German battery developers face Dec 31 deadline for FID to avoid grid fees, with realistic deployment forecasts far below queue sizes.
Summary
Speakers discuss the urgency of Germany’s December 31st deadline for battery developers to make a Final Investment Decision (FID) to secure a 20-year exemption from capacity-based grid fees under the 'Agnes' reform. Marie Sophie Braun argues that the reported 300 GW of grid connection requests is an unrealistic 'battery tsunami,' forecasting actual deployment at only 50–70 GW by 2040–2060 due to merchant market dynamics that punish overbuild. Keon Energy’s transition from developer to operator is highlighted as a strategy to shape regulatory frameworks and prove storage affordability without state financing. The episode details the critical need for clear Flexible Connection Agreements (FCAs) to ensure debt financeability, contrasting this with the risks of unlimited curtailment. Finally, speakers note regulatory misalignments between Transmission and Distribution System Operators regarding ancillary services and voltage stress.
Episode sections
- 0:00 – 1:18
The German Battery Deadline and Grid Fee Exemption
Speakers outline the December 31st deadline for Final Investment Decision (FID) and 50% component order commitment to avoid capacity-based grid fees for 20 years. Assets must be operational before August 2029 to qualify, despite grid usage rules not being finalized until after the commitment.
- 1:18 – 3:30
The 'Battery Tsunami' vs. Realistic Deployment
Marie Sophie Braun characterizes the ~300 GW of grid connection requests as a queue artifact rather than realistic deployment. She forecasts 50–70 GW by 2040–2060, arguing that merchant market dynamics and margin compression from overbuild disincentivize massive deployment.
- 3:30 – 9:01
Keon Energy’s Transition from Developer to Operator
Keon Energy shifted from project development to independent flexibility provision to shape regulatory frameworks and demonstrate storage affordability without state financing. This required building in-house asset management capabilities and navigating new regulations like NIS2.
- 9:01 – 12:18
Risk Management and the Agnes Grid Fee Reform
The 'Agnes' reform ends the grid fee exemption for storage if FID is not taken by year-end. Speakers note that while the business case remains viable, the tight seven-month timeline requires aggressive risk management to close financing and secure supply agreements.
- 12:18 – 14:25
Dynamic Grid Fees and Congestion Management
Dynamic and locational grid fees are discussed as mechanisms to incentivize storage for congestion resolution. Speakers express concern that non-remunerated congestion management could hinder financing, as integrating storage into redispatch processes is still developing.
- 14:25 – 17:04
Flexible Connection Agreements (FCAs) and Financing
The industry supports FCAs allowing some non-remunerated redispatch but opposes unlimited curtailment without reimbursement. Such unlimited risk is deemed unfinanceable because debt providers require clear definitions of asset availability.
- 17:04 – 20:04
Route-to-Market Providers and Benchmarking
Keon Energy splits its portfolio across multiple route-to-market providers to benchmark performance on live assets. The focus is on partners ensuring physical delivery and uptime, prioritizing this over minor algorithmic optimizations.
- 20:04 – 31:04
TSO vs. DSO Dynamics and Ancillary Services
A misalignment exists between TSOs and DSOs regarding ancillary services. TSOs benefit from services like frequency control, but these can cause voltage issues for DSOs, who receive no compensation for the resulting grid stress.
- 31:04 – 31:08
Closing Remarks
The speaker expresses hope that the audience can make necessary decisions to get projects online and thanks the listeners.
Claims worth verifying
German battery developers must make a Final Investment Decision (FID) by December 31st and commit 50% of component orders to avoid capacity-based grid fees for 20 years.
Unidentified speaker ·0:16
How to verify: Check German grid fee regulations (Agnes reform) published by the Federal Network Agency (Bundesnetzagentur) or Keon Energy’s investor presentations regarding the 2029 deadline.
Grid connection requests for battery storage in Germany totaled approximately 300 GW.
Unidentified speaker ·2:15
How to verify: Review grid connection queue data published by German Transmission System Operators (TSOs) or Distribution System Operators (DSOs).
Forecasted battery storage deployment in Germany is between 50 and 70 GW by 2040–2060.
Unidentified speaker ·2:29
How to verify: Check energy market forecasts from agencies like Fraunhofer ISE, BSW-Speicher, or Keon Energy’s internal reports.
Keon Energy started with smaller mid-voltage projects to build in-house operational skills before scaling to larger greenfield developments.
Unidentified speaker ·6:04
How to verify: Review Keon Energy’s project portfolio history or corporate case studies detailing their development pipeline.
The 'Agnes' reform is a Germany-first initiative by the German regulator to standardize grid fees for all asset types.
Unidentified speaker ·9:27
How to verify: Search for official documents or press releases from the Bundesnetzagentur regarding the 'Agnes' grid fee reform.
Redispatch costs in Germany are increasing significantly due to congestion between northern production and southern consumption.
Unidentified speaker ·25:17
How to verify: Analyze annual reports from German TSOs (e.g., TenneT, 50Hertz, Amprion, TransnetBW) detailing redispatch volumes and costs.
The EEG (German Renewable Energy Sources Act) includes a regime where renewable assets in highly congested areas face non-remunerated curtailment for a limited number of hours over six years.
Unidentified speaker ·27:49
How to verify: Review the text of the German EEG (Erneuerbare-Energien-Gesetz) regarding curtailment rules and compensation limits.
MISPL is a German regulation defining metering concepts that enable proper collocation of renewable generation and storage.
Unidentified speaker ·29:50
How to verify: Search for 'MISPL' (Mess- und Steuerungsleittechnik für dezentrale Erzeugungsanlagen) regulations or guidelines from the VDE or Bundesnetzagentur.
Do your own research
- Verify the specific text of Germany's 'Agnes' grid fee reform and the December 31st Final Investment Decision (FID) deadline requirements.
- Check current grid connection queue data from Transmission System Operators (TSOs) and Distribution System Operators (DSOs) in Germany to assess the '300 GW' claim.
- Review Keon Energy’s corporate filings or press releases to confirm their transition from developer to operator and their current project pipeline.
- Analyze draft or final Flexible Connection Agreement (FCA) templates from German grid operators to identify clauses regarding curtailment and compensation.
- Research NIS2 (Network and Information Security) regulations and their specific impact on energy storage asset management in the EU.
- Investigate the regulatory framework for ancillary services in Germany to understand the compensation mechanisms (or lack thereof) for DSOs regarding voltage stress.
Full transcriptexpand
- 0:00
- Unidentified speaker: I'm your host, Ed Porter.
- 0:01
- Unidentified speaker: Welcome back to Transmission.
- 0:10
- Unidentified speaker: An end-of-year deadline to manage a 20-year exposure.
- 0:13
- Unidentified speaker: That's the deal on the table for German battery developers.
- 0:16
- Unidentified speaker: Reach a final investment decision by the 31st of December, commit to 50% of the required component orders, and get the battery live before August 2029, and you pay no capacity-based grid fees for 20 years.
- 0:31
- Unidentified speaker: Miss the cutoff by a day, and the fees start in 2029.
- 0:35
- Unidentified speaker: Then there's the catch.
- 0:36
- Unidentified speaker: The rules on how those batteries can actually use the grid from dynamic fees to flexible connection agreements that won't be settled until after the money is committed.
- 0:45
- Unidentified speaker: So, how do you commit to a battery when you can't see the terms it will run under?
- 0:50
- Unidentified speaker: Marie Sophie Braun is head of markets and regulation at Keon Energy, taking projects from development into operation.
- 0:58
- Unidentified speaker: She's making those calls right now.
- 1:00
- Unidentified speaker: And if you want to see what German batteries are earning today or how that compares with solar or wind, ask co.
- 1:12
- Unidentified speaker: Hello Marie, welcome to Transmission.
- 1:14
- Unidentified speaker: Thank you very much for having me here.
- 1:16
- Unidentified speaker: Our pleasure.
- 1:16
- Unidentified speaker: And as ever, let's get straight into it.
- 1:18
- Unidentified speaker: So, what is the one thing that people get wrong about the German battery storage market right now?
- 1:24
- Unidentified speaker: I do think, to be honest, uh during the last year the discussion was still centered about around this battery tsunami.
- 1:31
- Unidentified speaker: So this really high number of grid requests, I do think it's it's not a good measurement in general on how storage deployment will be in Germany.
- 1:41
- Unidentified speaker: It might be a sign that there's still interest in uh in the German market, which of course is an I think for uh for a project developer and operator that apparently people believe that there is a business case, but in the end it has no impact on the number of projects that will be deployed, will be built, and will be ultimately also integrated into our energy system in Germany.
- 2:05
- Unidentified speaker: Yeah.
- 2:05
- Unidentified speaker: And it's kind of fascinating, right?
- 2:06
- Unidentified speaker: So that the when you talk about the battery tsunami, right?
- 2:09
- Unidentified speaker: The number of grid connections that came forward, I was like around 300 gigawatts or so, more or less.
- 2:15
- Unidentified speaker: I don't wanna don't don't quote me on that number, but it's kind of more or less that number.
- 2:18
- Unidentified speaker: And when when we do the the forecasting for sort of how many get built in Germany, it depends exactly what what date we're covering.
- 2:25
- Unidentified speaker: So like whether it's by 2040, 2050, 2060, like whatever it might be.
- 2:29
- Unidentified speaker: But the the number's probably somewhere between like 50 and 70 gigawatts, right?
- 2:33
- Unidentified speaker: So if you're going from 300 down to 70, you've kind of you've got a lot of applications coming in.
- 2:38
- Unidentified speaker: But yeah, as you say, like if you're the 301st gigawatt that joins the back of the queue, you're probably not going to get built.
- 2:45
- Unidentified speaker: And it's also not in the interest of the storage industry, to be honest.
- 2:48
- Unidentified speaker: Like it's a merchant asset that needs to uh to earn back its money.
- 2:52
- Unidentified speaker: Uh so also from the industry itself, there is no incentive to have 300, 600 gigawatt of storage installed in Germany.
- 3:00
- Unidentified speaker: Yeah.
- 3:00
- Unidentified speaker: And sort of like unlike other sort of unlike some other energy assets, like storage is generally competes on just a pure sort of supply and demand basis, right?
- 3:08
- Unidentified speaker: So the thing you're alluding to there is you're saying that as you add more batteries to the system, they compete with each other and you get this kind of compression of margins, which means that the batteries that have been built all suffer if lots of overbuild happens, uh, which is kind of a fascinating thing.
- 3:23
- Unidentified speaker: Okay, I'm excited to get into uh gem and best, and uh maybe we'll downgrade the tsunami to a wave as as the conversation goes on.
- 3:30
- Unidentified speaker: Um and let's talk about Keon.
- 3:33
- Unidentified speaker: So you started life as a developer and you've moved into sort of operating and optimizing your own assets.
- 3:39
- Unidentified speaker: It's kind of an interesting transition, and not everyone does it.
- 3:43
- Unidentified speaker: So why did you decide to hold on to those assets and operate them rather than what some developers do, which is you kind of get the rights and then just sell that off to another party?
- 3:54
- Unidentified speaker: I do think Kjon as a as a company always had a very clear mission uh and also somehow a kind of ambitious like a vision for the storage industry in Germany.
- 4:06
- Unidentified speaker: So we really came into the market and wanted to shape the regulatory framework.
- 4:12
- Unidentified speaker: And there were maybe three kind of motifs that still are true today, to be honest.
- 4:18
- Unidentified speaker: Uh, the one would be that we believe that storage in itself is not just an asset like a customer and something like a producer of energy, but really its own asset class.
- 4:30
- Unidentified speaker: We do believe that the last few milestones of the energy transition in Germany will only be feasible and yeah, also affordable, to be honest, when we integrate flexibility somehow efficiently in Germany.
- 4:44
- Unidentified speaker: And we do believe that this is still possible without having a big financing scheme from some from the German state.
- 4:52
- Unidentified speaker: And I do believe that this transition from being just a project developer to an operator is kind of delivering that mission as well for us.
- 5:03
- Unidentified speaker: So we kind of now are deploying this vision that we have been telling people since a few years and call ourselves now an independent flexibility provider.
- 5:15
- Unidentified speaker: So that's uh that's good for us.
- 5:17
- Unidentified speaker: And I would say this has always been the purpose of Kion.
- 5:21
- Unidentified speaker: And for me, like one of the interesting parts about that, right, is that uh as a business, you'll have built up this ability to find sites, get grid connections, acquire the land, and then finance that and bring it through.
- 5:32
- Unidentified speaker: And there's a particular set of skills that exist there, and it's sort of the classic developer set of skills.
- 5:36
- Unidentified speaker: And the next set of skills is how do you best optimize this?
- 5:39
- Unidentified speaker: How do you best operate these assets?
- 5:40
- Unidentified speaker: Sometimes not the same set of skills, right?
- 5:43
- Unidentified speaker: So as a company, have you had to can you can you kind of see that the company's changing a little bit around making sure that it's got that set of skills to deliver that next part?
- 5:52
- Unidentified speaker: Of course, I mean, Kion had to grow up together with the storage industry.
- 5:56
- Unidentified speaker: Uh, and I do think that's a huge advantage that we have in-house, because, for example, we had the chance to start with the smaller projects.
- 6:04
- Unidentified speaker: Uh, it's it's better to learn on a mid-voltage project, I assume, than aiming high for the bigger projects right away, just in order to kind of understand the processes, learn from it, have this like fast learning organization that is able to deploy an asset, learn from it, and then when the next green field development starts, we kind of already had this full cycle once uh once done in-house, which enabled us to be much more efficient for the for the next projects.
- 6:33
- Unidentified speaker: But obviously, there has been a lot of new learning experience.
- 6:37
- Unidentified speaker: We're building an asset management, um, which was obviously was not there before.
- 6:43
- Unidentified speaker: And this requires a very high skill set.
- 6:46
- Unidentified speaker: There's people like uh like the NIST2 regulation, cybersecurity rules that uh need to be respected.
- 6:53
- Unidentified speaker: This was out of scope before uh and still challenging, but uh but good to for us as an organization to learn from it.
- 7:03
- Unidentified speaker: Okay.
- 7:04
- Unidentified speaker: And and uh it's interesting, we had an episode recently with Alexandra and Jan from Entrix who were talking about Poland, and they were saying that because they haven't had the ability in Poland to sort of add in these one to five to ten megawatt sites, and they've had to go in with a 200 megawatt site essentially, so they've started with a very large site, they've missed a lot of those stages that you've just talked about, which is like we learnt on this asset, we learnt on this asset, we we got better at these pieces.
- 7:28
- Unidentified speaker: So it's interesting to see different countries do this in different ways.
- 7:31
- Unidentified speaker: I think the the approach of kind of allowing those smaller projects to come through is really important because it allows groups like yourself, who are tied to sort of the battery industry, to build up the capability that you want to.
- 7:42
- Unidentified speaker: And maybe like what one sort of final question on this.
- 7:44
- Unidentified speaker: So um one thing we see quite a lot in in independent producers uh or flexibility providers, however you want to sort of describe them, like there comes a question of like how much do they bring in-house?
- 7:56
- Unidentified speaker: Because there are loads of good optimizers out there, but there's always this kind of temptation to do it in-house and to sort of become an optimizer yourself.
- 8:04
- Unidentified speaker: Do you do you see that temptation, or is it something that um is it something where like there's you're pretty happy with the roots to market you've got?
- 8:12
- Unidentified speaker: I do think this is a whole different skill set, to be honest, um, because also our interest is really asset-centered, and of course, you know, we want to educate ourselves, we want to be smart about the root-to-market option, we want to understand what's actually happening beyond just the euro per kilowatt hours, uh, and we want to learn how the asset interacts with the grid.
- 8:35
- Unidentified speaker: Okay.
- 8:35
- Unidentified speaker: Um, but still, I do feel like there's a lot of really good solutions already on the market, and it would not be worth it to internalize it when we can also have very strong partners alongside of ours.
- 8:50
- Unidentified speaker: Yeah, it's it's it's really interesting.
- 8:51
- Unidentified speaker: It's like a it's like a global like um point of contention for developers and owners.
- 8:57
- Unidentified speaker: Um, but let's let's kind of move it back to the decisions that you're taking right now.
- 9:01
- Unidentified speaker: So um you're being asked to take final investment decisions this year on assets, and those assets, their grid usage terms, won't be settled until after you've committed to those projects.
- 9:14
- Unidentified speaker: So perhaps two things.
- 9:16
- Unidentified speaker: One, could you kind of describe a little bit of what you're seeing in those grid usage terms?
- 9:20
- Unidentified speaker: And two, how do you as a company, how do you make that decision?
- 9:24
- Unidentified speaker: To be honest, it's it's a big sprint for us for now.
- 9:27
- Unidentified speaker: Um, I mean, the the background being the reform of the grid fees, it's called Agnes in German.
- 9:34
- Unidentified speaker: Uh, this was something that was is actually a Germany first, that the German regulator is the party who's taking care of how the grid re or grid fees in Germany for all asset types should look like.
- 9:49
- Unidentified speaker: It's a huge task for them as well.
- 9:51
- Unidentified speaker: It has a lot of impact on more industries than just the storage industry.
- 9:56
- Unidentified speaker: But for us, of course, it's really important because for now we are exempted from uh from grid fees if your asset goes live before August 2029.
- 10:06
- Unidentified speaker: And this grid fee exemption is not gonna subsist if you don't take FID by the end of the year.
- 10:13
- Unidentified speaker: At least that's uh that's the the current knowledge base, I would say.
- 10:18
- Unidentified speaker: And FID is not just assigned paper, but really you need to allocate a big portion of your CapEx for the asset still this year.
- 10:27
- Unidentified speaker: Um and for us at least it's uh it's really ambitious to do so.
- 10:32
- Unidentified speaker: Uh just because of the tight timeline.
- 10:35
- Unidentified speaker: We know of this deadline since I would say May of this year.
- 10:41
- Unidentified speaker: Uh and it's like if if you really want to do infrastructure investment, seven months is usually not enough to close financing, to do your due diligence on supply agreements.
- 10:55
- Unidentified speaker: We do think we do have a fair chance to achieve that, uh, but it's now much more about active risk management because we have this deadline.
- 11:06
- Unidentified speaker: Uh by the way, I mean the business case still will subsist.
- 11:08
- Unidentified speaker: So it's not a harsh deadline, and then no battery build-out in Germany is going to continue.
- 11:14
- Unidentified speaker: I was going to ask like your project next year.
- 11:16
- Unidentified speaker: Like how like how are you going to think about those?
- 11:19
- Unidentified speaker: I mean, better to have the grid fee exemption, but I do think that's my personal opinion that the regulator has found a good compromise for everyone.
- 11:29
- Unidentified speaker: Now, like storage will pay the same good fees as uh also renewable assets, for example, will will pay.
- 11:37
- Unidentified speaker: Uh and this is something which is understandable in a s situation where the bill that has to be paid for good builder is getting bigger and bigger, and this cannot only be given to consumers.
- 11:49
- Unidentified speaker: Yes.
- 11:50
- Unidentified speaker: Uh so I think it's it's a fair regime.
- 11:54
- Unidentified speaker: Like the the business case, of course, is better when you don't pay grid fees, but it it will subsist.
- 12:00
- Unidentified speaker: Uh, hence it's a commercial decision to take FID this year.
- 12:04
- Unidentified speaker: Uh, and it's a really ambitious one because in the meantime in Germany we do have a big discussion on how are we actually going to integrate all these storages into the grid while keeping our security of supply.
- 12:18
- Unidentified speaker: And I I think there's some really interesting parts of those grid fees.
- 12:22
- Unidentified speaker: The one that I uh, from my reading have liked the most is the sort of look at locational and dynamic grid fees.
- 12:30
- Unidentified speaker: I think it's like a really nice concept where where you're showing that you've got congestion, you're encouraging the storage assets to act in a way that is going to help to resolve that congestion.
- 12:41
- Unidentified speaker: That to me feels like sorry, I know I'm gonna borrow something you said.
- 12:44
- Unidentified speaker: You were kind of saying it's it's kind of like a reflective uh way of try of sort of treating the costs, and it seems it sort of seems more fair.
- 12:51
- Unidentified speaker: Um, to me, like a a dynamic and locational grid fee, it feels like it does that right and it encourages assets to work in ways that help the grids rather than just sort of layering in extra cost.
- 13:04
- Unidentified speaker: Is that your take?
- 13:05
- Unidentified speaker: Yeah, I I would agree totally.
- 13:07
- Unidentified speaker: I do think, of course, you know, like every model you will build that's never gonna be perfect.
- 13:12
- Unidentified speaker: There will be the point in time where you've set the grid fee maybe one day in advance, and then there is an unexpected event, and you will have a wrong incentive that grid fees is only part of the solution, or dynamic grid fees are only part of the solution.
- 13:28
- Unidentified speaker: Uh it will be still a combination of redispatch, of other measures, and but I also do believe, to be honest, that it's really important to incentivize storage to act on grid needs because for now, to be honest, our storages are kind of blind when it comes to to grid congestion.
- 13:49
- Unidentified speaker: And for people who are listening to this who aren't necessarily um in the detail of the German market, redispatches essentially when you get close to delivery, the assets are redispatched to account for things like congestion in the system.
- 14:01
- Unidentified speaker: Exactly.
- 14:02
- Unidentified speaker: That's that's the normal process in Germany.
- 14:04
- Unidentified speaker: It's it's also hard to include storage into it because the processes are not fully there yet, but we see it more and more, and obviously that's a good thing.
- 14:12
- Unidentified speaker: Storage should be integrated as every other asset into German congestion management.
- 14:17
- Unidentified speaker: Yeah, yeah, it's I I I totally agree.
- 14:19
- Unidentified speaker: Um, okay, moving on from the those decisions around Agnes changes.
- 14:25
- Unidentified speaker: Uh do you do you think that there is a and it this can be both be for sort of Agnes, so from the grid connection side, but it also can be from sort of flexible connection agreements as well.
- 14:37
- Unidentified speaker: What what sort of splits a regime that a developer like you can support and actually finance versus one that sort of stops everything?
- 14:46
- Unidentified speaker: As a storage industry, we have always been used to market risks.
- 14:52
- Unidentified speaker: Uh that's that's the game you're playing when you try to deploy a storage asset.
- 14:56
- Unidentified speaker: Uh so I would say we we are inertly kind of good to manage uncertainty.
- 15:02
- Unidentified speaker: When it comes to these FCAs, we do see that there is a few ones which are hitting very hard.
- 15:08
- Unidentified speaker: This particularly comes into play when uh you're faced to uh congestion management management which is not remunerated.
- 15:19
- Unidentified speaker: For example, there is uh there's schemes which are discussed which just do not limit the capabilities of your connecting grid operator to just curl tail you without reimbursing you.
- 15:29
- Unidentified speaker: Yeah.
- 15:30
- Unidentified speaker: And this is something which, of course, I mean you can do the scenario analysis.
- 15:34
- Unidentified speaker: You can see with different weather years how it's going to be.
- 15:37
- Unidentified speaker: Yeah.
- 15:38
- Unidentified speaker: But uh the risk profile just increases so much uh that it will be really hard to find uh financing for not only one asset but for a larger portion of flexibility.
- 15:52
- Unidentified speaker: And this is something that I feel should be limited.
- 15:56
- Unidentified speaker: Um it's an idea that has been floating around at Keon since 2024 or three, even I think, to kind of grant the grid operator a certain portion uh of non-compensated redispatch measures somehow.
- 16:10
- Unidentified speaker: This is something that we can do if it helps to alleviate the grid, but it needs to be a really like distinct amount of numbers.
- 16:19
- Unidentified speaker: And I think also from other market participants, for example, green flexibility, you can see that this is something which is achievable through negotiation with your grid operator.
- 16:30
- Unidentified speaker: Did you did you catch the green flexibility episode on transmission?
- 16:33
- Unidentified speaker: I catch.
- 16:33
- Unidentified speaker: Very good, very good, very good.
- 16:35
- Unidentified speaker: It's a great episode.
- 16:36
- Unidentified speaker: Um but yeah, I totally agree with you, right?
- 16:39
- Unidentified speaker: So imagine that I'm a developer and I'm going to a financier and I say, Hey, um, can you can you put debt into my projects?
- 16:46
- Unidentified speaker: And they say, Oh, yeah, sure, like we can do that.
- 16:48
- Unidentified speaker: And you say, Well, look, I've got this connection, but I might get turned off for the year.
- 16:51
- Unidentified speaker: Like, no financier is gonna say yes to that.
- 16:53
- Unidentified speaker: So, as you say, like you've got to have the you have to have like a very clearly defined, like, this is when my asset's gonna be available, um, or else bringing debt into that project is gonna be super tough.
- 17:02
- Unidentified speaker: Well, let's move from the theory into like real life of uh you have an asset coming online soon.
- 17:09
- Unidentified speaker: I don't want to put a date on it, uh, but you can you can do that for me.
- 17:12
- Unidentified speaker: Um and you and I think you're gonna split the asset to have three different route to market providers.
- 17:17
- Unidentified speaker: Uh I I believe that might be correct.
- 17:19
- Unidentified speaker: You you can correct me in a second.
- 17:20
- Unidentified speaker: But oh, like by by splitting assets out across uh different root to market providers, um what are you trying to learn with that approach?
- 17:28
- Unidentified speaker: Well, what we do is actually we we as Keon, we do have a like a bit a bigger portfolio of storage assets, and we do not split each asset, but we have comparable assets and we give them to different root to market providers.
- 17:39
- Unidentified speaker: Of course, that's still a little bit not comparing apples to apples, but kind of ish.
- 17:45
- Unidentified speaker: Uh and what we really hope is uh, of course, you know, first it's a benchmarking approach.
- 17:51
- Unidentified speaker: The best market is still emerging.
- 17:54
- Unidentified speaker: There are a few established-ish players uh from the root to market providers, but I do think we want to see and learn from for ourselves beyond the shiny PowerPoint presentations, who's actually performing on live assets.
- 18:09
- Unidentified speaker: And on the other hand, we also are seeking a long-term partnership with our wood to market providers.
- 18:16
- Unidentified speaker: We do see, and I think that's that's not a secret, that the regulatory environment is changing fairly quickly in Germany.
- 18:24
- Unidentified speaker: And for us, it's a strain on the business case, but for the root to market provider, uh, this is something that he will need to act on in real life.
- 18:33
- Unidentified speaker: So when a load gradient and FCA regime comes in, it's the root to market provider which is the responsible party to really deliver on these new rules.
- 18:45
- Unidentified speaker: And this is something where you need a really well-oriented partner to achieve that and not have not having downtimes on your asset, for example, because they're late on algorithmic development.
- 18:58
- Unidentified speaker: That's exactly what I was gonna say, actually.
- 19:00
- Unidentified speaker: So uh we we on on transmission we've interviewed a lot of of optimizers, and occasionally someone will come in and say, Oh, we're better than all the other optimizers.
- 19:08
- Unidentified speaker: I don't I really don't hear that very much these days, actually.
- 19:11
- Unidentified speaker: I probably more often than not I hear we help parties get assets online, we're up to speed with the regulation.
- 19:18
- Unidentified speaker: When there's something that goes wrong on the site, we're quite quick to get it back online.
- 19:22
- Unidentified speaker: Because I I think what they're pointing at is that the way you can really lose money on assets is like being a month late or being, you know, uh just just missing some element of the dispatch that you should be running.
- 19:33
- Unidentified speaker: So actually, like the physical delivery of of their of their performance is is kind of more important than having a slightly more refined trading algorithm.
- 19:43
- Unidentified speaker: Maybe an optimizer will be listening to this and be like, hey, you're so wrong.
- 19:46
- Unidentified speaker: I'm gonna come on and tell you why you're wrong.
- 19:48
- Unidentified speaker: Uh and I look forward to that day because I'm sure it will happen again soon.
- 19:52
- Unidentified speaker: But uh, yeah, that's definitely the themes, the the those are the themes that that we're hearing.
- 19:56
- Unidentified speaker: And and in terms of different assets, right?
- 19:59
- Unidentified speaker: So you mentioned you've got lots of different assets coming through, and there's obviously transmission and distribution networks.
- 20:04
- Unidentified speaker: Those networks have different incentives from their grid operator.
- 20:10
- Unidentified speaker: Or do those networks sort of change where you'd rather build as a developer?
- 20:14
- Unidentified speaker: Uh I do believe it's worth when when I would start a greenfield development today.
- 20:18
- Unidentified speaker: Uh I think the biggest work is to really investigate your grid connection point.
- 20:24
- Unidentified speaker: Um, because also kind of as an asset operator, you might even be able to manage your expectation, what the result is going to be.
- 20:31
- Unidentified speaker: This like there can be a lot of factors to that.
- 20:35
- Unidentified speaker: For example, if you know, and these data are partially public that the grid area is highly congested already, I mean, your chances are getting lower, obviously.
- 20:47
- Unidentified speaker: And that's a natural thing.
- 20:49
- Unidentified speaker: On the other hand, of course, we do see a difference between a TSO and a DSO connected assets, and a lot of people are not really happy about the DSOs.
- 20:58
- Unidentified speaker: I do think that's not fully true.
- 21:01
- Unidentified speaker: Uh we do see really like highly engaged DSOs, we do see highly digitalized DSOs, we do see DSOs that we are really like working on integrating storage into their goods fairly efficiently.
- 21:15
- Unidentified speaker: Okay.
- 21:16
- Unidentified speaker: So so that's that that might be the olive branch there.
- 21:19
- Unidentified speaker: In the in the same time, of course, just from uh from the way they are regulated, there are a few incentives which align much better between a TSO and a storage operator than it is the case for a DSO and a storage operator.
- 21:36
- Unidentified speaker: Like giving you an example, ancillary services in Germany are provided for frequency control.
- 21:42
- Unidentified speaker: And obviously all grids need a stable frequency, but it's just not the job of a DSO to care for frequency or for the stability of the frequency at least.
- 21:54
- Unidentified speaker: Uh so when you provide an ancillary services, be it FCR, be it maybe even inertia, um this is a service that you provide to the TSO and might create issues in your DSO network.
- 22:09
- Unidentified speaker: This can create voltage issues, for example, in the DSO network.
- 22:12
- Unidentified speaker: Yeah.
- 22:13
- Unidentified speaker: And the DSO will only see the trouble you're making and not the benefit, because it's just out of his scope to care for frequency control.
- 22:23
- Unidentified speaker: And this is an issue which needs some kind of regulation, to be honest.
- 22:29
- Unidentified speaker: I do think like the only party will who who is able to kind of decide what is more important will be the regulator, because obviously the TSO wants to have the ancillary services.
- 22:40
- Unidentified speaker: We want to make money on the ancillary services, the DSO's uh has has no like proper incentive beyond being happy about storage deployment, maybe to see it in its grid.
- 22:54
- Unidentified speaker: Uh so that's uh that's an issue which creates a lot of friction, but is solvable through proper stakeholder management, explanation, like proper like discussion on a technical level to really understand the issues your connecting grid operator has or might have with your asset.
- 23:15
- Unidentified speaker: I think this is a fascinating part of the market and um um the conversation just kind of going beyond storage, just um uh charging at a low price and discharging at a high price, which is kind of what people think about it most simply, to go into things like uh voltage control, to go into things like inertia, frequency response, and frequency response is perhaps more well understood, things like fault current being injected into the system.
- 23:37
- Unidentified speaker: I think this is where the conversation's going over the next three to five years.
- 23:42
- Unidentified speaker: We'll we'll find the umbrella term of system strength and all the stuff that goes underneath it.
- 23:46
- Unidentified speaker: I think we're gonna start to think a lot more about and like be more tactical about where we place batteries onto these systems.
- 23:52
- Unidentified speaker: And maybe this kind of ties actually really into a nice sort of uh market design question and one that is everywhere.
- 23:59
- Unidentified speaker: So this kind of same thing is happening, right?
- 24:01
- Unidentified speaker: Where we've gone from really large, transmission connected, big power stations to all of a sudden solar, wind, uh batteries, much more distributed assets, they can kind of be placed anywhere.
- 24:12
- Unidentified speaker: Um, and what's happening is that the the big sort of national system that we used to have is being questioned and saying, well, actually, do we want a big national system, or should we have a zonal system, or should we have a nodal system?
- 24:22
- Unidentified speaker: And Germany's going through that process, right?
- 24:24
- Unidentified speaker: There was a few, this was looked at a little bit this year, it was also looked at a little bit last year as well.
- 24:30
- Unidentified speaker: Where where does Germany stand on the system design?
- 24:34
- Unidentified speaker: What where where do you think it might go?
- 24:36
- Unidentified speaker: I think there there are more and more actors really rooting for uh a price split in Germany.
- 24:44
- Unidentified speaker: That's uh that's that's for for sure true.
- 24:47
- Unidentified speaker: Is that is that zone that would be zonal?
- 24:49
- Unidentified speaker: Uh that would be zonal, yes.
- 24:50
- Unidentified speaker: Um that's I mean it's it's an ongoing debate.
- 24:54
- Unidentified speaker: I think like the congestion issues be having a lot of energy production in the north of Germany, a lot of customers in the the south of Germany, uh that's uh that's a problem that has been recognized.
- 25:09
- Unidentified speaker: There is a lot of like DC uh high high voltage cables being built out in Germany to kind of try to cope with that.
- 25:17
- Unidentified speaker: Uh but we see that now it's not enough because just the the the amount of money we spend each year on redispatching, which is kind of uh realigning the price uh the the price signals with the actual reality of the physical energy network um are getting higher and higher.
- 25:43
- Unidentified speaker: I do think from a flexibility perspective, of course, uh it's an advantage to have to have a to to have price zones because then assets can actually react on more local signals.
- 25:58
- Unidentified speaker: Yes.
- 25:59
- Unidentified speaker: That's that's the big issue.
- 26:00
- Unidentified speaker: I mean, I've been talking about it.
- 26:01
- Unidentified speaker: Like it's it's a pity that there is no real mechanism where storage can are enabled to align with the grid needs beyond an FCA regime.
- 26:11
- Unidentified speaker: And the dynamic uh grid fees that will be coming.
- 26:15
- Unidentified speaker: But for now, like for now, there's nothing beyond like the your connecting grid operator telling you you're just not allowed during certain time windows to uh to act freely in in the grid.
- 26:26
- Unidentified speaker: And it's a pretty it's a pretty bad solution for consumers, right?
- 26:28
- Unidentified speaker: So consumers are told, oh by the way, you're gonna pay large redispatch fees, and also we're gonna like the lever that we've got to pull is this big HVDC line we can build from north to south.
- 26:38
- Unidentified speaker: It's not that's not really great.
- 26:39
- Unidentified speaker: Yeah, and the in the same time, you know, for me this and this is probably also why it hasn't been solved so far, that it's an issue that goes beyond the storage industry and maybe also beyond the energy industry.
- 26:51
- Unidentified speaker: Because when you do it, this will have an impact on other industries, on people living maybe in certain areas where electricity prices go up.
- 27:01
- Unidentified speaker: Uh so when talking about this, I think you really need also to assess the social factors that come with it beyond also operational complexity to maybe cut a German TSO in half.
- 27:14
- Unidentified speaker: Yeah.
- 27:15
- Unidentified speaker: Yeah, it's it's it's gonna be uh it's gonna be an interesting, interesting debate, right?
- 27:19
- Unidentified speaker: And it it rumbles on.
- 27:20
- Unidentified speaker: It's it's also for people listening outside of Germany, like it's not just a German thing, right?
- 27:23
- Unidentified speaker: We're seeing this everywhere where people are questioning the the sort of single national uh market design.
- 27:28
- Unidentified speaker: Right, let me take me through to the final question.
- 27:31
- Unidentified speaker: So, what is a contrarian view you hold about energy in Germany or the battery storage industry in Germany?
- 27:38
- Unidentified speaker: I would say like we do see a lot of good approaches also when it comes to reflection on good usage conditions.
- 27:44
- Unidentified speaker: Unfortunately, I see them more in the renewable sector.
- 27:49
- Unidentified speaker: Uh what we see in the in the EEG, the German law for renewables, is for example, that they have this idea on in highly stressed areas you'll get congested without renew without remuneration, but only for a certain amount of hours and only for I think it's six years.
- 28:10
- Unidentified speaker: And this regime makes a lot of sense.
- 28:12
- Unidentified speaker: You know, there I can get behind it, it's something which is financeable because we can quantify it.
- 28:18
- Unidentified speaker: This would be an an easy yes, I think, for most storage operators.
- 28:22
- Unidentified speaker: But this is something which is kind of discussed isolated for renewable assets.
- 28:26
- Unidentified speaker: Then you have the big debate about grid usage conditions uh for storage assets, which is fairly different and mostly more restrictive, but in the same time, German regulation and also energy policy is kind of pushing for colocated assets.
- 28:44
- Unidentified speaker: And this is something in in my mind that doesn't make any sense.
- 28:48
- Unidentified speaker: Why would you introduce different rules for different asset types, which in the end are co-located?
- 28:55
- Unidentified speaker: Because then just no one will know how it's actually working and which rule should apply in which moment.
- 29:00
- Unidentified speaker: Yeah, so you're saying that um uh the kind of status quo of the market is that you have this uh remuneration uh or support for renewable assets uh through EEG around, say congestion, but you don't have that for storage.
- 29:14
- Unidentified speaker: And when you're starting to think about co-locating those assets, the contrarian view is that we've kind of we've we've got this wrong and we should be trying to align these two so that there's kind of a fair playing field between these two assets.
- 29:27
- Unidentified speaker: Yeah, and also that could the collocation just works from an operational level, to be honest.
- 29:31
- Unidentified speaker: Because when you when you're yeah, when you just have different rules that apply to different to different asset types, like it gets harder when they are collocated, uh, which is something that is also pushed from the regulation.
- 29:43
- Unidentified speaker: And we want it like we see it in in the EEG regime, we see it through something which is called MISPL.
- 29:50
- Unidentified speaker: Uh that's actually a German regulation which is defining metering concept, which enables you to do proper collocation and also to switch between green energy being stored in your energy in your battery uh from a solar power plant, for example, and the battery just acting as a standalone bass.
- 30:09
- Unidentified speaker: But how should this work once you have then a redispatch policy that only applies to the green part of the battery and another one that applies to the grey part of the battery?
- 30:20
- Unidentified speaker: It's getting more and more complex instead of looking at the problem from the technical perspective, uh, which is is my grid actually capable of taking the energy or not?
- 30:33
- Unidentified speaker: And when you're talking about green and grey, that's um green is effectively a battery that is charging only from renewable, and grey is where it's also being able to charge from the grid.
- 30:41
- Unidentified speaker: Uh, we don't we don't colour batteries differently.
- 30:44
- Unidentified speaker: Uh this is just how we talk about regulation in the sector.
- 30:48
- Unidentified speaker: Okay, Marie, thank you very much for coming on.
- 30:50
- Unidentified speaker: You've been a wonderful guest.
- 30:51
- Unidentified speaker: Uh, I think people will learn a lot about sort of how to think about the the German battery space.
- 30:55
- Unidentified speaker: It feels like so much is gonna has changed over the last year, and then then the next year coming, it feels like we're gonna do the same thing again.
- 31:02
- Unidentified speaker: But good luck with your projects coming online.
- 31:04
- Unidentified speaker: I hope you're able to make those decisions and get them online.
- 31:06
- Unidentified speaker: Thank you very much.
More from Transmission
Where The Value Is In European Renewables Today - OX2
Episode discussion: OX2's Ed Porter and Mehmet Energin discuss shifting value in European renewables from generation to financing and operations.
Speakers’ claims: Ed Porter and Mehmet Energin of OX2 argue that Europe's renewable capacity has grown significantly, but grid and storage infrastructure lag, shifting investment value from simple generation to complex financing and active operations. They emphasize that OX2 treats each project as a distinct company, managing 20-30 levers to optimize returns through offtake agreements and financial structuring rather than relying solely on Levelized Cost of Energy (LCOE). The speakers highlight a strategic preference for acquiring stalled projects to bypass lengthy permitting timelines, particularly in Sweden, where greenfield development can take up to a decade. They advocate for a humble approach to market forecasting, using the metaphor of Ayrton Senna to illustrate the risks of being ahead of one's time, and view falling energy prices as a sign of industry success in delivering affordable power.
There’s No Such Thing as a Global Battery Price - Benchmark Mineral Intelligence
Episode discussion: Benchmark analysts argue battery prices are regional, not global, driven by policy and tariffs rather than manufacturing costs
Speakers’ claims: Ed Porter and Iola Hughes from Benchmark Mineral Intelligence discuss how battery pricing has fragmented into regional markets due to tariffs, sourcing rules, and logistics. Hughes explains that China's 'anti-involution' campaign and reduced export rebates have ended the era of ultra-low cell prices, while the US market is driven by policy incentives like 48E and 45X. The speakers note that sodium-ion technology has lost momentum with over 1 GWh of projects cancelled in favor of LFP, and that stationary storage is gaining share relative to EVs, particularly in the US data center sector. They conclude that only LFP and NCM chemistries are viable long-term, dismissing hype around solid-state and sodium-ion as noise against continuous improvements in incumbents.