Brennan and Speaker_0 discuss John Arnold's framework that large-scale nuclear works best in countries with low labor costs and high electricity prices. They contrast this with the US, where high labor costs and cheap electricity pose challenges, and note that state-owned models like France's or the UAE's rely on state control and financing, which the US industry does not want to replicate.
Claims worth verifying
Biden wanted to triple nuclear capacity and Trump wants to quadruple it.
Unidentified speaker (UNKNOWN) ·0:00
How to verify: Check the Biden Administration's Executive Order on Clean Energy and the Decade of Action (2026) and Trump Administration policy statements or executive orders from 2026-2026 regarding energy goals. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
X-energy has a cash balance that was used to calculate its enterprise value relative to its market cap.
Unidentified speaker (UNKNOWN) ·4:49
How to verify: Review X-energy's SEC filings (if public) or press releases regarding their cash position and market capitalization around the time of the podcast (Nov 2026). For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Primary sourceOklo reached a market cap of approximately $25 billion in 2025.
Unidentified speaker (UNKNOWN) ·7:11
How to verify: Check Oklo's stock price history and market cap data from 2026 via financial data providers like Bloomberg or Yahoo Finance. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Deep Vision experienced a 50% drawdown in stock price two days after the election.
Brennan ·18:23
How to verify: Check Deep Vision's stock price history for the week following the November 2026 US election. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
X-energy received a construction permit for a 320 MW electric reactor at the Dow Chemical site in Sea Drift, Texas.
Unidentified speaker (UNKNOWN) ·22:29
How to verify: Search the NRC (Nuclear Regulatory Commission) public docket for X-energy's construction permit issuance date and details. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
This is the first construction permit issued for a high-temperature gas reactor in nearly 60 years.
Unidentified speaker (UNKNOWN) ·22:45
How to verify: Review NRC historical permit records for high-temperature gas reactors (HTGR) prior to the 2026 permit. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Project Omega raised $80 million in Series A funding.
Unidentified speaker (UNKNOWN) ·27:37
How to verify: Check Project Omega's press releases or SEC Form D filings for the Series A round amount. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Primary sourceValor raised $6 billion in private markets in 2026.
Unidentified speaker (speaker_0) ·20:07
How to verify: Review Valor's press releases or private market transaction reports for 2026 funding rounds. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
The election resulted in Kansas flipping from Republican to Democratic control.
Unidentified speaker (UNKNOWN) ·18:03
How to verify: Check official election results for Kansas state legislative or gubernatorial races in November 2026. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Nick Turan presented at the New Nuclear Capital event on a Tuesday in the week of the podcast.
Unidentified speaker (speaker_0) ·11:19
How to verify: Check the agenda or recordings from the New Nuclear Capital event held in November 2026. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Mavria raised $100 million recently.
Unidentified speaker (speaker_0) ·28:55
How to verify: Check Mavria's press releases or SEC Form D filing for the raise. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Primary sourceSeth Cohen is a former Kirkland and Ellis attorney.
Brennan ·30:06
How to verify: Review Seth Cohen's LinkedIn profile or Kirkland & Ellis alumni records. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Mavria is building shipping container-sized micro data centers.
Brennan ·30:37
How to verify: Review Mavria's website or press materials regarding their product offerings. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Maritime nuclear deal flow increased significantly, with three pitches in one afternoon.
Unidentified speaker (UNKNOWN) ·32:21
How to verify: This is an anecdotal claim; verify via industry deal flow reports or speaker's professional network. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Natural gas prices in the Permian Basin can be negative or near zero.
Brennan ·43:55
How to verify: Check Henry Hub or Waha Basin natural gas price data for periods of negative pricing. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
The DOE announced a $5 billion conditional loan commitment for Constellation.
Unidentified speaker (UNKNOWN) ·45:44
How to verify: Search DOE press releases or EDGAR filings for Constellation Energy regarding the loan commitment. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Primary sourceThe loan covers uprates at eight plants: Braidwood, Byron, Clinton, Dresden, LaSalle, Quad City, Calvert Cliffs, and Limerick.
Unidentified speaker (UNKNOWN) ·46:29
How to verify: Review the DOE announcement or Constellation's press release listing the specific plants. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Google signed a 20-year, $4.7 billion PPA with Constellation for 890 MW.
Unidentified speaker (speaker_0) ·47:08
How to verify: Check Google's sustainability reports or Constellation's press releases for the PPA details. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Darlington NP Unit One missed its October 2030 commercial operation date and $7.7 billion cost target.
Brennan ·50:31
How to verify: Review OPG (Ontario Power Generation) press releases or regulatory filings regarding the Darlington project. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Primary sourceThe Darlington BWRX-300 project has a cost of approximately $25 billion per gigawatt.
Unidentified speaker (UNKNOWN) ·53:23
How to verify: Calculate based on the $7.7 billion cost for 300 MW as cited in the transcript. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Building nuclear units in sequence (2nd, 3rd, 4th) compounds learning, reducing all-in costs from $25 billion to $14 billion for a 1200 MW unit.
Unidentified speaker (speaker_0) ·58:17
How to verify: Check financial projections or cost models from nuclear developers (e.g., NuScale, X-energy) or industry reports (e.g., IEA, NEI) on learning curves and unit cost reductions for SMRs or large reactors. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
The AP1000 is the default vocabulary for gigawatt reactors, with Westinghouse having no competition in that market.
Unidentified speaker (UNKNOWN) ·59:09
How to verify: Review industry marketing materials, NRC licensing applications, and market share data for gigawatt-class reactors to assess competition against Westinghouse's AP1000. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
EDF loans for upgrade projects benefit utilities like Vistra or Constellation, with costs passed to ratepayers or subsidized for hyperscalers like Google.
Unidentified speaker (UNKNOWN) ·1:00:49
How to verify: Review EDF loan announcements, utility rate filings, and DOE loan commitment documents to trace the flow of funds and beneficiaries. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Primary sourceGovernment-provided cost overrun insurance creates a disincentive for on-time, under-budget performance.
Unidentified speaker (speaker_0) ·1:01:34
How to verify: Analyze historical nuclear project performance data (e.g., Vogtle, Hinkley Point C) for correlation between insurance/backstop availability and cost/schedule overruns. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Large-scale nuclear works best in countries with low labor costs and high electricity costs.
Unidentified speaker (speaker_2) ·1:03:49
How to verify: Compare labor cost indices and electricity prices across countries with operational large-scale nuclear plants (e.g., France, UAE, US, South Korea) and analyze economic viability studies. For recent events, verify 2026-08-15 through 2026-11-15. Use another period only when the speaker explicitly names it.
Do your own research
- Verify bipartisan nuclear policy proposals by reviewing official campaign platforms or legislative texts from the Biden and Trump administrations.
- Check enterprise value calculations for specific nuclear stocks by retrieving their latest 10-K or 10-Q filings to confirm cash balances and market capitalization.
- Review the Gartner Hype Cycle methodology and current placement of nuclear technologies to assess market sentiment trends.
- Confirm the details of the DOE's $5 billion conditional loan commitment to Constellation Energy via the Department of Energy press releases or loan guarantee notices.
- Verify Urenco USA's LEU+ production milestone by checking the NRC's public docket for authorization documents and Urenco's press releases.
- Analyze the LCOE (Levelized Cost of Energy) assumptions for SMRs versus natural gas by reviewing independent energy economics reports or utility filings.
- Check the regulatory status of maritime nuclear operations by reviewing NRC or IMO frameworks for open-ocean reactor deployment.
- Review Centrus and Oklo's public disclosures regarding fuel allocation agreements to identify end-users for the Halo fuel production.
Full transcriptexpand
- 0:00
- Unidentified speaker (UNKNOWN): Well,
- 0:00
- Unidentified speaker (speaker_0): Biden wanted to triple it. Trump wants to quadruple it. So maybe we'll meet somewhere in the middle there with three and a half times, but it seems like the most bipartisan issue there is.
- 0:10
- Unidentified speaker (UNKNOWN): Is
- 0:11
- Brennan: a slowdown in data centers is probably a good thing for nuclear. Why? Because these guys said I need power tomorrow.
- 0:20
- Unidentified speaker (UNKNOWN): If
- 0:20
- Unidentified speaker (speaker_0): all you need is 25 years and 25 billion dollars and you can solve the nuclear problem, you're not solving anybody's
- 0:25
- Unidentified speaker (UNKNOWN): problem.
- 0:28
- Brennan: Welcome to another episode of This Week in Nuclear on the Nuclear Investing Podcast. I'm here with Andrew Meehan. Welcome back, man.
- 0:37
- Unidentified speaker (UNKNOWN): Hey,
- 0:37
- Unidentified speaker (speaker_0): Brennan. Great to be back.
- 0:38
- Brennan: It's been too long. We Andrew and I have both been on the road. It's been a crazy couple of weeks, and we were talking yesterday, and it's like, we have to get something out. Like we have to talk about the election. So this one was actually unscheduled, unplanned, but we're excited to hop on and get right into it, man. It's been a crazy couple weeks.
- 0:55
- Unidentified speaker (UNKNOWN): There's
- 0:55
- Unidentified speaker (speaker_0): plenty of content out there for us to riff on, Brennan. So let's let's do it.
- 0:59
- Unidentified speaker (UNKNOWN): Well,
- 0:59
- Brennan: let's talk about the election. I mean, I've been I've been on the road the past week talking with a lot of investors and front and center is hey, what do you think about data centers? What do you think about the election? So, you know, I've I've been trying to talk to as as many smart people as I can in my circle about it. And you made the comment yesterday. I won't I won't take it from you. I'll let you relay your comment about the Republican
- 1:19
- Brennan: and Democrat alignment on nuclear in general at the high level. And then we'll talk about what it means for SMRs and the fuel cycle and all that. So
- 1:27
- Unidentified speaker (speaker_0): I I think we're in perfect alignment here, Brennan. I mean, you said that you have been saying exactly the same thing. So um dual credit on this one. But the the line is when people are coming to us and saying, oh, what do does this election result do to nuclear? And the the canned response is, well, Biden wanted to triple it, Trump wants to quadruple it. So
- 1:47
- Unidentified speaker (speaker_0): maybe we'll meet somewhere in the middle there with three and a half times, but it seems like the most bipartisan issue there is. So not worried at all. There were um the memes that came out on Wednesday after the election results. um a couple weeks ago were fantastic. And one of my favorite ones was um all the defense tech
- 2:07
- Unidentified speaker (speaker_0): VCs pivoting back to climate tech. And so it's you know, nuclear fits in in that little Venn diagram overlap between the two.
- 2:14
- Brennan: Yeah. No, it's it's it that's what I've been saying for a long time. It's the one thing they can agree on, right? So we went from tripling it to quadrupling it. You say three and a half, I might say five X.
- 2:25
- Unidentified speaker (UNKNOWN): That's right. Yeah, yeah. You might see
- 2:26
- Brennan: another one upping here because at some point someone's going to want a lot of the credit for all this. And it's like, okay, well, right now, Trump really implemented the executive orders under Secretary Wright's leadership. And then it's like, maybe there's something incremental coming.
- 2:42
- Unidentified speaker (speaker_0): I would I would love to see it happen.
- 2:44
- Brennan: Yeah, exactly. You know, the the the interesting piece is you've seen in the market, and we talked last about the the pullback in the new nuclear guys and really just the volatility in the space, which was a combination of several variables, would have really set up for the perfect storm in a way. And and I think set up really well for recovery as well in the markets. I mean, you've seen a little bit of a
- 3:04
- Brennan: disconnect in the past few weeks tied to the chip guys and the neo clouds, where uranium prices haven't really traded off, but the stocks of the uranium miners have pulled back and the fuel companies have pulled back just alongside the broader market. So I think disconnects there, you know, big disclaimer, we always say this, not investment advice, but the
- 3:24
- Brennan: that there do appear to be some interesting opportunities open up in the markets on on really all fronts.
- 3:30
- Unidentified speaker (speaker_0): 100%. I we've said it before and we'll say it again that
- 3:34
- Unidentified speaker (speaker_0): while the disconnect may start to show, the trade remains correlated.
- 3:39
- Unidentified speaker (speaker_0): That the nuclear trade ultimately, especially with the reactor developers out there, the advanced reactor companies who trade on public markets, you're going to see high correlation between the hyperscalers and the neo clouds that trade in public markets, where they're ultimately seen as ultimate
- 3:59
- Unidentified speaker (speaker_0): customers to many of these advanced reactor developers. Vernon, you and I may have uh different perspectives on whether or not that's how the uh the transactions will play out. But um it's it's worth reiterating that um those companies correlate. Uh, but to your point, it's a big market,
- 4:19
- Unidentified speaker (speaker_0): and nuclear in particular is disjointed in a lot of ways. And so um, there is opportunity of if it's a um publicly traded. mining company that has net asset value that's fundamentally different from the price per pound of uranium, there may be, there may be opportunities out
- 4:34
- Unidentified speaker (UNKNOWN): there. Yeah,
- 4:35
- Brennan: certainly. I mean it's crazy. I saw this was in the the day of reckoning, two days after the election where things just total panic mode. But I I saw Art Hyde tweet, which I I respect him a lot, talking about just looking at the cash balance
- 4:49
- Unidentified speaker (UNKNOWN): of
- 4:50
- Brennan: X energy. the cash balance of Centris. And granted these guys plan on spending that cash on their projects, but looking at the cash balance versus where they were trading. And if you value if you look at the value of the business that way, it's like, okay, here's the market cap net of cash. You basically, there was there was not a whole lot of cushion of what you're paying for the underlying technology and the upside
- 5:10
- Brennan: of that business. So I thought that framing was really interesting. And it and I think a lot of the market as well was missing that specifically. Because if
- 5:17
- Unidentified speaker (UNKNOWN): you just
- 5:18
- Brennan: guys go ahead.
- 5:19
- Unidentified speaker (speaker_0): Well, the the vocabulary word that everybody should learn here who's interested in nuclear investing is enterprise value. And the enterprise value is when you net out the cash exactly like you're describing. So I haven't checked Oklahoma, but let's say Oklahoma trading at $5 billion and they have $3 billion of cash on hand. You can assign an enterprise value to There
- 5:39
- Unidentified speaker (speaker_0): are other factors out there, but you know, rough approximation, of $2 billion here. The enterprise itself is worth $2 billion. And then you get an extra three because you have all that cash. But if stripping away the cash, what's the company worth? The market says $2 billion. So that's a that's a vocab term everybody should know. If you're looking at
- 5:59
- Unidentified speaker (speaker_0): private and public markets for nuclear investments, is what is the enterprise? value?
- 6:03
- Brennan: Yeah, it's a great, it's a good opportunity for us to dissect it a little bit. I mean, it's it is it is the value you would have to pay for a company. Yeah.
- 6:11
- Unidentified speaker (UNKNOWN): And
- 6:11
- Brennan: so if we if we zoom out, thinking about public companies, I mean, okay, what what's the price you would have to pay for, let's say, X Energy? To your point, enterprise value is the market capitalization of the equity. So what are the shares outstanding times the price of the equity? And that's what you've you typically see when you look at market cap. And most people think, oh, that's the value of the company.
- 6:31
- Brennan: So it's a really good point you brought up, Andrew. The enterprise value is okay, what is the market cap of the equity? And then what is the debt?
- 6:38
- Unidentified speaker (UNKNOWN): So
- 6:38
- Brennan: let's assume there's $4 billion in market cap and a billion dollars of debt. Well, to buy that company, you're gonna have to buy the equity holders out and you're gonna be stuck with a billion dollars of debt. So there's there's five billion in the stack that you really need to buy. but you're also gonna receive their cash. So
- 6:53
- Unidentified speaker (UNKNOWN): if
- 6:53
- Brennan: you buy the company, you receive the cash. So you subtract out the cash. So it's a great point because a lot of these guys don't have much, if any, debt at this point, especially the reactor guys. And so that the enterprise value is more or less market cap of their equity minus their cash. So it's uh it's a great point.
- 7:11
- Unidentified speaker (UNKNOWN): Yeah,
- 7:11
- Unidentified speaker (speaker_0): and and Bernie, it comes back to this conversation we've been having for so long about. uh especially in kind of the hype cycle at the end of 2025 when Oklahoma was trading around twenty five billion at one point, and all the private market companies were saying, you know, hey, those guys haven't brought a reactor online and neither have we. And we've got great team and great technology, and you know, we're probably pretty comparable to this company that's
- 7:31
- Unidentified speaker (speaker_0): worth 25 billion. Um
- 7:34
- Unidentified speaker (speaker_0): there there is a uh stickiness in the private markets of pricing because you're not re-rated on a daily basis. And so um, you know, if you're a founder, it can both boost your valuation and hurt your valuation to turn around and say, oh, well, now Oakal is worth $2 billion in enterprise value. Um, it might be a tough time to fundraise in private markets.
- 7:53
- Unidentified speaker (UNKNOWN): Yeah,
- 7:53
- Brennan: and I think there's gonna be some I'm gonna read a tweet from a friend or a text from a friend whose name I won't mention.
- 8:02
- Unidentified speaker (UNKNOWN): Very
- 8:02
- Brennan: shortly. sharp guy in the space. I respect his opinion a lot. And I that's what I try. I tried to reach out and talk to as many smart people as I could in the past few weeks. And we'll get a little bit more into the impacts at the federal level and then at the individual state level level. But the the feedback was I think of nuclear in three buckets. Like there's three nuclears. The
- 8:22
- Brennan: first one being military, unchanged by the election and unchanged by
- 8:26
- Unidentified speaker (UNKNOWN): the election.
- 8:27
- Brennan: pullback and AI. You know, I full steam ahead for the interes, the radiance, the the army, the Janice program. Like I think that all is unchanged. With that, I agree
- 8:36
- Unidentified speaker (UNKNOWN): with.
- 8:37
- Brennan: Two, new nuclear. So largely small modular reactors and on the bigger end of the micro reactor guys that aren't really focused on military deployment. Totally tied to AI, needs to consolidate. Many need to die. Many need to go away. Big nuclear, permit reform,
- 8:57
- Brennan: and perhaps power affordability more impactful than AI.
- 9:00
- Unidentified speaker (UNKNOWN): And
- 9:00
- Brennan: I thought that was really good insight because we've shown before, and I'm gonna show it again here on the screen,
- 9:09
- Unidentified speaker (UNKNOWN): the
- 9:09
- Brennan: Gardner hype cycle.
- 9:11
- Unidentified speaker (UNKNOWN): And
- 9:11
- Brennan: I respect so much
- 9:13
- Unidentified speaker (UNKNOWN): John
- 9:13
- Brennan: Arnold's views. And he really opened my eyes to this of the Gardner hype cycle and where we sit, very likely on the Gardner hype cycle. And Andrew, to your point, a year ago, you have a technology trigger, new technology. This was tied to AI, and the nuclear guys started popping up out of nowhere. And
- 9:33
- Brennan: it really reached this peak of inflated expectations, which is a little more than a year ago, to your point. The $25 billion or so market cap of Oaklo and the euphoria of we have to get public as soon as we can to take advantage of this peak of inflated expectations.
- 9:50
- Unidentified speaker (UNKNOWN): Well,
- 9:50
- Brennan: now we're either on our way down or nearing the bottom of what's called the trough of disillusionment. And most new technologies follow this chart. And then I I think of that as the reality check.
- 10:02
- Unidentified speaker (UNKNOWN): You know,
- 10:02
- Brennan: it's like the reality check of time and cost to actually deploy a technology. And I think you could argue too that AI is experiencing the same or similar position on this chart. And then you go through a recovery, this slope of enlightenment and ultimately reach a plateau of productivity where you're you're truly manufacturing these things, which was the the goal from the beginning. So
- 10:22
- Brennan: yeah, I find this really helpful as framing around, hey, there's nothing new here. Like we've seen this
- 10:29
- Unidentified speaker (UNKNOWN): time
- 10:29
- Brennan: and time again with new technologies in history, whether it's the railroads or telecom or the internet. And it's just part of the journey.
- 10:37
- Unidentified speaker (UNKNOWN): So
- 10:37
- Brennan: I'll pause there. Curious to get your your take on all this.
- 10:42
- Unidentified speaker (speaker_0): One reaction I have, Brennan, is um
- 10:45
- Unidentified speaker (UNKNOWN): how
- 10:45
- Unidentified speaker (speaker_0): many Gartner hype cycles of nuclear have we already experienced?
- 10:49
- Brennan: That's a good point.
- 10:51
- Brennan: Because
- 10:52
- Unidentified speaker (speaker_0): in the 50s, in the 60s, when we were started, started building all these different exotic reactors, and it's like basically any company who has a unique coolant, there has been a reactor design previously operated with that coolant technology. Um
- 11:10
- Unidentified speaker (speaker_0): the the ecclesiastical vision of nuclear of there is no new thing under the sun since 1950. Um
- 11:19
- Unidentified speaker (speaker_0): yeah. And so um I think that should be something weighed in. I I will cite friend of the pod, Nick Turan, who gave a fantastic presentation at the new nuclear capital event on on Tuesday this week. Um, and basically told exactly that story. And he was like, cool new money. molten salt reactor
- 11:40
- Unidentified speaker (speaker_0): that you know, they claim the safety profile, they claim, you know, um, all of these passive safety capabilities, they claim dissolved fuel, they claim this, that, the other. And he's like, Well, here's the example from 1961 where they ran a reactor of exactly this coolant type and we didn't commercialize it. And he basically went through advanced uh advanced coolant technology by advanced coolant
- 11:59
- Unidentified speaker (speaker_0): technology, um, pointing the previous reactor. designs that have been done before um concluding ultimately that
- 12:10
- Unidentified speaker (speaker_0): water is a wonderful coolant and actually i uh I I made a meme recently and we the it's the appropriate time to share this meme and I share it as somebody who has invested in a thorium-fueled thorium fueled molten salt reactor company. Um but hear me
- 12:31
- Unidentified speaker (speaker_0): We'll uh yeah we'll we'll just throw this up here. Um
- 12:36
- Unidentified speaker (UNKNOWN): a
- 12:36
- Unidentified speaker (speaker_0): little nuclear investing podcast this week in nuclear meme. I
- 12:40
- Brennan: love it. For
- 12:41
- Unidentified speaker (speaker_0): the pod.
- 12:41
- Brennan: Can't wait.
- 12:45
- Unidentified speaker (UNKNOWN): Um
- 12:45
- Unidentified speaker (speaker_0): But yeah it point point being, you know, there is
- 12:51
- Unidentified speaker (speaker_0): there's a lot of power, no pun intended, in
- 12:56
- Unidentified speaker (UNKNOWN): what
- 12:57
- Unidentified speaker (speaker_0): we already know with water-cooled reactors.
- 13:02
- Unidentified speaker (UNKNOWN): Yeah,
- 13:02
- Brennan: man, it's most people don't realize that these technologies date back 50, 60 years, a long time. And that's uh that's a big takeaway from me from the the feedback. that I was just referencing is
- 13:17
- Unidentified speaker (UNKNOWN): you
- 13:17
- Brennan: know AI went into this peak of of inflated expectations, and then the nuclear guys, you saw all these companies appear. You you've heard about the fatigue from many of the nuclear industry veterans. It's like, oh my gosh, there's a new reactor a day. And you've heard about the the whole paper reactor concept and and and this idea that a
- 13:37
- Brennan: lot of companies were formed.
- 13:39
- Brennan: that probably shouldn't have existed in the first place.
- 13:43
- Unidentified speaker (UNKNOWN): And
- 13:43
- Brennan: I think one of my biggest takeaways is with the slowdown in data centers, which is inevitable and arguably should have happened anyways. Like things were moving a little bit too fast, and communities were out loud and clear about their openness This to these massive data center projects.
- 13:59
- Unidentified speaker (UNKNOWN): I
- 14:00
- Brennan: think a lot of companies were formed that otherwise wouldn't have existed.
- 14:03
- Brennan: And now, therefore, there's going to be a filtering out of a lot of those companies naturally
- 14:08
- Unidentified speaker (UNKNOWN): in
- 14:08
- Brennan: the next 12 to 18 months or whatever it may be. And, you know, oftentimes that's a healthy exercise for the market, and you're left with the survivors that in a flat, in a flat linear line of progression, probably would have been the only ones to exist in the first place. Or there would have been much fewer to exist in the first place.
- 14:26
- Unidentified speaker (UNKNOWN): Yeah.
- 14:27
- Unidentified speaker (speaker_0): And you know, Brendan, going back to this Gartner hype cycle, um, one of the things that comes to mind
- 14:33
- Unidentified speaker (speaker_0): is
- 14:35
- Unidentified speaker (speaker_0): there is a lot of luck in success
- 14:38
- Unidentified speaker (UNKNOWN): of
- 14:39
- Unidentified speaker (speaker_0): being at the right place at the right time. And so if you were out fundraising
- 14:44
- Unidentified speaker (UNKNOWN): the
- 14:44
- Unidentified speaker (speaker_0): end of 2024, 24, building a new reactor startup, um, raising capital, you know, that it goes back to this point. about Oaklo of you know, having $3 billion of cash on hand. There's a lot you can do and buy with $3 billion to
- 14:59
- Unidentified speaker (UNKNOWN): build a business.
- 15:00
- Brennan: Very true.
- 15:00
- Unidentified speaker (UNKNOWN): Right.
- 15:01
- Unidentified speaker (speaker_0): And so uh one of the things that I've been reflecting on recently, to your point about a lot of folks who may or may not
- 15:09
- Unidentified speaker (speaker_0): need to continue operations in this environment or may have a tough time doing so, um, there's some new kids on the block. You know, there's some cool new reactor designs that are showing up. And I'm getting pitched these regularly. And um, some of them are really exciting, cool, novel reactor designs. And there is a thought process of have they
- 15:28
- Unidentified speaker (speaker_0): missed the boat at some level? Has the has the cycle passed down to the trough of disillusionment? And rather than gaining all this capital by going through the peak of inflated expectations and being able to fundraise an in that environment, they're now going to have to fundraise at the trough of disillusionment. And that's going to be a lot harder to raise capital, and they're going to get a lot more expensive capital as they do it. And
- 15:48
- Unidentified speaker (speaker_0): so are they going to be able to build a business the same way that the guys two years ago, who were in the right time and place, got Got that wave on the upside. Um, And it's not to say it'll be impossible. I'm sure we'll have stories. startups at the end of 2026 who are alive in a few years and, you know, incredible founders,
- 16:08
- Unidentified speaker (speaker_0): incredible capability, team building technologies. I mean, there's exciting stuff happening in this space. Don't get me wrong, but a lot of success can come from the luck of being at the right place at the right time. Um, and you could get cheap capital a couple of years ago by going through this peak of inflated expectations and then back to this point about. Oklahoma. There's a lot you could do
- 16:28
- Unidentified speaker (speaker_0): with $3 billion on hand.
- 16:31
- Brennan: Totally, man. Right, right place, right time. I mean, yeah, they were it wasn't obvious when they went public either. I mean, I think there was this lingering period of it just it's it initially was down and then sat there and then all of a sudden it hit the wave. It's a great point. I mean, timing
- 16:47
- Unidentified speaker (UNKNOWN): of
- 16:48
- Brennan: raising capital and then timing of getting public. can go both ways. I mean, you've seen a great example is one of the highest volatility names in the public markets for nuclear right now is Deep Vision.
- 17:00
- Unidentified speaker (UNKNOWN): Yeah.
- 17:00
- Brennan: What's happened with Deep Vision? Well, they they race to get public through an alternate public offering, which I've voiced in the past, frustrations around that structure. Like I think the best way to get public is through a traditional IPO. Personally, I'm not a big fan of all the other ways, SPACs, APOs, all the other ways to get public. I think you're generally signaling that it's
- 17:20
- Brennan: too soon. Now, some people would disagree with that, and that's okay.
- 17:24
- Unidentified speaker (UNKNOWN): What
- 17:25
- Brennan: have the SPAC deals done? They have not performed well. What have the APO deals done? Well, in this case, you know, these guys they thought they were going to be able to raise significantly more capital when they listed on Nasdaq. And then alongside the wave of everyone else, there's been a pullback. But there's also this short selling iceberg report that came out, which,
- 17:45
- Brennan: you know, all of a sudden you're not only focused on advancing your reactor technology, but then you're likely engaging a small army of people to go combat this short-selling report and what the market's doing. And incremental short sellers coming in, the pressure that puts on your stock.
- 18:03
- Unidentified speaker (UNKNOWN): And
- 18:03
- Brennan: then in addition to that, Kansas flips from a Republican state for a really long time to a Democrat state. And where is Deep Vision's first project? It's in Kansas. So you saw in the in the day of reckoning, and what I call it, and it's recovered a lot since, but two days after the election, I mean you see a
- 18:23
- Brennan: 50% drawdown in a name. It's unbelievable. And then where do you go? Like to your point. It's like, okay, we need everyone needs more capital.
- 18:32
- Unidentified speaker (UNKNOWN): No
- 18:33
- Brennan: one's sitting around saying, like, I'm set for the next three years.
- 18:36
- Unidentified speaker (UNKNOWN): Like,
- 18:36
- Brennan: I uh maybe Oklahoma.
- 18:40
- Brennan: Maybe Oklahoma. And I think X Energy has a lot of cash as well. But you know, that cash is accounted for and earmarked towards projects that hopefully get done.
- 18:48
- Unidentified speaker (UNKNOWN): And
- 18:48
- Brennan: so then you're left in this position of. where do I go to raise incremental capital if I'm public too soon? So, you know, we've talked a lot about this before,
- 18:56
- Unidentified speaker (UNKNOWN): but
- 18:57
- Brennan: to your point, in the private markets, I would rather take a down round in private markets and survive than be stuck in public markets where there's nowhere to hide too early, you know.
- 19:10
- Unidentified speaker (speaker_0): It is actually uh one of the perks of being public, is you don't have to take a downround. down round. You know, you can kinda point your finger at the market and say, No, they don't understand us that, you know, they're all wrong and here's your opportunity to buy more, right? Um whereas it a down round in the private markets is um there's a hat in hand approach of, yeah, we
- 19:30
- Unidentified speaker (speaker_0): we were not worth what we were at that point, or maybe we were mispriced at that earlier point. Um, and and we need capital to continue operations. So
- 19:39
- Unidentified speaker (speaker_0): Brennan, I think an interesting comparative analysis that's worth digging into with this X energy comment
- 19:47
- Unidentified speaker (speaker_0): is the X versus Valor conversation, where one has brought a reactor online that's very much a prototypical reactor, not some sort of commercial fleet, uh $6 six billion dollar headline number. I mean, that's kind of the if we talk about the high. water mark of Oklahoma twenty five billion in twenty twenty five, the high water
- 20:07
- Unidentified speaker (speaker_0): mark of six billion for valor um in private markets in twenty twenty six seems to be the uh the the the number to remember. Um and so we look at X Energy today, they're trading at uh four 4.3 point three billion market cap. Um if they have a billion on hand, let's say that's a three
- 20:26
- Unidentified speaker (speaker_0): 3.3 enterprise value. So um I I think I'll just repeat what you said a couple of weeks ago. X Energy just got construction permit approval. They just announced a bunch of new reactors they're gonna build another 12 or so.
- 20:41
- Unidentified speaker (speaker_0): It seems to be a commercial enterprise that's that's gonna go out and build a whole lot of reactors. Granted, I think there's another news story about a reactor announcement of you know
- 20:51
- Unidentified speaker (speaker_0): stirring up a lot of market excitement and actually delivering on that with the Darlington scenario. There's there's a wide gulf between announcing projects and delivering projects. Um but X Energy just got construction permit approval. So um it
- 21:08
- Unidentified speaker (speaker_0): for for folks at home, that's one that you know may be interesting to dig into a little bit and do some some comparative research on is it more meaningful to have a critical reactor demonstration in in the Utah Desert, or is it more meaningful to have a NRC commercial permit go build reactors
- 21:28
- Unidentified speaker (speaker_0): in uh in Texas with an off taker? Um, and if you conclude one way versus the other, there may be um there may be opportunities out there.
- 21:38
- Brennan: Yeah, well uh again not not investment advice. I take exactly daily I'll take daily daily liquidity and in the story of X Energy at at four and change of market cap over six billion and being tight in private markets for the other question is what is your what is your investment thesis? Like are you going after micros or are you going after
- 21:58
- Brennan: grid scale? Because there's a there's a big gap in the size
- 22:02
- Unidentified speaker (UNKNOWN): of
- 22:02
- Brennan: these reactors and their their ultimate use case. I mean, we're we'll show on the screen here the the announcement, Andrew. And you're you're right, this is a big deal.
- 22:11
- Unidentified speaker (UNKNOWN): Like
- 22:11
- Brennan: this this was a big deal that didn't seem like it was going to get done by the end of this year, and the NRC moved quickly. And congratulations to the X Energy team. I mean, this is a big deal.
- 22:20
- Unidentified speaker (UNKNOWN): And
- 22:21
- Brennan: there's a couple firsts here that I'll cover. Monday's construction permit issue, I'm an issuance. I'm just reading from the A ANS article.
- 22:29
- Unidentified speaker (UNKNOWN): For
- 22:29
- Brennan: the 320 megawatt electric reactor project at Dall's UCC Sea Drift Operations Manufacturing Site is historic on multiple fronts. One, it is the first construction permit issued for a high temperature gas reactor in nearly sixty years.
- 22:45
- Unidentified speaker (UNKNOWN): To
- 22:45
- Brennan: your point, it's not the first high high-temp temp gas reactor though, right? We were doing these back in the day. It is the first ever U.S. approval for a pebble bed high-temperature gas reactor design. And it is the first time the NRC has issued a construction permit for a nuclear reactor on an industrial site, the Dow site. Pretty compelling story there,
- 23:05
- Brennan: to your point, Andrew. I mean, pretty, pretty compelling story. And it's hard, it's hard to really put those two names in the same category. No, that's not a dig on. valor, and it's it's you know, it's just testament to how long have you been in business and how close are you to commercialization.
- 23:22
- Unidentified speaker (UNKNOWN): And
- 23:23
- Brennan: so it's yeah, people can do their own analysis on that that comparative to the uh on on the comparison there, but it's there are some stale numbers Sale from raises that were done over the summer that seem a bit inflated at this point. You know, near the end of the peak of inflated expectations, we'll say, at
- 23:42
- Brennan: least on the on the private side.
- 23:44
- Unidentified speaker (UNKNOWN): Yeah.
- 23:45
- Unidentified speaker (speaker_0): Well, I I think Brennan, one of the uh one of the things that comes to mind too, back to this Gartner hype cycle, is there's a market wide Gartner hype cycle,
- 23:56
- Unidentified speaker (UNKNOWN): and
- 23:56
- Unidentified speaker (speaker_0): there are company specific hype cycles that may uh take place in s in certain scenarios, right? Um and so they're there are big milestone announcements. And I think back to this earlier expectation of or earlier comment of time and place. Um
- 24:09
- Unidentified speaker (UNKNOWN): it
- 24:09
- Unidentified speaker (speaker_0): does make a lot of sense to raise some capital when you've got this big milestone announcement and you need to moderate the capital raised with the the valuation um because it's it's tough to take down down rounds. I mean I just in any market, nuclear uh included
- 24:27
- Unidentified speaker (speaker_0): private market down rounds are tough. Yeah.
- 24:30
- Brennan: They're
- 24:30
- Unidentified speaker (UNKNOWN): really
- 24:31
- Unidentified speaker (speaker_0): tough. They're they're tough to underwrite as an investor saying, you know,
- 24:34
- Unidentified speaker (UNKNOWN): you
- 24:35
- Unidentified speaker (speaker_0): guys were worth that, now you're worth this. And now I you think you're going to be worth a lot more than what you were worth, you know, the first time. It's hard to recruit from an employee perspective. It can be really tough on employees of, you know, you you go join a company and for startups, yeah, you make you make good money most of the time, hopefully. Um, but the the
- 24:54
- Unidentified speaker (speaker_0): opportunity is really in
- 24:56
- Unidentified speaker (UNKNOWN): the
- 24:57
- Unidentified speaker (speaker_0): equity that you get in participating in these companies. Um so it can be really tough on existing employees and and recruiting of, you know, um the same hesitation that investors see with down rounds, the the prospective employees see of, you know, why would I go join this company when potentially I could go join uh um this this one that looks like a
- 25:16
- Unidentified speaker (speaker_0): rocket ship.
- 25:17
- Brennan: Yeah.
- 25:19
- Unidentified speaker (UNKNOWN): No,
- 25:19
- Brennan: it's very true. Very true. It makes me think a bit about shifting gears here slightly. I recently had a great conversation with Mike Loffer on a podcast that were soon to be released about Kairos' Kairos's 10 10-year year journey and the iterative development approach. And they are fortunate to have patient private capital
- 25:39
- Brennan: to be able to do that. One of the concerns we talked about was there's a difference in iterating on pilot or demonstration projects and iterating on commercial projects.
- 25:51
- Unidentified speaker (UNKNOWN): And
- 25:51
- Brennan: I think another another risk of a market like this is every new dollar of capital that comes in needs to be put to work in something that's going to produce revenue.
- 26:02
- Unidentified speaker (UNKNOWN): Like you
- 26:02
- Brennan: don't have this patient capital saying, okay guys, go build another pilot, another pilot program project, which we should talk in a minute about what's the new benchmark for these private guys that are popping up now, because a year ago it was the DOE pilot program.
- 26:18
- Brennan: But it's a it's it's another risk that shouldn't be overlooked in the industry. And what what these companies are really going to have to battle is is my am I going to iterate on commercial reactors? Like, or am I going to be able to do some sort of demonstration testing behind the scenes to learn those lessons that I'm inevitably going to have to learn between now and that first commercial
- 26:37
- Brennan: reactor? Because it's it's there's a lot to be learned, even to get capacity factors up over time. Like I think that iteration's going Is to happen on the commercial, on the commercial reactors themselves.
- 26:48
- Unidentified speaker (UNKNOWN): But
- 26:48
- Brennan: it's also, I don't know if it's a it's a winning formula for all these companies to say, we're gonna, we're gonna be the SpaceX of nuclear, we're gonna iterate, learn, iterate, learn on commercial reactors. Because ideally, by the time you get to a commercial reactor, you've iterated and learned and iterated and learned. And then you can just go cookie cut or spit those things out. But I I think it's just
- 27:08
- Brennan: the inevitable reality of having to move as fast as we're having to move that some of the iterations gonna come. going to go from first of a kind to these nth of a kind projects. And maybe the eighth or the tenth one is where, okay, like now we have the recipe down.
- 27:23
- Unidentified speaker (UNKNOWN): Um,
- 27:24
- Unidentified speaker (speaker_0): Brendan, it brings to mind an exciting private market announcement. Neutron Power Ventures was part of this.
- 27:31
- Unidentified speaker (UNKNOWN): Um,
- 27:32
- Unidentified speaker (speaker_0): Project Omega announced a Series A. They raised $80 million. Um,
- 27:37
- Unidentified speaker (UNKNOWN): first
- 27:37
- Unidentified speaker (speaker_0): of all, massive congratulations. to Staff Sheehan and the whole Project Omega team. Super impressive what they're working on. Definitely, definitely some bias over here.
- 27:48
- Unidentified speaker (speaker_0): But to the point of this conversation,
- 27:51
- Unidentified speaker (UNKNOWN): you got
- 27:52
- Unidentified speaker (speaker_0): to find ways to monetize a business outside of just let's iterate on our singular commercial reactor design and hope we can improve it over time. And so I bring them up because they've got such a cool approach to fuel recycling where they're going to harvest isotopes and sell the isotopes and have a separate line of business that can
- 28:11
- Unidentified speaker (speaker_0): then reinvest in the fuel recycling program. And if their whole value prop was, no, we're just going to figure out fuel recycling and over time we'll get better and better and better at it. And ultimately that'll make money, you know, we've we've had this joke before if uh if all you need is 25 years and 25 billion dollars and you can solve the nuclear problem, you're not solving anybody's problem. Right?
- 28:34
- Unidentified speaker (speaker_0): So
- 28:35
- Unidentified speaker (UNKNOWN): you
- 28:35
- Unidentified speaker (speaker_0): gotta find ways to monetize the business as you go and to produce revenue, exactly to your point. Um, and so I I gotta give them a shout out. It's it's really exciting, I think, especially to this point about where we are in the market cycle at this point, the ability to raise. money in the current environment will speak at some level to the quality of the
- 28:55
- Unidentified speaker (speaker_0): company and the and the team they've built. Another company, I'll I'll just shout them out who announced a big round recently is uh Seth Cohen and the Mavria team. Uh Nick Poradek and Adam Blake. Um shout out to those guys. They just raised $100 million. Um, you know, Seth's been such an
- 29:15
- Unidentified speaker (speaker_0): important individual in the nuclear conversation in the in the nuclear um
- 29:22
- Unidentified speaker (UNKNOWN): in
- 29:22
- Unidentified speaker (speaker_0): where we are today in nuclear. You know, I'm I'm hesitant to call it the renaissance, right? But but we would not be where we are today in nuclear without Seth Cohen's contribution. Um and and so shout out to him. Super, super cool to see what he's working on. Um
- 29:39
- Unidentified speaker (UNKNOWN): yeah,
- 29:39
- Unidentified speaker (speaker_0): yeah, but uh to the point of high high quality companies are still able to go out and raise capital despite market conditions.
- 29:46
- Brennan: Yeah, cool business too. And by the way, our our our friend Brett Rampall has an excellent episode with Seth Cohen on his Generate podcast that everyone should go listen to. And it was it was pretty recent. It was like in within the last month or two. Go listen to that because you hear about Seth Cohen went in and broke a bunch of things, starting in the
- 30:06
- Brennan: Doge effort, but then also in the DOE. And really high caliber former Kirkland and Ellis attorney, which those of you familiar with KE, it's not easy to get a job there.
- 30:17
- Brennan: Some of the highest caliber lawyers in the world. And it i also a little bit of an interesting genesis of how he got there. You know, like his he had this interest in UFOs and so go listen to it. It's worth listening to. What a cool concept though. They're doing basically shipping container sized data centers, right? Like they're making
- 30:37
- Brennan: micro data centers that are presumably transportable, huh?
- 30:41
- Unidentified speaker (speaker_0): The uh the data center equivalent of an SMR. Yeah.
- 30:45
- Brennan: That's awesome. And I wonder, I'm sure eventually they're gonna try to use uh a micro reactor for power as well. huh?
- 30:53
- Unidentified speaker (UNKNOWN): I I
- 30:53
- Unidentified speaker (speaker_0): think they'll take whatever electrons they can get at some level, but but I think that given the uh the interest and desire to catalyze nuclear, that they'd be happy to to off take some electrons at the right price from
- 31:05
- Unidentified speaker (UNKNOWN): from a
- 31:05
- Unidentified speaker (speaker_0): nuclear reactor.
- 31:07
- Brennan: I saw those guys hi highlighted in a Wall Street Journal episode the other day. Congrats to both. Like and and I totally agree with you. Staff and what they're doing at Project. Omega. Congrats to you also for the deal there. Again, guys, not investment advice here, but congrats to you and the team on the deal there. And congrats to Seth. That's exciting. It's cool to see these guys that went in and
- 31:26
- Brennan: broke things and were impactful in whether it was in Doge or in the whole push for nuclear inside the DOE. And what are they doing now? Like, what are they excited about now?
- 31:35
- Unidentified speaker (UNKNOWN): Yeah,
- 31:35
- Brennan: you mentioned Nick Turan earlier. Like he's he's also a part of a maritime fan. focused endeavor, which is really interesting. And it's I think it'd be hard to get that guy excited about something. He knows a lot about a lot of things in nuclear, and he's been a teacher to many of us. And
- 31:51
- Unidentified speaker (UNKNOWN): the
- 31:51
- Brennan: fact that that got him excited makes me really want to pay attention as well. You know, it's just like these these smart guys, what got them excited is certainly worth paying attention to.
- 32:02
- Unidentified speaker (UNKNOWN): Yeah,
- 32:02
- Unidentified speaker (speaker_0): you know. Brennan, it's it's worth uh taking a moment to mention maritime nuclear. You know, there's certain moments in life where something happens and you realize that um the tides are changing or that there's a a new cool kid on the block. Um and so I'll tell the story without naming any names, but um
- 32:21
- Unidentified speaker (UNKNOWN): th
- 32:21
- Unidentified speaker (speaker_0): there had had a few cold outreaches and a few warm referrals and a few meetings. set up that I went into about three weeks ago. And back to back over the course of the afternoon, I had three pitches for maritime nuclear companies. And I went into that day, you know, not thinking much about maritime nuclear, right? It was
- 32:41
- Unidentified speaker (UNKNOWN): on my
- 32:41
- Unidentified speaker (speaker_0): radar. I knew about Nick and Ocean Atomics. Um, but you know, walked away from that that Wednesday afternoon of like, maritime nuclear is in vogue right now. So you know, opening up the curtain a little bit of what uh what we're seeing, you know, from a deal flow perspective, um, there's a lot of maritime nuclear deals that are that are being pitched. And
- 33:01
- Unidentified speaker (speaker_0): um it's it's an interesting space. It's kind of a a new area to underwrite at some level when you think about, hey man, the regulatory perspective Perspectives is hard enough for terrestrial base reactors. Um what happens when you're talking about shipping cargo to to oversea ports and you know, who's regulating in in in the open oceans? And um, you know,
- 33:21
- Unidentified speaker (speaker_0): you're you're
- 33:24
- Unidentified speaker (UNKNOWN): the
- 33:24
- Unidentified speaker (speaker_0): the the waters are a bit muddy there, no pun intended.
- 33:28
- Brennan: I guess part of the the technology pitch there is that you have this abundance of water that you can just use s cycle as coolant, right? So you're not having to the the water thing is much sol more solid. solvable. The thing that I go to there it's it's a massive, massive industry, right? Yeah. Like the amount of goods that gets transported in these these
- 33:48
- Brennan: massive vessels, whether it's commodities or goods get the move moved around the world. I don't know the percentage of fuel consumption that is diesel powering these ships, but it's a lot. It's a significant amount. And so yeah, it's it's certainly an exciting space.
- 34:05
- Unidentified speaker (speaker_0): The line I'll use there is the further you get from Texas, the more you pay for energy. Right. And
- 34:12
- Brennan: this is true.
- 34:14
- Unidentified speaker (UNKNOWN): And so,
- 34:15
- Unidentified speaker (speaker_0): you know, um it's one thing to have a terrestrial sighted reactor uh somewhere in the US or somewhere on on planet Earth is as you get out in the oceans, you're probably paying more per megawatt than what you would pay uh for a land-based system. And then as you get into outer space, you're paying a lot more than what you would pay on either of those two primary um
- 34:34
- Unidentified speaker (speaker_0): locations. So you can kind of extrapolate it out from there.
- 34:38
- Brennan: Yeah, which is why the the space, the space space.
- 34:44
- Brennan: The space area of all this is is so interesting as well. You know, what the interes interiors guys are doing. And you know, there's others checking. chasing that too. Is you're gonna need a lot of power in space, reliable, high density power in space, not just to get there and to move around, but also to power the things that we want to do there. So
- 35:01
- Brennan: interesting stuff, man. Well, look, let's close the loop on the election.
- 35:06
- Unidentified speaker (UNKNOWN): Get
- 35:07
- Brennan: fair to say neutral to positive at the federal level and state dependent, depending on where you're at. You know, I think my my home state of town. Texas, it's gonna be an interesting dynamic related to data centers. And you know, there's no no hiding the fact that a lot of these newer SMR companies were born on renderings of parking a
- 35:27
- Brennan: co-located reactor next to a data center. And so the I think the macro there, depending on the state, Date could be challenged, but I don't think the macro for the power we need. for the grid in general has changed. I mean, I saw a great tweet the other day talking about, hey, did you guys advent forget the advance act? That was before
- 35:47
- Brennan: this AI craze. And that was under Biden. And that that was pre underwriting any need from AI. And at that point we were, you said earlier, Andrew, wanting to triple nuclear by twenty 2050, fifty, right?
- 35:59
- Brennan: And so the the the base case for
- 36:03
- Brennan: baseload, grid scale nuclear, neutral to positive, and I that's my framing, is state dependent on penetration of data centers. A positive to that, which another friend of ours, very smart guy, gave me this insight, and I thought it was spot on, is a slowdown in data centers is probably a good thing for nuclear.
- 36:23
- Brennan: Why? Because these guys said, I need power. tomorrow. What power can I get tomorrow?
- 36:30
- Unidentified speaker (UNKNOWN): I
- 36:30
- Brennan: can get nat gas.
- 36:32
- Unidentified speaker (UNKNOWN): Give
- 36:32
- Brennan: me a nat gas turbine. Well, those are back ordered through the early 2030s now, too. And
- 36:38
- Brennan: okay, oh the menu, I'll rewind. The menu is nat, gas and nuclear for incremental baseload scale, nat, gas and nuclear. So what does this do? I think it really gives the nuclear guys the ability to catch up.
- 36:51
- Unidentified speaker (UNKNOWN): You
- 36:51
- Brennan: know, a lot of these projects, if they're not going to break around tomorrow like they thought they were going to, it gives nuclear a lot of time to catch up with the technology. And maybe by the time we get there, that on the menu they say, I will build an SMR on site here instead of a gas turbine.
- 37:06
- Unidentified speaker (UNKNOWN): You know,
- 37:07
- Brennan: because gas is gas is great.
- 37:09
- Unidentified speaker (UNKNOWN): We
- 37:09
- Brennan: have an abundance of gas. We need to use a lot of gas. We've talked about this. It is very exposed to changes in fuel prices. You are continuously refueling this thing. It's like you know, it's like filling up your car. You always got to be putting more fuel in. The big benefit of nuclear is you gotta you have to use new fuel every couple years,
- 37:29
- Brennan: you know, every five years, depending on the design. But the the benefits of that of not having that exposure day to day to day, week to week on the fluctuations the and prices. and what that does to the economics of the project if prices change is change fundamentally is
- 37:44
- Unidentified speaker (UNKNOWN): is
- 37:44
- Brennan: what a big part of what makes nuclear stand apart as well. So
- 37:49
- Unidentified speaker (speaker_0): it's it's the catch 22 of nuclear of if you already have the CAPEX spin, if you already have a reactor in place, the OpEx is fairly negligible relative to the amount invested to build the thing. Um whereas with the net gas plant, that's that's quite the opposite, right? It's it's fairly cheap to build
- 38:08
- Unidentified speaker (speaker_0): a net gas plant um relative to a nuclear plant, uh, but it can become very expensive depending on the price of gas, uh, wherever you may be. And to your point, you're subject to volatility in those fuel prices in in a much more meaningful way.
- 38:26
- Unidentified speaker (UNKNOWN): Yeah,
- 38:26
- Brennan: it's a it's a good it's a good comparison of understanding overnight capital costs, which is if I were to build this thing tomorrow overnight, what would it cost to build the thing versus the LCOE calculations? Now, neither one of these are perfect, but the LCOE estimates the cost over the life of the project.
- 38:45
- Unidentified speaker (UNKNOWN): Now,
- 38:45
- Brennan: an LCOE assumption, to your point,
- 38:48
- Unidentified speaker (UNKNOWN): is
- 38:48
- Brennan: gonna going to bake in current gas prices. What are gas prices today? $3 in MCF, something like that, more or less. What have they been before? Well, they ran up to north of $10 in MCF in the early 2000s, like 2006, 2007. And what broke that? Well, the
- 39:08
- Brennan: the Shale Revolution and oil and gas broke that, which also was part of the big pullback in interest for nuclear, because suddenly gas got really cheap.
- 39:16
- Unidentified speaker (UNKNOWN): And
- 39:16
- Brennan: then Fukushima happened. You know, you had this perfect wave.
- 39:20
- Unidentified speaker (UNKNOWN): But
- 39:20
- Brennan: comparing the two, what is the LCOE sensitivity to natural gas prices versus what is an LCOE sensitivity to the price of uranium? And the LCOE is much more sensitive, I imagine, to changes in gas prices because you're continuously fueling the thing over the life. So yeah,
- 39:40
- Brennan: that's a great point.
- 39:41
- Unidentified speaker (UNKNOWN): Um, you know,
- 39:42
- Unidentified speaker (speaker_0): Brennan, that that does bring to mind a point that's worth making
- 39:47
- Unidentified speaker (speaker_0): about ceilings and about kind of moderating expectations. Um, we had talked previously about the price of diesel going up and that being positive for nuclear, right? The the price of alternative fuels to nuclear going up simply makes those those LCOEs go up, exactly to this conversation. Um, that said, I
- 40:07
- Unidentified speaker (speaker_0): read this really interesting analysis about $200 oil.
- 40:11
- Unidentified speaker (UNKNOWN): And
- 40:11
- Unidentified speaker (speaker_0): it was basically saying, you know, $200 oil is never going to happen. And if you look back at March when the Iran War started and the Strait of Hormuz moves was was,
- 40:22
- Unidentified speaker (UNKNOWN): you
- 40:22
- Unidentified speaker (speaker_0): know, suddenly closed, and all of these sections. sets of conditions that suddenly showed up, the shocks to the oil market, and we still didn't hit $200 oil. Yeah. And it's like, okay, provide to me some set of conditions where you could reach $200 oil. And you would have to make a lot
- 40:42
- Unidentified speaker (speaker_0): of pretty crazy assumptions to get there. Um, if if the shock previously couldn't do it. Um and so I I I think that leads to
- 40:51
- Unidentified speaker (speaker_0): one other key piece of this hydrocarbon conversation that's I think just a good knowledge base. I mean, I think to this point of
- 41:00
- Unidentified speaker (speaker_0): sensitivity between the two fuels of oil, gas, and nuclear, is understanding the relationship between oil and gas. And that in the Permian Basin and in many of the productive um oil product oil producing. regions in the world, oil and gas are co-produced. And so when the straight-up
- 41:20
- Unidentified speaker (speaker_0): hormouse was closed in March, um a bunch of people bet that, hey, the price of oil is going up and the price of net gas is going up. And what we saw was the price of oil did go up, but the price of natural gas actually moderated down slightly over the cour course course of that trade. And people were really confused about this. And the response,
- 41:40
- Unidentified speaker (speaker_0): Dunberg wrote a great article on this, I think in May or so, we can
- 41:45
- Unidentified speaker (speaker_0): confirm that. But he basically just talked about co-production. And that when you drill a well, you're going to get out some oil and you're going to get out some gas. And in certain areas, you'll get out a little more oil. And in some areas, you get out a little more gas. But you know, these are co-produced chemicals. They're coming out of the same well bore. And so you go out and you drill
- 42:05
- Unidentified speaker (speaker_0): drill a well. Um, and it's just, I think it's important to understand that there is ultimately, you know, in the ultra-long-term macroeconomics, you know, theoretical perspective, you're going to find clearing prices that have pretty comparable fuel costs um across the board. But there will still be some
- 42:25
- Unidentified speaker (speaker_0): um
- 42:27
- Unidentified speaker (speaker_0): interrelation caused by co-production, right? So uh I just think that's an important piece. The to to answer why did net gas prices go out, it's because all these mining rigs got stood up in March and April saying, hey, there's not oil coming out of the Middle East. We need to drill new wells in existing locations. We drilled those
- 42:46
- Unidentified speaker (speaker_0): new wells with a desire to produce oil. And what do you get? You get a whole lot of natural gas coming out of those wells as well. And so that drives down the the price of gas as a co-produced item. And I I go through this long uh diatribe just to make the point of yeah gas may go up over time, but I I wouldn't count on um going past $10
- 43:07
- Unidentified speaker (speaker_0): gas ever in our lifetimes. Times, Right. That that we will find inventory um and and new ways to produce this stuff. Um
- 43:16
- Unidentified speaker (UNKNOWN): new
- 43:16
- Unidentified speaker (speaker_0): new shale to frack. So you've got to bring the cost of nuclear down as the solution to this. You can't count on the other guys getting worse.
- 43:25
- Unidentified speaker (UNKNOWN): Uh
- 43:25
- Brennan: it's it's great framing and and great education as well. It's I with my oil and gas background, my brain tends to try to draw parallels there
- 43:35
- Brennan: because it's true. I spent a lot of time in the Permian Basin. I was just in Midland most of this week, actually. And it's crazy if you conceptually think about negative gas prices. Like, just what does that even mean? Negative gas prices. Like, imagine you go to fill your car up, and
- 43:55
- Brennan: I'm talking about natural gas, but just Disconception. conceptually, you go to fill your car up,
- 43:59
- Unidentified speaker (UNKNOWN): and
- 43:59
- Brennan: instead of paying
- 44:00
- Unidentified speaker (UNKNOWN): for
- 44:01
- Brennan: the gas, they pay you to take the gas.
- 44:04
- Unidentified speaker (UNKNOWN): This
- 44:04
- Brennan: happens in the Permian Basin, to your point. Negative gas prices or close to zero gas. What does that mean? It means I'm producing this thing that I can't get rid of.
- 44:14
- Unidentified speaker (UNKNOWN): And
- 44:14
- Brennan: therefore I'm going to pay someone to take it off of my hands. And so it's it's really good framing, Andrew, because what happens out there, and this is why a lot of data center projects have gotten stood up out there and they're using behind the meteor gas generation, because right now, gas is cheap. Why is gas cheap? Because it they're producing it to produce the oil, it comes out, they have to do something with it.
- 44:33
- Brennan: Gas is really hard to transport without a pipeline. You can't move it.
- 44:37
- Unidentified speaker (UNKNOWN): So
- 44:38
- Brennan: if there's not pipeline capacity to move it around the country, then there's nothing to do with it. What do they do historically? They've flared it. Well, that's not great for the environment either. So there's a lot of restrictions and rules around flaring the gas. Flaring it means you're just burning it into the atmosphere, wasting it essentially. And so there's a big push to get even more pipeline capacity out
- 44:58
- Brennan: of the Permian for this reason, because there's so much gas there. With the extra gas, you can either build something right on site that uses it or you can build a pipeline to move it. And it's also why gas gets really expensive in certain parts of the country in the winter when there's a big storm and a big freeze, and then it stays. cheap in Texas, to your point. So we could probably
- 45:18
- Brennan: talk an hour, or maybe we should do an episode someday on natural gas and how it functions. But it's a really good point you made about to produce the oil, you got to produce the gas. They come out together. Oil comes with a bunch of gas typically and a bunch of water. And that mix changes depending on the basin. But great framing, man. I love it.
- 45:38
- Brennan: Let's move on now. You ready to talk? So we we covered, we covered the X energy deal.
- 45:44
- Unidentified speaker (UNKNOWN): You
- 45:44
- Brennan: want to give another shout out to Julian team, the EDF, the consolation loan, the conditional financing, $5 billion.
- 45:53
- Brennan: It's so great to see these announcements. The energy department announces a It's $5 billion loan to boost nuclear power and help lower costs in Illinois, Maryland, and Pennsylvania.
- 46:05
- Unidentified speaker (UNKNOWN): A
- 46:05
- Brennan: lot of good work being done there on upgrades and extensions, huh? It's good. It's awesome to see another announcement here. It seems like they've been coming out every couple weeks these days.
- 46:15
- Unidentified speaker (UNKNOWN): It
- 46:15
- Brennan: looks like this is
- 46:17
- Brennan: uprights at eight plants in Illinois, Maryland, and Pennsylvania. The plants being Braidwood, Byron, Clinton, Dresden, LaSalle, and Quad City, Quad City. Cities in Illinois, and Calvert Cliffs in Maryland,
- 46:29
- Unidentified speaker (UNKNOWN): and
- 46:29
- Brennan: Limerick in Pennsylvania.
- 46:33
- Unidentified speaker (speaker_0): Some of these plants were the uprights were announced earlier. We had the week of uprights, I think at uh middle, middle of October, beginning of October.
- 46:43
- Unidentified speaker (UNKNOWN): Um
- 46:44
- Unidentified speaker (speaker_0): and so some of these plants now are getting
- 46:47
- Unidentified speaker (UNKNOWN): um
- 46:48
- Unidentified speaker (speaker_0): energy dominance financing. uh as part of the up rate project. So um if the investment alone or the offtake alone wasn't uh wasn't good enough now you get an even sweeter package on it. So um I I think moreover to the the comment we've shared and I don't know if I've um publicly called it but the the Google
- 47:08
- Unidentified speaker (speaker_0): announcement of uh 4.7 billion dollars um against 890 megawatts of upgrades. It's probably going to be the best rough gigawatt uh dollar spent of the 2020s.
- 47:23
- Unidentified speaker (UNKNOWN): Yeah,
- 47:23
- Brennan: you've made that framing before. What is a dollar per gigawatt?
- 47:26
- Unidentified speaker (speaker_0): Yeah.
- 47:27
- Unidentified speaker (UNKNOWN): Yeah,
- 47:28
- Brennan: and to your point, too, this was this was really part of other hyperscaler announcements that have already been announced, have taken this capacity away. And so what did those agreements allow consolation? Constellation to do? They said, okay, we're going to get a market premium rate by hyperscalers for these volumes, and therefore we can go underwrite spending that
- 47:47
- Brennan: capital to bring these volumes online. What does the EDF financing do? Well, it's just additional tailwinds to get those volumes online with lower cost financing. So instead of using equity dollars to go deploy these projects or higher cost project finance, they're going to be able to. use low cost debt financing. So great for great for all parties here.
- 48:07
- Brennan: Great for the plants, uprights, extensions, great for the hyperscalers. They get firm volumes with twenty plus year commitments and great for constellation. They get low cost financing. So win
- 48:18
- Unidentified speaker (UNKNOWN): win
- 48:19
- Brennan: win on this front.
- 48:20
- Unidentified speaker (speaker_0): I think the simplest model to understand this is it brings down the interest rate.
- 48:26
- Unidentified speaker (UNKNOWN): Right. You
- 48:27
- Unidentified speaker (speaker_0): know, you're gonna you're gonna loan some money to do an upgrade project. And um, you know, think of it as taking a uh a loan to do a renovation on your house uh and renovate the kitchen and the EDF steps in and says like hey we'll give you a a sweeter interest rate on your loan. Um that's I I think that's the right mental model for for
- 48:46
- Unidentified speaker (speaker_0): folks.
- 48:47
- Unidentified speaker (UNKNOWN): Yeah
- 48:48
- Brennan: and I'm just looking here I just briefly looked up the hyperscale agreements tied to this as Google. Five of the eight plants were in an October 6th announcement of a 20-year PPA between Google and Constellation. Amazon on September 30th, Constellation finalized the PPA with Amazon, supporting a 190 megawatt up rate at Calvert Cliffs. Meta
- 49:08
- Brennan: Clinton was already in line for a 30 megawatt uprate upprate under a 2025 deal with Meta. Walmart became the first. retailer to sign a nuclear PPA for power from Dresden.
- 49:20
- Unidentified speaker (UNKNOWN): It's
- 49:20
- Brennan: awesome to see Walmart jumping in there. So yeah, these are deals we've already discussed previously, but again, it's it's they're now gonna get done with lower cost financing from the EDF, which is good for all parties.
- 49:34
- Unidentified speaker (speaker_0): Should we talk about Darlington?
- 49:36
- Brennan: Let's do it, man. I saw this.
- 49:39
- Brennan: I I I really like and follow Stefan Sumowski. I apologize if I pronounce it wrong, has some great insights on X
- 49:47
- Unidentified speaker (UNKNOWN): and
- 49:48
- Brennan: brought this up. You want to start, Andrew or me?
- 49:51
- Unidentified speaker (speaker_0): Um
- 49:52
- Unidentified speaker (speaker_0): Darlington
- 49:54
- Unidentified speaker (speaker_0): has a BWR X three hundred project that announced a delay that it will no longer be on time, nor will it be on budget.
- 50:05
- Brennan: Uh-oh.
- 50:07
- Brennan: Uh-oh. I said this came from Nick Turan as well. Uh I initially posted this.
- 50:12
- Unidentified speaker (UNKNOWN): It was
- 50:13
- Brennan: another great one to follow.
- 50:14
- Unidentified speaker (UNKNOWN): Go
- 50:15
- Brennan: ahead, Andrew.
- 50:17
- Unidentified speaker (speaker_0): They didn't provide too much more than that, frankly. They they didn't give revised pri you know, cost, they didn't give a revised deadline. Uh Um they just said,
- 50:29
- Unidentified speaker (UNKNOWN): hey,
- 50:29
- Unidentified speaker (speaker_0): we're not gonna be there on time.
- 50:31
- Brennan: Let's read. So Nick Turan's tweet, I'm gonna read it here. Oop OPG update on the BWRX 300. The NP Unit One is no longer expected to achieve the previously disclosed commercial operation date target of October 2030, or be completed within the previously disclosed estimated cost of $7.7 billion.
- 50:50
- Unidentified speaker (UNKNOWN): And
- 50:50
- Brennan: that's where a lot of the you know, the skeptics here have been around this specific technology being deployed in Canada. So you have that pushback from the Canadians. Like, why did we, why did we not pick a sovereign design? Why do we not pick a domestic design? So Chris Kiefer was quite vocal about this, the support for the can do
- 51:10
- Brennan: reactors and why they went this way.
- 51:12
- Unidentified speaker (UNKNOWN): And
- 51:13
- Brennan: then separately, just you know, if we're if going to gonna do an SMR project, why are we picking older technology that is very high on a dollar per kilowatt basis? So that's that's been the pushback I've seen. The proponents of it I've seen is more like look, well, the here and the now technologies that are licensed and deployable and understood is basically the
- 51:32
- Brennan: AP1000 from Westinghouse, the BWRX 300 from GE.
- 51:36
- Unidentified speaker (UNKNOWN): See So
- 51:37
- Brennan: if you want to build something today and get to work on coming down the cost curve, those are your options. Well, you've seen the Oppenheimer guys, you've seen the nuclear company really go more targeted towards the AP1000 design. You've seen Elemental go towards the BWRX 300 design, their project in Ohio with Google. By the way,
- 51:57
- Brennan: David Faraday was on the Catalyst podcast with Shale Khan yesterday. That's also worth a listen. That's a
- 52:02
- Unidentified speaker (speaker_2): must listen. That's a fantastic episode.
- 52:05
- Unidentified speaker (UNKNOWN): And
- 52:05
- Brennan: those men, those guys are inspiring. I I really like them a lot, what they're trying to do, and just really focused on execution. So the question is like, okay, hey, look, we're going to go execute on multiple projects and we're going to learn from that, and then we're going to execute on multiple more projects in a technology agnostic way. Well, their view is that this is a
- 52:25
- Brennan: smaller smaller-sized sized build. so we can build more of them quicker. Therefore, we're going to try to go deploy half a dozen of these things in Ohio. And we're going to learn a lot along the way. So the
- 52:38
- Brennan: other positive or defense I heard of this is: look, there's a lot of civil infrastructure costs being spent
- 52:45
- Unidentified speaker (UNKNOWN): in
- 52:45
- Brennan: And Darlington that will be spread out across future units. Like that has to be, it's that fixed cost that has to be deployed either way. And so, you know, at the end of the day, I think you and I both agree we want this to get built. We want it to get built on time. We want it to get built on budget. And we're also not immune to the realities of building these things for the first time.
- 53:05
- Unidentified speaker (speaker_0): Brennan, um
- 53:06
- Unidentified speaker (UNKNOWN): it's
- 53:07
- Unidentified speaker (speaker_0): always important to normalize our numbers. So the original estimate seven 7.7 point seven billion against three hundred 300 megawatts, is a twenty-five point six billion dollar gigawatt. If you're gonna put in
- 53:23
- Unidentified speaker (UNKNOWN): you
- 53:23
- Unidentified speaker (speaker_0): know a few of these units,
- 53:26
- Unidentified speaker (UNKNOWN): uh
- 53:26
- Unidentified speaker (speaker_0): that's expensive as hell. Say
- 53:28
- Unidentified speaker (UNKNOWN): that number
- 53:29
- Brennan: again. Say that number
- 53:30
- Unidentified speaker (UNKNOWN): again.
- 53:34
- Unidentified speaker (speaker_0): Yeah, it's an expensive gigawatt. And I I
- 53:37
- Unidentified speaker (UNKNOWN): just
- 53:37
- Unidentified speaker (speaker_0): I I it's the solution to building new nuclear is bringing down the cost to be it it goes back to this whole thing we've been talking about of overnight cost of gas plants about $2 billion, $3 billion, and then you're subject to uh the price of the fuel. And that's the the market
- 53:57
- Unidentified speaker (speaker_0): has declaratively announced they'd much rather take fuel risk. And I think that's why we harped on about understanding ceilings around hydrocarbon markets, because we got to get more competitive there. If we can build a nuclear plant for $5 billion, we'll have announcements all over the country. But if we're saying,
- 54:17
- Unidentified speaker (speaker_0): hey, it's $25 billion for a gigawatt of this technology,
- 54:25
- Unidentified speaker (speaker_0): it's going to be really tough to keep doing these, especially when the first one sees a delay and we don't even know what the cost is going to be and what the due date is going to be.
- 54:38
- Unidentified speaker (speaker_0): Markets are highly influenced by expectations. Anybody who's done enough economics, you know, there's always a expectation term. And when you create volatility in that expectation term, you have to underwrite to a to a downside case. And so it it becomes
- 54:53
- Unidentified speaker (UNKNOWN): it
- 54:54
- Unidentified speaker (speaker_0): becomes really tough to get excited about some of these projects when you when you don't have a good expectation and your your base case is a $25 billion gigawatt.
- 55:05
- Brennan: Yeah.
- 55:05
- Unidentified speaker (speaker_0): Right.
- 55:07
- Unidentified speaker (speaker_0): One of the lines that uh uh has been discussed is um there's there may be a valley of death with some of these. 300 megawatt SMR uh water-cooled reactors. And it's not that I'm inherently bearish. And I think a lot of what I'm commenting sounds like, oh, I'm super against these. I'm not
- 55:27
- Unidentified speaker (speaker_0): against these. I'm I'm you know, NPV is an investor in blue energy. They're taking the BWRX 300 design and planning to build it in the Port of Victoria in Texas. Um, novel build approaches, but realistic expectations. about what can be done there. Um, but the the line is with some of these, you know, valley of death reactors, as they've been dubbed, is
- 55:47
- Unidentified speaker (speaker_0): how about 75% of the civil infrastructure for a third of the power output?
- 55:52
- Unidentified speaker (UNKNOWN): And
- 55:52
- Unidentified speaker (speaker_0): it's like, well, wait a second, we're already talking about something that's super expensive to begin
- 55:56
- Unidentified speaker (UNKNOWN): with.
- 55:57
- Unidentified speaker (speaker_0): So it it's
- 56:00
- Unidentified speaker (speaker_0): w we need to find a way to lower the cost.
- 56:02
- Unidentified speaker (UNKNOWN): Yeah.
- 56:03
- Unidentified speaker (speaker_0): And and that's why I think with some of these EDF announcements, the operator projects are great, but they have a cap.
- 56:09
- Brennan: Yeah.
- 56:09
- Unidentified speaker (speaker_0): Right? You can only get so much juice out of out of a reactor.
- 56:13
- Brennan: Yeah. Um
- 56:13
- Unidentified speaker (speaker_0): and so at some point you gotta build new infrastructure. And um
- 56:20
- Unidentified speaker (speaker_0): yeah, the the subsidizing them is not going to be the path to
- 56:27
- Unidentified speaker (speaker_0): building.
- 56:32
- Brennan: Yeah. Uh I mean reality, there's only so much capacity to your point of upgrades and extensions, and it's the lowest hanging fruit.
- 56:39
- Unidentified speaker (speaker_0): Yeah.
- 56:39
- Unidentified speaker (UNKNOWN): Yeah,
- 56:40
- Brennan: but it's it that's what's so tough about the financing piece of this, is like,
- 56:44
- Unidentified speaker (UNKNOWN): you
- 56:44
- Brennan: know, if you're an investor, you want to underwrite
- 56:47
- Unidentified speaker (UNKNOWN): the
- 56:48
- Brennan: project, the widget, whatever it is. And
- 56:52
- Brennan: maybe you say, I want to see how the first one goes before I make a decision on the second one.
- 56:56
- Unidentified speaker (UNKNOWN): And
- 56:57
- Brennan: then I want to see how the second one goes before I make a decision on the third one. But to your point, the civil infrastructure bill needs to happen either way.
- 57:04
- Unidentified speaker (UNKNOWN): So
- 57:04
- Brennan: do you bill all that to the first investor? Or are you able to allocate that over multiple projects? And I that's that's the hard thing, is it's like, okay, well,
- 57:14
- Unidentified speaker (UNKNOWN): we need
- 57:15
- Brennan: you to commit to three of these or four of these for the math to work.
- 57:19
- Unidentified speaker (UNKNOWN): And
- 57:19
- Brennan: we're gonna average out the dollar per kilowatt across those three or four facilities. Where are we at? We're at a gigawatt. Okay, what is the what does the math look like? What does the civil infrastructure look like? Should I just go build an AP 1000? And I don't know. I haven't seen that math, but I think that's what g these guys are wrestling, and I can see both sides. I can see that
- 57:39
- Brennan: if I'm gonna do three or four of these, I might as well do one of those. And I can see, well, the third and the fourth version of this thing's gonna be a lot more efficient than doing one of those things.
- 57:48
- Unidentified speaker (UNKNOWN): Yeah.
- 57:48
- Brennan: And I and so
- 57:50
- Unidentified speaker (speaker_0): And and Brendan, I should I should point out when I say twenty five billion dollars a gigawatt, there are many people who would correctly argue with me and say
- 58:00
- Unidentified speaker (UNKNOWN): you're
- 58:01
- Unidentified speaker (speaker_0): gonna you're gonna do better on the second and you're gonna do better on the third than you did on the second, you're gonna do better on the fourth than you did on the third. And at that point, you're at 1200 megawatts, and you're you're you know, you're able to kind of compound down and you're not at 25 billion all in, you're
- 58:16
- Unidentified speaker (UNKNOWN): at
- 58:17
- Unidentified speaker (speaker_0): 14 billion all in. And then you look a little
- 58:20
- Unidentified speaker (UNKNOWN): bit
- 58:20
- Unidentified speaker (speaker_0): more like an AP 1000, you have more flexibility, and you can go out and build these as one-offs. one offs. Hopefully, the way you built the fourth. unit, not the first unit, um, in in other locations and other places. And now you have more flexible power resource to give to a community who may only need 300 megawatts and doesn't need an AP one thousand.
- 58:39
- Brennan: Yeah, that's a good point. It's a good point. At some point we have to uh talked about this with John Arnold as well. At some point we have to innovate our well up our way up the size curve.
- 58:51
- Unidentified speaker (speaker_0): That's been what I've been saying for for months now is when people talk about a gigawatt reactor, they can't help themselves. They use the term AP 1000.
- 59:01
- Brennan: Yeah.
- 59:02
- Unidentified speaker (UNKNOWN): I
- 59:02
- Unidentified speaker (speaker_0): mean yeah, I I nobody calls it gigawatt, they call it AP one thousand. And it's like the default vocabulary in the industry is
- 59:09
- Unidentified speaker (UNKNOWN): if you want a big
- 59:10
- Unidentified speaker (speaker_0): reactor, it's an AP one thousand and it's Westinghouse and like there's not competition in that market. Um and you know we've said it here before and we'll say it again of American greatness comes from competition. And we if we want to have greatness at this scale, we need competition at this scale.
- 59:27
- Brennan: Yeah, totally true. It's become the Google or the Uber word of I'm gonna search for something, I'm gonna Google it. Yeah, I'm gonna order a car, I'm gonna order an Uber, I'm gonna build a gigawatt, I'm gonna build an AP one thousand. It's it's a good point. It's a very good point.
- 59:40
- Unidentified speaker (speaker_0): Yeah. Um, I I I
- 59:43
- Unidentified speaker (UNKNOWN): I
- 59:43
- Unidentified speaker (speaker_0): think it's worth kind of closing the loop too on this new nuclear capital summit from Tuesday. Um, the line in the room was
- 59:55
- Unidentified speaker (UNKNOWN): um,
- 59:56
- Unidentified speaker (speaker_0): you know, the the the question was, can we end on a positive note? And they went down the panel and everybody, you know.
- 1:00:03
- Unidentified speaker (speaker_0): being funny. I'm positive we need more government subsidies and government
- 1:00:07
- Brennan: support in
- 1:00:09
- Unidentified speaker (speaker_0): building nuclear. And and like it was a harmonious uh announcement coming from the stage.
- 1:00:17
- Unidentified speaker (UNKNOWN): And
- 1:00:17
- Unidentified speaker (speaker_0): you know, maybe I'm a bit subversive here, but I I don't think so. I I think that American markets are great when they're competitive and
- 1:00:27
- Unidentified speaker (speaker_0): properly advantaged. And so government's role, my my reaction to this is like, I don't think these EDF loans are going to solve any problems, frankly. Like who who's the beneficiary when EDF announces these upgrade projects? It's the person who is going to have to take a higher interest loan, which was either the
- 1:00:47
- Unidentified speaker (speaker_0): utility or the off taker. Right.
- 1:00:49
- Unidentified speaker (UNKNOWN): Vistra
- 1:00:49
- Brennan: or constellation, basically.
- 1:00:51
- Unidentified speaker (speaker_0): Yeah. So so it's the so the utility, if if if it's Vistra or constellation, then that means ultimately the ratepayers are paying a little bit less, which is which is a good thing for society. If it's Google, then it's taxpayer dollars going to subsidize a loan for a a hyperscaler, right? And you know, we can have a a conversation about whether or not that's how tax
- 1:01:11
- Unidentified speaker (speaker_0): taxpayer dollars should be spent. Yeah. Um
- 1:01:14
- Unidentified speaker (UNKNOWN): but
- 1:01:15
- Unidentified speaker (speaker_0): if it's, hey, we're going to go out and build greenfield projects, and what we need is the EDF to uh provide cost overrun insurance, I I think that is a horrible model for building these things because it adds a disincentive to on time, under budget performance. And it says, hey, if things do go
- 1:01:34
- Unidentified speaker (speaker_0): sideways, like you'll get bailed out. And in the investment community, at large is not going to show up and underwrite these things without that backstop. And that backstop is not how we're going to solve the problem here. And there is a time and a place, right? I I have a bit of a uh crass analogy that I've developed of the the nuclear
- 1:01:54
- Unidentified speaker (speaker_0): methadone clinic. Right. The the EDF office in some ways can be the methadone clinic of like, you got gotta to get off the hard stuff. and you know, there's a transition period and there's a time and a place, and we're gonna provide you the materials to uh to help you out and and get better. But if you if you keep going back to the methadone clinic
- 1:02:14
- Unidentified speaker (speaker_0): and you don't actually heal and you can't go off and live a life, you just switch your juice, right? Um and and so I I wanna want to see competition solve big scale reactors. I wanna want to see competition bring down the price of a gigawatt such that the private markets are saying,
- 1:02:34
- Unidentified speaker (speaker_0): hey, we don't need a subsidized loan. I'll I'll build this thing. I'll throw my infrastructure finance dollars into this and we'll go build a bunch of these and be competitive. And if
- 1:02:42
- Unidentified speaker (UNKNOWN): the
- 1:02:42
- Unidentified speaker (speaker_0): EDF wants to show up and make it cheaper for us, great. But we don't need their cash to make it work. And so and and that's, you know. that's my positive vision of a of a nuclear abundant future and my belief of how how we need to solve that to get there.
- 1:02:57
- Brennan: Yeah, you've been pretty vocal about it. It's like let the private markets figure it out.
- 1:03:03
- Unidentified speaker (UNKNOWN): Well,
- 1:03:03
- Brennan: cause the alternative is no one I won't say no one. Most people don't want the government overly involved in anything, right? Like they want the government to stay out of healthcare. health care. They want the government to stay out of education. But in this case, it's almost like if you were to say what was the dollar per kilowatt of
- 1:03:22
- Brennan: the
- 1:03:23
- Brennan: reactors built in France by the other EDF, the utility the state owned state backed utility in France. I don't think it mattered.
- 1:03:32
- Brennan: And there's there's criticism on the the cost costs as well of a uh Hinkley Hinckley point C, for example.
- 1:03:38
- Unidentified speaker (UNKNOWN): But
- 1:03:38
- Brennan: when when the governments get involved in backstopping these things and providing all the financing for these things, I mean France is not a low labor cost country.
- 1:03:49
- Unidentified speaker (speaker_2): Yeah.
- 1:03:49
- Unidentified speaker (UNKNOWN): You know,
- 1:03:50
- Brennan: that was the framing John Arnold laid out as: hey, large-scale nuclear works really well in countries with low labor costs and high electricity costs.
- 1:04:00
- Unidentified speaker (UNKNOWN): So
- 1:04:00
- Brennan: you can use cheap labor to compete with prices. that are really high.
- 1:04:04
- Unidentified speaker (UNKNOWN): And
- 1:04:04
- Brennan: so then you you look at the US and you say, okay, we have relatively high labor costs and we have very cheap electricity costs versus the rest of the world. Granted, we use a lot more, we need a lot more because we're leading the AI race. But for for cup countries like France, it doesn't really matter. The facilities in the UAE, you know, those were done
- 1:04:24
- Brennan: respectably well,
- 1:04:26
- Unidentified speaker (UNKNOWN): but like
- 1:04:26
- Brennan: at it probably didn't matter so much. Why? Because they're state owned, state controlled, state financed. And I don't think the nuclear industry in the US wants to be state owned, state controlled, and state financed. But we want the benefits of that, right? Like we want
- 1:04:41
- Unidentified speaker (UNKNOWN): the
- 1:04:41
- Brennan: benefits on the front end of the financing. And so yeah, I mean, I I largely agree. I think we need a lot of oxygen on the front end, and then we need that there, we need there to be a weaning off plan
- 1:04:54
- Brennan: of subsidized financing.
- 1:04:57
- Unidentified speaker (UNKNOWN): I
- 1:04:57
- Unidentified speaker (speaker_0): so two things come to mind. One is I would add a um an additional piece to John Arnold's uh framework of you need
- 1:05:06
- Unidentified speaker (speaker_0): scientific and engineering institutional capability as the third piece to to build this stuff because if it's low labor and expensive, low labor costs and expensive electricity costs, then sub-Saharan Africa would be full of nuclear plants.
- 1:05:21
- Unidentified speaker (UNKNOWN): Yeah,
- 1:05:22
- Brennan: that's true.
- 1:05:22
- Unidentified speaker (speaker_0): So you there's there's more to the model than than those two things. Um and the other the other piece on the EDF front that I'll call out, and I may be misattributing Attributing this, but I believe it's Peter Drucker who said, show me the incentive and I'll show you the outcome, and I'll tell you the outcome. Right. So if you incentivize and you create some incentive
- 1:05:42
- Unidentified speaker (speaker_0): of, oh, hey, we're going to use uh government dollars to provide cost overrun insurance and make that premium cheaper, well, guess what? You're gonna get cost overruns. And if you if you do some sort of performance-based bonus or tax credit, and I, you know, I don't have the answer. I I wish I did, but I I think we need to scheme up.
- 1:06:03
- Unidentified speaker (speaker_0): on the carrot on the front end, um
- 1:06:07
- Unidentified speaker (speaker_0): not not the uh the cushion on the back end. Right. If if you say, hey, we've got all these cushions and you guys can spend as much as you need to, you're gonna end up with cost plus nuclear. And if we have cost plus nuclear, we're not gonna build this stuff.
- 1:06:21
- Brennan: Yep.
- 1:06:24
- Brennan: Cost plus scares me. I don't like that phrase.
- 1:06:30
- Brennan: Other
- 1:06:30
- Unidentified speaker (UNKNOWN): than Mark
- 1:06:31
- Unidentified speaker (speaker_0): Human's company. Yeah.
- 1:06:32
- Brennan: Yeah.
- 1:06:35
- Brennan: Okay. I know we're running short on time here. Let's finish this up. Lots of other things we could talk about. Let's talk Urenco real quick. What happened? Urenco USDA produced its first cylinder of UF6, enriched to five to ten percent U235. which is considered LEU plus, and UNIS New Mexico, which it calls the
- 1:06:55
- Brennan: first commercial LEU plus production in the Western world. This was announced on November 2nd. The NRC authorized enrichment up to 10% in September 2025.
- 1:07:06
- Unidentified speaker (UNKNOWN): The
- 1:07:06
- Brennan: customer and fabricator aren't named here, but the cylinder ships with others in late spring 2027.
- 1:07:13
- Unidentified speaker (UNKNOWN): Good
- 1:07:13
- Brennan: news here, huh? We're finally getting there on domestic enrichment capacity for LEU plus and eventually Tehalu.
- 1:07:23
- Unidentified speaker (UNKNOWN): I'm
- 1:07:23
- Unidentified speaker (speaker_0): not counting my cylinders before they hatch, but um yeah, it's it's it's fantastic news. I mean, we need the capability. We we need to be able to
- 1:07:33
- Unidentified speaker (UNKNOWN): um
- 1:07:33
- Unidentified speaker (speaker_0): have a domestic
- 1:07:36
- Unidentified speaker (speaker_0): robust front-end fuels fuel cycle.
- 1:07:39
- Unidentified speaker (UNKNOWN): Um yeah,
- 1:07:41
- Unidentified speaker (speaker_0): you know, uh Brennan and I sometimes we we'll do like small digressions for a little educational material. Um one of the small digressions for educational material and a question I have around this announcement, um, your ENCO USA produced produced this. Um
- 1:07:58
- Unidentified speaker (speaker_0): basically the point is if you're going to have unobligated supplies, that'll that applies not only to the material itself, the physical material. So, yeah, you gotta mine it in the US and you convert it in the US, and you gotta enrich it in the US, and you gotta fuel fabricate it in the US. And there, your uranium for unobligated material is US
- 1:08:17
- Unidentified speaker (speaker_0): based. Not only does the physical material have to be unobligated through that supply chain, but the technologies along the way. used to process it also have to be domestically supplied. And so I'm curious on the Urinco, granted, uh they're not the primary suppliers for uh
- 1:08:37
- Unidentified speaker (UNKNOWN): for
- 1:08:37
- Unidentified speaker (speaker_0): unobligated materials, but um, could they be is is kind of the question of are are the centrifuge designs and the parts used in these centrifuges um
- 1:08:46
- Unidentified speaker (UNKNOWN): what
- 1:08:47
- Unidentified speaker (speaker_0): they qualify as unobligated? And so um uh you know typically. tidbit I had learned recently and figured the world should know that the technology itself must also be unobligated um and the materials and the in the equipment used for the processing. So um the term un unobligated when it comes to uranium has uh wide and and reaching
- 1:09:06
- Unidentified speaker (speaker_0): implications.
- 1:09:08
- Brennan: That's interesting, man, and good perspective.
- 1:09:11
- Unidentified speaker (UNKNOWN): Yeah.
- 1:09:11
- Brennan: On the fuel front, also talking Halo.
- 1:09:15
- Brennan: Oaklo announced a deal, Centris, and a really interesting takeaway here. I saw again a shout-out to this Stefan Sumowski. I think he has some great perspectives on X. Six Centris is making about 600 kilograms of Halo per year. And who is getting that Halo? Is the question. You've seen
- 1:09:35
- Brennan: four deals announced with Centrus, Oaklo, X Energy. and Terrace, Radiant by 2030. Who's actually getting the delivery was the question. I thought this was a good question. And clearly not something that was disclosed. So, you know, we talked about the cent the cash on Centris' balance sheet, I'm sure, is earmarked to
- 1:09:55
- Brennan: try to help solve this problem. But it is a good question. Who's getting the allocation by 2030? And if not, where is the incremental capacity coming from?
- 1:10:05
- Unidentified speaker (speaker_0): Will Centrist become the kingmaker of nuclear?
- 1:10:11
- Brennan: Yeah. So yeah, interesting take there, but you know, congratulations for those guys to continue to announce deals. Anything else on that front, Andrew?
- 1:10:19
- Unidentified speaker (speaker_2): Nothing there.
- 1:10:20
- Brennan: Okay. Oaklo Gros Groves One cleared project in Lockhart, Texas. The DOE cleared the final operation. operations for the Groves Isotope Test Reactor. Groves One, this was the reactor used for their criticality, allowing it to move into research, testing, and the training phase. So congratulate congratulations to the Oaklo isotopes
- 1:10:40
- Brennan: team. And another win following up their criticality win earlier this year.
- 1:10:48
- Brennan: Who's going gonna to go critical next, Andrew? Do we know? Something's coming. Yeah, something's coming out of Radiant or last injury. Energy, there's someone else. There's got to be something else coming soon. We need a we need another win on the pilot program.
- 1:11:01
- Unidentified speaker (UNKNOWN): I'll
- 1:11:01
- Unidentified speaker (speaker_0): predict Radiant goes critical by the end of the
- 1:11:03
- Unidentified speaker (UNKNOWN): year.
- 1:11:05
- Unidentified speaker (UNKNOWN): Yeah,
- 1:11:05
- Brennan: and I I guess dissecting that a little bit,
- 1:11:10
- Brennan: they're taking it a step further, right? Which is part of the delay there. Like Radiant is taking it a step beyond just cold criticality, is my understanding. Isn't that correct?
- 1:11:19
- Unidentified speaker (speaker_0): That's correct. They're working on balance plant.
- 1:11:22
- Unidentified speaker (UNKNOWN): Yeah,
- 1:11:22
- Brennan: and I think too, the last energy is doing similar. They're trying to ultimately convert it into a power producing facility. So
- 1:11:31
- Brennan: it's last real point here. I meant to pose this earlier and didn't come back to it. What is the new benchmark for a company starting right now?
- 1:11:42
- Unidentified speaker (UNKNOWN): You know,
- 1:11:43
- Brennan: we had we talked about earlier this this wave of companies that were formed around the peak of inflated expectations. And they were able to point to the pilot program.
- 1:11:53
- Unidentified speaker (UNKNOWN): You know,
- 1:11:53
- Brennan: they were able to roll up their sleeves and say, Hey, we got selected into this thing, and there's this deadline, and whoever gets there is a winner. We'll
- 1:11:59
- Unidentified speaker (UNKNOWN): will
- 1:12:00
- Brennan: be deemed a winner by the investment community. We've seen some companies get there, some not for various reasons reasons. What's the new benchmark? Is it the launch pad program? Because I've talked to another startup company here recently, and they were like, Yeah, you know, we're not doing launch pad because we feel like you had to do the pilot program
- 1:12:20
- Unidentified speaker (UNKNOWN): to
- 1:12:21
- Brennan: reach the criticality date, because the press and everyone was focused on that, and you
- 1:12:25
- Unidentified speaker (UNKNOWN): know,
- 1:12:25
- Brennan: now launch pad. we're not sure it creates the same level of hype around potential fundraising, which is an interesting perspective. Because my response was you should absolutely do the launch pad program. Like
- 1:12:36
- Unidentified speaker (UNKNOWN): the
- 1:12:36
- Brennan: ease of the access to the DOE facilities and everything that that provides is you should absolutely do the launch pad program.
- 1:12:43
- Unidentified speaker (UNKNOWN): See,
- 1:12:43
- Brennan: it led me thinking though, like what is the benchmark between
- 1:12:48
- Brennan: startup today and commercialization? now that the pilot program's gone? And does there need to be some second round of some second deadline set by the DOE, or are these guys going to be able to create their own benchmarks more or less in fundraising?
- 1:13:04
- Unidentified speaker (speaker_0): I would think the latter. I would think that individual companies will have different priorities, and that's probably a good thing.
- 1:13:11
- Unidentified speaker (UNKNOWN): Um and
- 1:13:12
- Unidentified speaker (speaker_0): the two benchmarks that come to mind are going to gonna be Power G. gen, balance plant, um,
- 1:13:17
- Unidentified speaker (UNKNOWN): in
- 1:13:17
- Unidentified speaker (speaker_0): a in a more meaningful way, and um manufacturing capabilities, right? Starting to stand up real manufacturing operations um for for some of these reactors and um beginning serial production because the hard part, the you know, the musk quote is the hard part's not designing an
- 1:13:37
- Unidentified speaker (speaker_0): electric car, it's making a million of them.
- 1:13:39
- Unidentified speaker (UNKNOWN): Right.
- 1:13:39
- Unidentified speaker (speaker_0): The hard part's not actually designing, you know, it is hard, but the harder part is not designing the reactor. It's going to be making a million of them. And so um fortunately here in the US, we have some some really impressive uh talent and deep tech expertise in manufacturing. As much as kind of um maybe less
- 1:13:59
- Unidentified speaker (speaker_0): sophisticated manufacturing has gone overseas in many ways. Um we we do have some great smart talent for for deep tech manufacturing here to to help build these projects out. But um yeah, I'll I'll be looking for announcements around uh standing up manufacturing sites.
- 1:14:16
- Brennan: Yeah. Good stuff, man. Well, this has been a lot of fun. Anything else? I know we we're we we're almost out of time here.
- 1:14:23
- Unidentified speaker (speaker_2): No. Thanks. Thanks, Brennan. This has been we're
- 1:14:26
- Brennan: exploring.
- 1:14:27
- Brennan: Friday, November thirteenth. I'll see you in Monday in Phoenix. Hopefully we can get this out by then. The AS Winter Conference. Man, we're almost at the end of the conference circuit.
- 1:14:38
- Unidentified speaker (speaker_2): See you in Phoenix, Brennan.
- 1:14:39
- Brennan: Thank you for joining another episode of the Nuclear Investing Podcast. Be sure to like, subscribe, and follow, and stay tuned to continue learning about how to invest in nuclear energy. See you next time.
- 1:14:48
- Unidentified speaker (speaker_3): Brennan Moore is the founder and managing partner of Nuclear Inc. Capital Partners. All opinions expressed by Brennan and podcast guests are solely their own opinions and do not reflect the opinion of nuclear capital partners. This podcast is for informational purposes only and should not be relied upon as a basis for investment decisions. Nothing in this podcast is an offer to sell or a solicitation of an offer to buy any security. Nuclear capital partners, its
- 1:15:08
- Unidentified speaker (speaker_3): affiliates, and investors may hold positions in companies discussed on this podcast.