Company Interviews

Central Asia Metals targets 70,000m drilling at Chibougamau to upgrade resource while Kounrad generates $100m annual FCF

28 min Listen to the original Episode page
Copper MiningCentral Asia MetalsKazakhstan OperationsChibougamau ProjectFree Cash FlowMining ExplorationCapital AllocationTier 1 Jurisdictions

Summary

Gavin Ferrar reports that Central Asia Metals (AIM:CAML) is targeting 12,000-13,000 tons of copper production in Kazakhstan, with Kounrad generating approximately $100 million in annual adjusted free cash flow. The company is formalizing a license extension process for Kounrad beyond 2034, citing waste dump recovery that has outperformed original leach curves. In Canada, Central Asia Metals acquired the Chibougamau project, which includes an idle processing plant and four core deposits totaling 6.4 million tons at 3% copper equivalent. Management plans 70,000 meters of drilling to expand the resource, with a new Preliminary Economic Assessment expected by mid-next year. The company has shifted to a self-funded growth model, prioritizing exploration and development while maintaining a 30-50% free cash flow dividend policy.

Episode sections

  1. 0:26 – 0:59

    Kazakhstan Operations and Kounrad Performance

    Gavin Ferrar reports that Kazakhstan operations are performing well, targeting 12,000-13,000 tons of copper production for the year. He highlights Kounrad as the lowest-cost copper producer without byproduct credits, generating significant margins despite a challenging environment and a license expiring in 2034.

  2. 0:59 – 5:03

    Kounrad Life Extension and Cash Generation

    The company is formalizing a process to extend the Kounrad license beyond 2034, as waste dump recovery has outperformed original leach curves, suggesting higher post-2034 production. Kounrad generates approximately 75% of group cash, with first-half adjusted free cash flow of nearly $50 million, implying a run rate of around $100 million annually.

  3. 5:03 – 13:25

    Sustaining Capex and Operational Efficiency at Kounrad

    Kounrad requires only $2-3 million in annual sustaining capex due to the lack of heavy equipment like trucks or crushers. The company is exploring efficiency gains, such as shutting down one of two electro-winning sections if production declines, and considering a second solar farm to mitigate rising energy costs.

  4. 13:25 – 19:42

    Chibougamau Acquisition Overview and Asset Condition

    Central Asia Metals acquired the Chibougamau project in Quebec, which includes an old processing plant (900,000 tons/year capacity) that has been idle since 2008 and requires significant refurbishment. The acquisition includes five ore bodies, with four core deposits (Corner Bay, Cedar Bay, Devlin, Goldeneye) offering a high-quality resource of 6.4 million tons at 3% copper equivalent.

  5. 19:42 – 23:38

    Chibougamau Drilling Plan and PEA Timeline

    Management targets 70,000 meters of drilling in the coming year to expand resource size and increase confidence. A new Preliminary Economic Assessment (PEA) is expected by mid-next year, with an updated Mineral Resource Estimate (MRE) likely in Q3, followed by a feasibility study.

  6. 23:38 – 25:09

    Strategic Shift to Self-Funded Growth and Capital Allocation

    The company has shifted from a dividend-focused base metals producer to a self-funded copper growth company following the Cygnus acquisition. Capital allocation prioritizes exploration in Kazakhstan and Canada, development of Chibougamau, and extending life at Sasa, while maintaining a 30-50% free cash flow dividend policy.

  7. 25:09 – 25:44

    Shibougamau Exploration Upside and Optionality

    Gavin Ferrar highlights the exploration potential at Shibougamau, citing 18 kilometers of strike and highly prospective ground assembled by previous owners. He describes this as a potential 'black swan' event for shareholders, offering significant upside beyond the current development curve.

  8. 25:44 – 26:25

    Diversification and Copper Thesis

    The speaker addresses diversification, noting that while diversification is generally good, the company avoids spreading itself too thin. He asserts that copper is fundamental to society forever and that acquiring a tier-one jurisdiction asset de-risks the business while focusing on copper as the primary metal.

  9. 26:25 – 27:12

    Production Replacement and Self-Funding Model

    Ferrar explains that the company has set itself up to replace production through internal growth rather than external deals. He contrasts the current self-funding junior model with traditional juniors that require market financing, stating that shareholders face minimal dilution risk unless a value-accretive deal arises.

  10. 27:12 – 28:19

    De-risking Through Operational Experience

    The CEO emphasizes that the company's proven operational experience in Kazakhstan and Macedonia de-risks the Shibougamau project. He notes that the same mining and tailings deposition methodologies are being applied, reducing execution risk and providing comfort to investors regarding the growth asset.

Assets discussed

AssetKindStanceContext
CoppercommodityneutralOkay. Look, Kazakhstan's going really well. Uh we've guided 12 to 13,000 tons of copper production this year, and the chaps are doing a fantastic job there, and we're looking to you know sort of hit the middle of the fairway there.
Goldcommodityneutrallittle more gold rich we'll come we'll get to that in time.

“Stance” is how the speakers talked about the asset, not a recommendation.

Claims worth verifying

2026 guidance is 12,000-13,000 tons of copper production from Kazakhstan assets.

Unidentified speaker (UNKNOWN) ·0:26

How to verify: Company press releases or quarterly production reports for H1 2026 and full-year guidance updates. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Kounrad C1 cash cost was $0.91/lb in the first half, up from $0.79/lb, due to a stronger tenge and payroll inflation.

Unidentified speaker (UNKNOWN) ·0:39

How to verify: Check the Interim Financial Results for the six months ended June 30, 2026, filed with the UK FCA or company website. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Kounrad generated an 84% EBITDA margin in the first half of 2026.

Unidentified speaker (UNKNOWN) ·0:39

How to verify: Calculate EBITDA margin from the Interim Financial Results for H1 2026. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Kounrad generates approximately 75% of the group's cash.

Gavin Ferrer ·2:07

How to verify: Review the Interim Financial Results for H1 2026 to compare segment cash flows from Kounrad vs. other assets. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Group adjusted free cash flow was nearly $50 million in the first half, implying a ~$100 million annual run rate.

Unidentified speaker (UNKNOWN) ·5:03

How to verify: Check the Interim Financial Results for H1 2026 for Adjusted Free Cash Flow figures. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Sustaining capex at Kounrad is $2-3 million per year, with no trucks, crushers, or mill.

Gavin Ferrer ·5:43

How to verify: Review the Interim Financial Results for H1 2026 for sustaining capital expenditure breakdown. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Chibougamau processing plant capacity is 900,000 tons per year.

Gavin Ferrer ·17:17

How to verify: Review the Cygnus Metals acquisition announcement or Central Asia Metals press release dated October 27, 2026. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Chibougamau measured and indicated resource is 6.4 million tons at 3% copper equivalent.

Gavin Ferrer ·18:33

How to verify: Review the Chibougamau Mineral Resource Estimate (MRE) technical report filed with Canadian securities regulators (SEDAR+). For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Chibougamau inferred resource is 8.3 million tons at 3.5% copper equivalent.

Gavin Ferrer ·18:53

How to verify: Review the Chibougamau Mineral Resource Estimate (MRE) technical report filed with Canadian securities regulators (SEDAR+). For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Management targets 70,000 meters of drilling at Chibougamau for the next year.

Gavin Ferrer ·19:42

How to verify: Review the Chibougamau exploration program announcement or updated technical report. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

There are 18 kilometers of strike to drill at the Shibougamau project.

Gavin Ferrer ·25:09

How to verify: Review Central Asia Metals' technical reports or press releases regarding the Shibougamau land package and geological strike length. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

The land package at Shibougamau was assembled by previous owners and is described as enormous and highly prospective.

Gavin Ferrer ·25:09

How to verify: Check Central Asia Metals' acquisition announcements or property descriptions for details on the land package history and geological context. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Copper is fundamental to society forever.

Unidentified speaker (UNKNOWN) ·26:07

How to verify: This is a subjective market view; verify by noting it is an opinion, not a factual claim, but cross-reference with long-term demand forecasts from the International Copper Study Group for context. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Shibougamau is located in a tier one mining jurisdiction.

Unidentified speaker (UNKNOWN) ·26:19

How to verify: Consult the Fraser Institute's Annual Survey of Mining Companies or similar jurisdictional ranking indices to verify Canada's (specifically Quebec's) ranking as a tier-one mining jurisdiction. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

The company is self-funding all of its growth and does not need to dip into the market for financing.

Gavin Ferrer ·27:15

How to verify: Review Central Asia Metals' latest quarterly financial statements or cash flow statements to confirm operating cash flow covers capital expenditures without external equity raises. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

The company will not dilute shareholders unless a value-accretive deal is done.

Gavin Ferrer ·27:39

How to verify: Review the company's capitalization table and recent share issuance history to confirm lack of dilution, and check board resolutions for any stated policies on dilution. For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

The company has proven operational experience in building assets in Kazakhstan and Macedonia.

Gavin Ferrer ·27:58

How to verify: Review Central Asia Metals' operational reports or news releases detailing the construction and operation of assets in Kazakhstan (e.g., Kounrad) and Macedonia (e.g., Zletovo). For recent events, verify 2026-08-20 through 2026-11-20. Use another period only when the speaker explicitly names it.

Do your own research

  • Verify the Kounrad license expiration date and extension application status via the Kazakhstani Ministry of Energy or company filings.
  • Check the Chibougamau project's title status and environmental permits in Quebec through provincial mining registries.
  • Review the historical production data and current idle status of the Chibougamau processing plant to assess refurbishment costs.
  • Compare Central Asia Metals' reported sustaining capex at Kounrad against industry benchmarks for similar in-situ leaching operations.
  • Analyze the Chibougamau Preliminary Economic Assessment (PEA) when released to validate the 3% copper equivalent grade and resource estimates.
  • Investigate the 'tier one' jurisdiction classification criteria used by the company for Chibougamau and compare with independent risk assessments.
  • Review the company's dividend policy history and free cash flow generation consistency over the past three years.
  • Check for any conflicts of interest or related-party transactions involving the Cygnus acquisition mentioned in recent proxy statements.
Full transcriptexpand

0:00Gavin Ferrer: Hi, I'm Gavin Ferrer. I'm the CEO of Camel. We are a base metals company with producing operations in Kazakhstan and North Macedonia, and we've recently acquired a development asset in Quebec.

0:12Gavin: Gavin, good to see you. Yeah, well, I think the big move is obviously this acquisition. You've got it over the line now. I do want to talk about that, but maybe just kind of give folks an update on where we are with the Kazakh assets.

0:26Unidentified speaker (UNKNOWN): um, and

0:27Gavin: then we can build it from there.

0:28Gavin Ferrer: Okay. Look, Kazakhstan's going really well. Uh we've guided 12 to 13,000 tons of copper production this year, and the chaps are doing a fantastic job there, and we're looking to you know sort of hit the middle of the fairway there.

0:39Unidentified speaker (UNKNOWN): Um,

0:39Gavin Ferrer: in terms of guidance, and you know, obviously it's the lowest cost copper producer, I think, around that doesn't have byproduct credits. And you know, even in this challenging environment, we're keeping the costs you know at levels where we're generating you know. huge margins so pretty happy with that at the moment the big challenge there is um you know looking towards the license expiring in 2034 we've got a team looking at how we can uh you know we've talked talked about this for a while now but we've finally got guys actually trying to formalize the process of doing that how do we go about doing it what approach do we have to make what documentation is required and studies required in order to do that and looking to extend that license out beyond twenty 2034 thirty four because we do believe those dumps have outperformed so far, or we know they've outperformed so far, and we believe they'll continue to, which means more copper post-2034 than we ever originally envisaged. So we're very pleased with that. And as an operating environment, uh, you know, I think people were sort of maybe raising a bit of an eyebrow because it took us a while to get the approvals for the Shibugumo deal. Um, but we got there in the end, and that's generally the story in Kazakhstan. If you you if you persist, you play by the rules. you you know what's required and you just relentlessly pursue that through the through the right channels, you'll get what you need.

1:46Gavin: Okay, let's this again this is part of the setup for me. Um i uh in situ recovery, copper, you got these dumps and license through to uh twenty thirty four. You think it can extend beyond that, right? So what's the kind of financial contribution fr from a business? that business at the moment and what does that look like beyond 2020?

2:07Gavin Ferrer: Yeah, so look, Conrad is and always has been the backbone of our business. It generates probably around 75% of the cash that we that we do, mainly because it's so low cost. I think it's a bit of a unique project. Um, as you said, it is uh leaching in situ, but we we wait we we're leaching waste dumps, so it's not drilling holes in. into the ground and abstracting solution. We're actually just percolating solution through dumps, collecting it out the bottom and putting it into our plant. Um, in fact, one of our previous shareholders was at a an event and he said they drizzle some stuff on top and cash comes out the bottom. It's not quite as simple as that. We all wish it was. We've got some highly talented uh technical people all running their the thing there, constantly fine-tuning the application rate. rates, the you know, to keep a constant flow of copper in solution into the plant. And yeah,

2:57Unidentified speaker (UNKNOWN): as

2:58Gavin Ferrer: I said earlier, we've so far outperformed. You know, we had um leech curves that we generated through all the test work, which included bench scale, you know, commercial scale stuff on a pilot plant basis.

3:08Unidentified speaker (UNKNOWN): Yeah.

3:08Gavin Ferrer: And then also learning from you know every previous cell as we go what we expect the leeches to uh leech leach curves to be. And

3:16Unidentified speaker (UNKNOWN): you

3:16Gavin Ferrer: know, generally speaking, over the east and the western dumps as we break them up, we have outperformed. So um, you know, these leech curves do mature over time. So what that means is the rate of copper recovery does actually reduce um as as these these dumps mature, and that's normal for any heap leach.

3:32Unidentified speaker (UNKNOWN): Um

3:33Gavin Ferrer: and we are heading into the sort of period now where overall production is going to. decline. And I think we've always been open and honest about that. And in fact, there's

3:42Unidentified speaker (UNKNOWN): a a

3:43Gavin Ferrer: study we put out in August this year that'll show the the sort of production profile over the next few years. So we do think there are opportunities to maybe enhance that profile, but we are working on those. That's going to take a little bit of MA trying And to get some more solution into the plant somehow. So we've got a a few years to execute on that as well. So happy to continue producing as we are. Um it'll be you know hugely cash generative all the way through to the end of the life. Um Can

4:10Unidentified speaker (UNKNOWN): you give me a number

4:11Gavin: though? Because I'm trying to work out the kind of free cash flow position there. So

4:14Unidentified speaker (UNKNOWN): you've got some su you've got some

4:15Gavin: choices to make. You you 'cause there's some trade off studies to be done. Whether or not you do try and extend beyond twenty thirty four, if you think it's profitable, why would you not, of course? Um but what would you what's your expectation of um what you're doing with the cash now? Because obviously th that's a long ways away. You've just made a big acquisition. You can gr I uh drive some efficiencies with your new acquisition, I'm sure, with that cash flow, but at some point you're gonna need to reinvest into back into Kazakhstan on on the copper corporate side if you do extend the the the license, presumably. So tell me your thinking.

4:54Gavin Ferrer: There's a lot of questions in there, but I'll start with the first one. You know, the cash flow that we receive from Conrad um amounts to around seventy-five percent of what we generate.

5:03Unidentified speaker (UNKNOWN): Uh

5:03Gavin Ferrer: if you look at our interim results we put out in September, we produced just under fifty million dollars of free cash flow, and the first half is always a little bit sort of cost heavy versus the second half. So you know if you just double that you get to about a hundred so coonrad is worth 75 of that and if commodity prices stay more or less where they are today we expect that to continue for at least another two three years and then you'll see the decline in production and you can make your make do the maths from there. So how do we deploy that cash? Kunrad Route itself as an asset is fully invested. So we have a run rate of around two to three million dollars with sustaining capex there, and what that is is just laying more of this pipework and maintenance, maybe replacing the odd piece of kit, for example, we're replacing some boilers, we've replaced pumps, you know, that sort of thing. But there's no heavy equipment there, there's no trucks, there's no crushers, there's no big mill. So that's why the costs are fairly low

5:57Unidentified speaker (UNKNOWN): of

5:57Gavin Ferrer: sustaining that operation all the way through. So come, you know, assuming we get the license extension, there's no big cap. capex hit there.

6:03Gavin: Okay.

6:04Gavin Ferrer: So we don't need to spend any more capital. The one thing we may spend capital on is another solar farm.

6:10Gavin: Okay.

6:11Gavin Ferrer: And we we spent around $5 million on something that does 4.7 megawatts. And that's now paying for itself because we have seen in energy costs go up around the world. And it was always a more sort of environmental greenhouse gas mitigation project. But when we've seen power prices go

6:26Unidentified speaker (UNKNOWN): up,

6:27Gavin Ferrer: that thing is now in the money

6:28Unidentified speaker (UNKNOWN): deeply

6:29Gavin Ferrer: and

6:29Unidentified speaker (UNKNOWN): you

6:29Gavin Ferrer: know so therefore we could justify doing a second one and that's the only

6:33Unidentified speaker (UNKNOWN): it

6:33Gavin: so there no no big major apart from that obviously the energy that makes makes sense and no big kind of capex outlet in terms of the kind of expected increase in the the opax numbers do you will will it be as profitable like a

6:45Gavin Ferrer: look I mean obviously if your production comes down and we keep the cost base the same the unit costs are going to go up. Yeah. But if you think about where we are, which is ninety-one cents a pound versus a copper price, yesterday I checked, haven't checked this morning, was five dollars sixty. So you've got quite a lot of leeway within there, but that doesn't mean we're not going to respond to the reducing units that we're going to be producing and trying to figure out where we can drive efficiencies. Now, you know, an obvious one is we've got two separate electro-winning sections. So if production falls below the aggregate capacity of those two, we can shut one

7:18Unidentified speaker (UNKNOWN): down.

7:19Gavin Ferrer: So there is opportunity to save cost on the way through as we

7:23Unidentified speaker (UNKNOWN): have.

7:23Gavin: But

7:23Unidentified speaker (UNKNOWN): are there any any

7:24Gavin: kind of uh uh uh uh implications in terms of remediation uh there?

7:29Gavin Ferrer: No, in fact um look again, uh these were waste dumps. So what we're really doing, and it's kind of neat to think about it this way, is we're accelerating what would otherwise be an environmentally polluting process. So you would have leached the copper into the groundwater anyway. What we're doing is accelerating that process and collecting the copper out of that solution. So we're doing the state a favour effectively by we're gonna leave behind something that is, yes, it might it may, you know, give up some sort of bits and bobs over there, but nowhere near to the levels it would have otherwise. And if you think about it, we've got a pretty small footprint in terms of our plant, and then we've got all this plastic dripper pipe running on there. So it's effectively just removing that, closing the plant down, you know, and

8:15Unidentified speaker (UNKNOWN): I

8:15Gavin: guess where I'm heading where I'm heading, so there's a logic to this. So I'm trying to work out if with increasing unit costs, etc., et cetera, is what that kind of um what the margin's gonna look like moving forward and then what do you do with that margin? because we'll talk about we are going to talk about Shapugum in a second, but I'm more interested in the kind of change in mindset of of the team going, actually this is a nice that's what you've known been known for, this this Institute League pro pro project in Kazakhstan, right? And and the lab and the Zing as well. But it's where does this company go? How does it

8:44Unidentified speaker (UNKNOWN): So if you if you

8:45Gavin Ferrer: if you just isolate it to Kazakhstan, which is what your question was, you know, we've got an amazing operational base. there. So we've got a a, as I said earlier, a talented group of technical people, but also backed up by really good administrative people. So if we did find through

9:00Unidentified speaker (UNKNOWN): um

9:01Gavin Ferrer: inorganic kind of growth um more material to put through that plant, we're all set up to do that.

9:07Unidentified speaker (UNKNOWN): So

9:07Gavin Ferrer: that's not a problem. We've also got a very good exploration team operating right now, and we actually released some pretty positive results in September for the you know after our maiden drilling campaign. We look like we've hit something. We were disappointed not to get another rig on site at Ujnoya this year, probably going to come early next year. And those guys can leverage off of all of the operational experience we've got and all of the kind of infrastructure, if you would like, around Kunrad that they can use. So lawyers, accountants, you know, procurement, all that sort of stuff, if we are successful. in the expiration side as well. So we think Kazakhstan is a good jurisdiction. We've operated there, you know, easily for yeah about fourteen years now. I think we we we started building sixteen years ago. And uninterrupted operation. We've had um you know very good relationship with all the local authorities, local communities. Local community, So our license licensed to operator operate is good. We understand how to go through permitting, we understand how to apply for licenses. So we do see it as a core part of our growth strategy, you know, to keep investing. And some of yeah, and maybe you know, as that margin decreases, you are going to see across the group, you know, other things coming on. For example, Shibugomo, which I know you're dying to ask me about.

10:18Unidentified speaker (UNKNOWN): Well,

10:18Gavin: I

10:18Unidentified speaker (UNKNOWN): I I am. But

10:19Gavin Ferrer: I think I think if we just you know, and I I understand why you're interrogating are you this, because it is a an unusual situation for a mining company. And every every mining company has to face it. at some point where you've got an asset that is going to you know hit declining production and ultimately close down. But I mean, we see, compared to what the market sees right now, we see much more upside at Cunrad because we do know that we're going to produce a lot more copper than we ever thought we would.

10:42Unidentified speaker (UNKNOWN): Um

10:42Gavin Ferrer: and it's going to extend beyond that 2034. So, you know, from a value perspective, that is going to be, you know, and but we've got to show the market. And I understand, I get that. There's we got to be these cash. catalysts.

10:51Unidentified speaker (UNKNOWN): But if

10:52Gavin Ferrer: I was a shareholder only looking at at that I'd be looking at production levels, I'd be looking at uh expiration successes, and I'd be looking at that license extension with potentially some other material coming into the into play in Conrad's

11:05Gavin: and it's important to say that because um you're being valued on that predominantly at the at the moment. People m perhaps can see the potential uh uh of the shopomi deal, but you've got to go show that as well. So thinking of life beyond twenty thirty four is important. So can you just get again you know you did cover it, but can you remember exactly what you have got to get over the line to be able to understand if you will be able to go forward past twenty thirty four in Kazakhstan.

11:32Gavin Ferrer: I think it's a it's literally just a bureaucratic process.

11:35Gavin: Okay.

11:35Gavin Ferrer: Yeah. And you know to we have not um previously focused on it and we started focusing it on on its this about two years ago when we were starting to get a real handle on this outperformance in the dumps and going, Okay,

11:48Unidentified speaker (UNKNOWN): if

11:48Gavin Ferrer: we go back a few years we'd go, Hey, look, you know, these leech curves are all asymptotic. By the time it gets to twenty thirty four there'll be some copra coming out, but it's probably not gonna be of interest to us 'cause it'll 'cause it'd be such a low level. What do we do? Do we just give it to the staff? Do we hand it back to the local community? Do we do something because you know a thousand tons of copper every year is not going to be that interesting in the context of a business that, you know, we're looking to produce 25,000 tons plus.

12:13Unidentified speaker (UNKNOWN): Now

12:13Gavin Ferrer: when we look at it, we're going, oh actually it's going to be multiples of that thousand.

12:16Gavin: Yeah

12:17Gavin Ferrer: you know, yes we should be much more interested in it. Oh what do we have to do? Yeah.

12:21Unidentified speaker (UNKNOWN): Set

12:21Gavin Ferrer: the guys a at task going and you know we're hoping that by the end of this year we'll have an answer as to you know what we have to do. And we'll

12:27Unidentified speaker (UNKNOWN): inform the

12:27Gavin Ferrer: market as to what the timetable is gonna be and

12:30Unidentified speaker (UNKNOWN): you know,

12:31Gavin Ferrer: i it may be we need to do further environmental studies. But if you think about it from the local community, the local authorities, local government and regional government, and even the feds,

12:41Unidentified speaker (UNKNOWN): you're

12:41Gavin Ferrer: gonna go, Hey, you're employing three hundred people, you're producing money, you're investing in the community, why would we not extend the licence? license?

12:47Unidentified speaker (UNKNOWN): Yeah.

12:48Gavin: Okay. Just wanna want to cover it off because look as it's I I a that it your next okay, you're being your company's being valid on what you've got at the moment in Kazakhstan. You're generating cash, I get it. It's then going to be a case of what do you do with that cash? I know you've got the dividend policy in in place, which is great, but that you know, in terms of what is the best use of that capital, that's what I'm interested in. And obviously there's the Chibug. Look, you've got Scotland as well, but that's a long lead item. Chibugamy, what is your expectation? expectation of what that project or pro you've got five deposits there, what those projects are going to do for the company?

13:23Gavin Ferrer: So look,

13:25Unidentified speaker (UNKNOWN): we

13:25Gavin Ferrer: played devil's advocate here a little

13:26Unidentified speaker (UNKNOWN): bit,

13:27Gavin Ferrer: or set up a straw amount of her. So if we do imagine that 2034 is the cutoff date and it's done, right? And you've got 2034 at Forward SUSA, Sasa, coincidentally, as well on their reserves, although that is very likely to extend. Shibugamo, once it's in operation, will replace both those assets from those five deposits you mentioned.

13:46Gavin: That might be worth reminding people what exactly you picked up, what data you can

13:48Unidentified speaker (UNKNOWN): have

13:49Gavin: on it now.

13:49Gavin Ferrer: So let me just I'll get to that in

13:50Unidentified speaker (UNKNOWN): a sec.

13:51Gavin Ferrer: So so to answer your question, what we're doing right now is shepherding the company. Um, you know,

13:56Unidentified speaker (UNKNOWN): and

13:56Gavin Ferrer: we're also more grown up as a business now because we have to make those decisions in terms of allocating every dollar, where's the best? bang for the buck for the shareholders? Is it into Kazakh exploration? Is it into Canadian exploration? Is it into development work on Shibugumo? Is it into drilling at Sasa to extend the life? So these decisions all need to be. So the finance team's kind of working pretty hard and you know they're doing all the kind of ROI calculations on all these things every time we need to make a a decision now. So you know we're we well informed and we will be making those decisions as we go. forward. And it's a case of allocating it, you know, you're not gonna stop exploring at Sasa because, you know, it is gonna extend this narrow vein and off we go. So the the sort of out the sort of use of the cash over the next four years is gonna be um we start at the early end. So there'll be exploration in Kazakhstan.

14:43Unidentified speaker (UNKNOWN): Um

14:43Gavin Ferrer: probably some exploration at Sassa Sasa to extend the extend the life there. We'll have development of the Shabugam Shabuga Masset, asset, which by which I mean engineering studies, you know, publishing studies, continuing with you know a whole bunch of technical engineering design work and you know option studies and that sort of thing. And then exploring in Canada as well. So those are the sort of things that are going into the ground, if you like. The other thing we've got the um got to look after our shareholders. So we've got the dividend policy that you mentioned, which is 30 to 50 percent of free cash flow, and then live. last but not least is building up a little bit of a um

15:18Unidentified speaker (UNKNOWN): a

15:18Gavin Ferrer: bank balance to finance the construction. That should be remembered when that comes. So it's a you know

15:25Unidentified speaker (UNKNOWN): a

15:26Gavin Ferrer: finance team is working pretty hard on figuring all this out. And we know as I said earlier, we're getting around a yeah,

15:32Unidentified speaker (UNKNOWN): quarter

15:32Gavin Ferrer: a hundred every year coming in for the next few years. So what do we how do we allocate that money?

15:38Unidentified speaker (UNKNOWN): Yeah,

15:38Gavin: okay.

15:39Gavin Ferrer: in order to sort

15:40Unidentified speaker (UNKNOWN): of

15:41Gavin Ferrer: generate enough interest in in well sort of not in generate interest but generate like actual value in the ground, but also with that little capital return coming to shareholders as

15:52Unidentified speaker (UNKNOWN): well.

15:52Gavin: Okay. So come back to the question of what exactly have you picked up? What do you know about it?

15:57Gavin Ferrer: So we spent a week as a management team out there probably two, three weeks ago. And um first of all, there's no buyer's remorse, so that's good. This is the first time we've gone out as owners. We clearly made several trips beforehand doing due diligence. And the purpose of the workshop that we ran there was to go, what what what's happening over the next 14 months? Now this is a a team that has gone from having a budget um constrained by junior capital markets. You know, these guys generally raise some capital, do a program, generate a study, and off the back of that go and raise another set of capital, you know, another bar of capital to further the project. We've now got a team that's very excited on the ground because they don't have to go through these uncertain funding cycles in order to finance what they want to do. And we've also got some cash in the bank. We've got almost $100 million in the bank, plus also this cash generation that's coming. So we can actually afford to do a whole lot more and therefore accelerate development better than it would have been in other hands. So what we've ended up coming up with there, so what we've bought is there's what we call the Copper Rand Mill, and that is a an old operating uh processing plant that produced uh copper concentrate, copper gold concentrate, with two tailing tailings stams. dams.

17:14Unidentified speaker (UNKNOWN): Okay,

17:14Gavin Ferrer: so that's the brownfields element.

17:16Gavin: What size is that plant?

17:17Gavin Ferrer: 900,000 tons a year.

17:19Unidentified speaker (UNKNOWN): Okay. All right,

17:20Gavin Ferrer: but it's in, it hasn't hasn't operated since 2008. Uh, apart from the steel work, the concrete, and a few steel tanks, it's in pretty poor condition, so it's going to need a huge amount of refurbishment. But that's an opportunity as well to modernize it. You know, new pipework, new wiring, new control systems, so that you can, you know, all the automation and that's available these days, um, you know, overlaid with all of the technology that we've got to make make sure it's a highly, highly efficient plant.

17:47Unidentified speaker (UNKNOWN): Um

17:48Gavin Ferrer: so that's the kind of and then underneath that is the old copper and mine, um

17:53Unidentified speaker (UNKNOWN): which

17:53Gavin Ferrer: is an exploration target in its own right. But we've also bought a mineral resource, so there's no discovery risk we're taking here. So the mineral resource is is uh is across five ore bodies as you said but the main one is called corner bay and there's one called Cedar Cedar Bay, uh Devlin and Goldeneye effectively the core four that will

18:12Unidentified speaker (UNKNOWN): and

18:12Gavin: Joe Man. Well

18:13Gavin Ferrer: Joe Man

18:14Unidentified speaker (UNKNOWN): is a little further to the south that's a

18:16Gavin Ferrer: little more gold rich we'll come we'll get to that in time. There has been some good drilling on there like really good intercepts. Yeah um it's a little further away so we need to do a bit more work on that. But in order to as I said get to a cash flow as quickly as possible, those are the four that we're going to do.

18:31Unidentified speaker (UNKNOWN): And so the resource

18:31Gavin: size and the grades?

18:33Gavin Ferrer: So the measured and indicated resource is uh six and about six point four million tons, and uh copper equivalent grade of three percent. So that's kind of what turned our heads in the first place. This is a high-quality mineral resource. Yeah. And you could probably you know build a mine off the back of that as it is. There's another 8.3 eight point million three tons. of inferred resource on top of that, um, at a copper equivalent grade of three and a half percent. So again, you know, really good sort of total global resource that you've got to play with there. And yeah, there's all underground.

19:03Gavin: Okay. So

19:04Gavin Ferrer: down to depths of uh 1,200 meters, you know, that sort of thing, which again in Canada is not unusual. These are steeply dipping all ore bodies, so you know pretty simple mining, uh using the methods actually that we use at uh at Sasa. So you know all that operational knowledge that we have. So on Corner Bay, there's uh effectively an expiration decline going in. Goldeneye, the same thing. Yeah. Um so it's a case of dewatering that, looking at uh accessing those all bodies and then building out the the uh the exp the sorry the access to these ore bodies as soon as we can. We've then um

19:41Unidentified speaker (UNKNOWN): so

19:42Gavin Ferrer: look taking those four deposits I mentioned uh we've targeted around 70,000 meters of drilling for next year.

19:48Unidentified speaker (UNKNOWN): Okay. So we've

19:49Gavin Ferrer: got a drill program that you can effectively split into two. First half of the year is really increasing the size of the re size of the resource base. Yeah

19:55Gavin: okay

19:56Gavin Ferrer: so targeting the depth extensions of um of three of those ore bodies plus the strike extension of golden GoldenEye eye as well. And then the second half of the year is really being is going to be tightening up on that resource confidence and infill drilling at all four. So it Devlin's a bit of a different looking ore body as well. But it is important and it's shallower. So you know, between those four ore bodies, we'll by the end of the year we'll have produced a new PEA that'll come out probably middle of the next year. So again, I think that's going to gonna be really informative. for the market to figure out what you know operating cost, CapEx is, production run rates, those

20:32Unidentified speaker (UNKNOWN): are the same. So not

20:33Gavin: all of that seventy thousand is going to make it into that PEA.

20:36Unidentified speaker (UNKNOWN): No, right.

20:36Gavin Ferrer: So s what what we're gonna do is kind of use the existing resource build the PEA off the back of that. Okay. Because um, you know, whilst While Cygnus was owning it, they were only running one rig, they didn't really drill enough to kind of infiltrate. infill as much as they could to yeah, really update the

20:53Unidentified speaker (UNKNOWN): what happened there,

20:53Gavin: were they

20:54Unidentified speaker (UNKNOWN): just

20:54Gavin: cash constraint or

20:55Unidentified speaker (UNKNOWN): think so. Right,

20:55Gavin: okay.

20:56Unidentified speaker (UNKNOWN): And

20:56Gavin Ferrer: I think the deal hit them as well, and they were sort of, you know.

20:59Gavin: Yeah, okay.

20:59Unidentified speaker (UNKNOWN): Yeah.

21:00Gavin Ferrer: So um look that's fine because we will have a an an updated MRE out shortly after, probably Q three, MRE meaning mineral resource estimate, um for those non non-miners miners in your audience. Um and that will will should be if you know what we discussed a couple of weeks ago, it should be larger and at a higher confidence than what we've got now. And then with these option studies going on in parallel, we will come to December next year with a very firm view of what this project can be and then drive it into a feasibility study.

21:30Gavin: Interesting. Okay. Right. So b business as usual in terms of producing cash. Kazakhstan.

21:36Gavin Ferrer: Correct.

21:36Gavin: With the option of extending out to continue. that ATM of yours. And then to booking me with with with the four kind of core copper projects, the idea is to kind of get in a fit state where you can make a decision as to the kind of sequencing of how you get after it.

21:51Gavin Ferrer: Exactly.

21:51Gavin: Okay. But one central plant.

21:54Unidentified speaker (UNKNOWN): So we continue to go

21:55Gavin Ferrer: with the Hubbins Burke model. And that's why we haven't mentioned Joe Man too much, because we need to figure out whether that can actually be part of that. Because it

22:02Unidentified speaker (UNKNOWN): is

22:02Gavin Ferrer: a little further away.

22:03Gavin: Yeah. Um

22:05Unidentified speaker (UNKNOWN): well

22:05Gavin: it's gold as well. And

22:06Unidentified speaker (UNKNOWN): it's gold. But I

22:07Gavin Ferrer: think that's not a problem. There's uh

22:08Unidentified speaker (UNKNOWN): there's also

22:08Gavin: tolling in Quebec, right?

22:10Gavin Ferrer: Look, I think what what what the real opportunity here for us, Matt, at Shabugumo is if we can get this asset up and running as quickly as possible. Yeah. We've kind of almost got first mover advantage there. We'll be one of the f one of the first copper producers in Quebec for a long time. Yeah. They've got the horn smelter there, so

22:28Unidentified speaker (UNKNOWN): that's I

22:28Gavin Ferrer: think Glencourt owns that. And there's a rich mining history, but in terms of just pure base metals, there's not a lot going on. There's lithium, there's gold, there's all these things. So it's an exciting jurisdiction from that perspective. But in terms of that camp uh around Shibugamo, to get up and running early will give us a huge advantage in terms of um you know access to labor, uh, you know. curry favour with the government and to consolidate the camp ultimately as well. So that's our our views. That you know, as I said earlier, if we switched off Sasa and and Kunrad at the end of twenty thirty four, Shibugumo would replace all of that, but we want to grow this business. So we definitely want to go out and do more deals in future and consolidate around that Shibugumo Shibugmo camp. Plus also, you know, we are looking at some more advanced stuff in Kazakhstan as well.

23:14Gavin: What's changed? What's changed in your thinking, right? You were happy carrying on business in in in uh in Europe or Eastern Europe. Um and then you said decided you needed a project in Can well like I say, a little one in Scotland, but that's expression. In Canada. What what problem were you trying to solve? What was the board talking about said let's do this?

23:38Unidentified speaker (UNKNOWN): I

23:38Gavin Ferrer: think. the company has moved a long way in the last couple of years. And as we've been telling investors we've been meeting, we cut we're at an inflection point now. So

23:48Unidentified speaker (UNKNOWN): we've

23:48Gavin Ferrer: gone through a lot of pain in terms of sorting out Sasa. We took the impairment on that in March. We've you know, I think we've spoken about it to your audience before. We've we've really cleaned house there, we've got new management, we've got a a reduced number of people in the workforce, you know, a better practices across a number of different areas, mining, processing, you know, exploration. So I think we've set that up quite nicely and it's sort of coming out of the turnaround pretty well. So that that has been a focus. Um, you know, the the other thing is um

24:19Unidentified speaker (UNKNOWN): you know,

24:20Gavin Ferrer: current is what it is, we've spoken about that.

24:22Unidentified speaker (UNKNOWN): Uh

24:22Gavin Ferrer: the other thing was capital markets. So we had this dividend policy, but still,

24:26Unidentified speaker (UNKNOWN): we're not going to be able

24:27Gavin Ferrer: we ended up in a position where we were paying a long way outside of that in order to generate returns. So the we'd always had this growth aspiration. The board has always been keen on growth, but I think what we needed to do was kind of signal to the market that that was really our priority. So we've brought the dividend back into policy, and the last dividend payment was 40% of free cash flow. So again, right down the middle

24:48Unidentified speaker (UNKNOWN): there.

24:49Gavin Ferrer: And moving forward. having missed out on an acquisition opportunity last year, you know, to actually execute on something that is really exciting. Now we were drawn by the quality of the resource there, you know, high grade copper in a good jurisdiction. It really what it does for our business is add a huge amount of growth, potential to the business, and therefore potential upside to that share price. Not only in terms of advancing shibugumo Shibugomo along the development curve. into feasibility study and then into production, but also, you know, we've got 18 kilometers of strike to drill and have you know the land package that is been assembled by the previous owners is enormous and all in really highly prospective ground. So we think from a

25:32Unidentified speaker (UNKNOWN): from

25:32Gavin Ferrer: an optionality perspective, this is for the first time that we're really offering our shareholders that kind of real kind of black swan event. in terms of finding something and making a discovery, uh, either in Kazakhstan or in Canada.

25:44Gavin: Okay, so there's a kind of de-risking component to this as well. I suspect one that grows.

25:48Unidentified speaker (UNKNOWN): A little bit in terms

25:49Gavin Ferrer: of diversification is always good. What you've got to be careful of is you don't spread yourself too thinly. But

25:54Gavin: you're not diversifying them at all.

25:55Unidentified speaker (UNKNOWN): We're

25:55Gavin Ferrer: not we we're sticking to our net expenses. We know we look we Copper's, we think, has got a great thesis. It's going through some interesting times in the macro. story at the moment is a little bit kind of schizophrenic, right? People were,

26:07Unidentified speaker (UNKNOWN): Oh

26:07Gavin Ferrer: yeah, it's all about this, it's all about that. But copper's gonna be fundamental to society forever. And we we're very confident in that. So buying uh something with you know copper as the main metal is was was an objective of ours.

26:19Unidentified speaker (UNKNOWN): Um

26:19Gavin Ferrer: and the fact that it's in a tier one mining jurisdiction does de-risk the business, for sure. I think you

26:25Unidentified speaker (UNKNOWN): know

26:25Gavin Ferrer: we'll we'll all agree that. But ultimately, um, you know, we've got to replace the production like any mining company does. You've got to go through a period of replacement. And I think we've set ourselves up really nicely now

26:37Unidentified speaker (UNKNOWN): that

26:37Gavin Ferrer: while I talk about doing other deals and consolidation,

26:40Unidentified speaker (UNKNOWN): uh,

26:41Gavin Ferrer: we've got a great opportunity within the business now just to completely replace everything we've had, as I said, Shibugume replaces the other two, with the opportunity. to expand that resource base across the group in Kazakhstan and in Canada.

26:56Gavin: So what okay, you're talking to existing shareholders and maybe folks look looking in, maybe two slightly different messages there is like the company profile two years ago.

27:06Gavin Ferrer: Two years ago, we were a dividend paying company with producing assets.

27:10Gavin: How do I view do you now? So

27:12Gavin Ferrer: now we're kind of a unique junior company where we are basically. self-funding all of the growth. A traditional junior mining company would be dipping into the market from time to time to finance the next step, the next step. We don't need to do that. So shareholders can comfortably enter our register, you know, comfortable in the knowledge really that we are not going to be diluting them unless there's a value Value accreditive a creative deal to be done. That's the only other time we go out and do a capital raise. Whereas we've and we've got all of this growth potential within our portfolio that we can self-finance, or using the clean balance sheet as well. So I think that is the real value proposition for people now is you know, you've got solid operating experience that's going to be applicable to Shibugamo, and therefore from a de-risking perspective, you've got a a a fantastic growth asset that is not really looking at a huge amount of financing risk, execution. risk we've kind of proven ourselves in terms of building stuff in Kazakhstan and in Macedonia and we're using the same methodologies in terms of mining and tailings deposition. So all of that knowledge is applicable to Shibugumo, which again from a risk perspective should give people a lot more comfort.

28:16Gavin: Appreciate huh thank you.

28:18Gavin Ferrer: Thank you very much.