Midterms may delay AI data center buildout by shifting timelines and locations, not derailing it
Summary
Ariana Salvatore argues that U.S. midterm elections will impact AI infrastructure development by driving political opposition related to electricity bills, water consumption, and local economic benefits. She contends that state-level regulatory actions in Texas, Ohio, and Georgia will shift where and when data centers are built rather than stopping them entirely. The federal government is expected to remain accommodative due to national security interests, though Morgan Stanley estimates a five-gigawatt shift of projects from 2028 to 2029. A projected 44-gigawatt power shortfall through 2028 is identified as the primary bottleneck, favoring well-capitalized hyperscalers and facilities with secured power. Finally, risks include weaker equipment orders and margin pressure in 2028, with financing becoming more scrutinized for new projects but favorable for existing data centers with stable cash flows.
Key takeaways
- 1 Growing concerns around electricity bills, water consumption, and the economic benefits of data centers have translated into meaningful political opposition.
Unidentified speaker (speaker_0) · 0:17
Episode sections
- 0:00 – 0:45
Introduction and Political Context
Ariana Salvatore introduces the topic of U.S. midterm elections impacting AI infrastructure build-out, noting that political opposition is driven by electricity bills, water consumption, and economic benefit concerns.
- 0:45 – 1:24
State-Level Regulatory Impacts
Salvatore argues that midterms will shift where and when data centers are built rather than stopping them entirely, citing specific regulatory actions in Texas, Ohio, and Georgia.
- 1:24 – 2:28
Federal Stance and Timeline Shifts
The federal government is expected to remain accommodative due to national security interests, while Morgan Stanley estimates a shift of 5 gigawatts of projects from 2028 to 2029.
- 2:28 – 3:19
Power Constraints and Investment Implications
With a projected 44-gigawatt power shortfall through 2028, the bottleneck shifts to power infrastructure, favoring well-capitalized hyperscalers and existing power-secured facilities.
- 3:19 – 4:49
Supply Chain and Financing Risks
Risks include weaker equipment orders and margin pressure in 2028, while financing becomes more scrutinized for new projects but favorable for existing data centers with stable cash flows.
Do your own research
- Verify Morgan Stanley's specific report citing the 5 GW shift from 2028 to 2029.
- Review Texas, Ohio, and Georgia state regulatory filings for recent data center zoning or utility rate changes.
- Check EIA or grid operator data for the projected 44-gigawatt power shortfall through 2028.
- Analyze equipment manufacturer order books for signs of weakening demand in 2028.
- Assess financing terms for new data center projects versus existing facilities with stable cash flows.
- Identify conflicts of interest if speakers have holdings in hyperscalers or power infrastructure companies.
Full transcriptexpand
- 0:00
- Unidentified speaker (UNKNOWN): Welcome
- 0:01
- Unidentified speaker (speaker_0): to Thoughts on the Market. I'm Mariana Salvatore, Head of Public Policy Research at Morgan Stanley. Today, the U.S. midterm elections and what they could mean for the build-out of AI infrastructure. It's Wednesday, November 11th at 10 a.m. in New
- 0:14
- Unidentified speaker (UNKNOWN): York.
- 0:17
- Unidentified speaker (speaker_0): Growing concerns around electricity bills, water consumption, and the economic benefits of data centers have translated into meaningful political opposition.
- 0:25
- Unidentified speaker (UNKNOWN): And
- 0:25
- Unidentified speaker (speaker_0): last week's results reinforced. reinforce just how salient those issues were in voters' decision making.
- 0:30
- Unidentified speaker (UNKNOWN): But
- 0:31
- Unidentified speaker (speaker_0): what are the practical implications for the build-out?
- 0:34
- Unidentified speaker (UNKNOWN): We think
- 0:34
- Unidentified speaker (speaker_0): that the midterms were actually more likely to change where data centers get built, when they come online, and what cost is associated with doing so rather than whether they get built at all.
- 0:45
- Unidentified speaker (UNKNOWN): We've
- 0:45
- Unidentified speaker (speaker_0): been flagging political opposition to data centers as a risk for some time.
- 0:48
- Unidentified speaker (UNKNOWN): And
- 0:49
- Unidentified speaker (speaker_0): the election results reinforce our view. that this is largely a state by state and even project by project issue. Let's take a few examples. Texas, we think was the most consequential result. Governor elect Hinojosa has proposed pausing new data center approvals until stronger protections are in place. In Ohio, Governor-elect Acton has proposed a
- 1:08
- Unidentified speaker (speaker_0): conditional moratorium. And in Georgia, we see policy action as more incremental, with greater scrutiny of consultation. construction approvals and how electricity infrastructure costs are allocated.
- 1:19
- Unidentified speaker (UNKNOWN): So
- 1:19
- Unidentified speaker (speaker_0): altogether, these developments point to a broader shift in political and community support.
- 1:24
- Unidentified speaker (UNKNOWN): The
- 1:24
- Unidentified speaker (speaker_0): opposition is increasingly bipartisan, but the friction remains primarily local.
- 1:29
- Unidentified speaker (UNKNOWN): At
- 1:29
- Unidentified speaker (speaker_0): the federal level, we think the government retains an accommodative posture, just given the importance of AI as national security infrastructure and the likelihood of a presidential veto. on restrictive legislation.
- 1:40
- Unidentified speaker (UNKNOWN): But
- 1:41
- Unidentified speaker (speaker_0): what does this mean for the build-out?
- 1:43
- Unidentified speaker (UNKNOWN): My
- 1:43
- Unidentified speaker (speaker_0): colleague Cameron McVeigh and his team estimate that approximately five gigawatts of US data center projects, or roughly 28% of the 2028 pipeline, will shift into 2029.
- 1:53
- Unidentified speaker (UNKNOWN): We
- 1:54
- Unidentified speaker (speaker_0): think 2027 construction will likely remain unaffected because projects are generally already permitted or underway.
- 2:00
- Unidentified speaker (UNKNOWN): As
- 2:01
- Unidentified speaker (speaker_0): a result, US data center capacity additions are projected to be roughly flat in 2028 before growing nearly 40% in 2029.
- 2:08
- Unidentified speaker (UNKNOWN): That
- 2:08
- Unidentified speaker (speaker_0): feeds into our tech analyst view, led by Brian Nowak, that hyperscaler CapEx next year should remain unchanged at approximately $1.6 trillion and $1.8 trillion in 2028.
- 2:20
- Unidentified speaker (UNKNOWN): So
- 2:20
- Unidentified speaker (speaker_0): our base case is a delay, not a fundamental reduction in investment.
- 2:24
- Unidentified speaker (UNKNOWN): In
- 2:24
- Unidentified speaker (speaker_0): fact, we think this could actually extend the duration. of the AI investment cycle.
- 2:28
- Unidentified speaker (UNKNOWN): And
- 2:29
- Unidentified speaker (speaker_0): it reinforces an existing constraint: access to electricity.
- 2:32
- Unidentified speaker (UNKNOWN): We've
- 2:32
- Unidentified speaker (speaker_0): been highlighting the three Ps that are bottlenecks here: people, power, and politics. Steven Byrd and our powering AI team now estimate a 44 gigawatt shortfall in US data center power through 2028, representing roughly 38% of projected demand.
- 2:47
- Unidentified speaker (UNKNOWN): That
- 2:47
- Unidentified speaker (speaker_0): means that the critical bottleneck is increasingly shifting from computing equipment. to power data center facilities. And that has several investment implications. First, the largest and best capitalized hyperscalers are particularly well positioned.
- 3:01
- Unidentified speaker (UNKNOWN): These
- 3:01
- Unidentified speaker (speaker_0): are the companies that have a line of sight to 25 to 50% return on investment. They also have flexibility to redirect their investment, they can absorb higher costs, and they can improve computing efficiency. Second, we see opportunities in existing power-secured facilities and technologies that help developers access electricity more quickly.
- 3:19
- Unidentified speaker (UNKNOWN): But
- 3:20
- Unidentified speaker (speaker_0): there are also risks to the supply chain. A slower build out in 2028 could mean weaker equipment orders, inventory accumulation, and pressure on supplier margins, even if the underlying AI demand remains strong. Lastly, as my colleagues in credit like Vishwas Patkar have been highlighting, the financing environment is likely to become more differentiated under the surface.
- 3:39
- Unidentified speaker (UNKNOWN): We
- 3:39
- Unidentified speaker (speaker_0): continue to expect substantial AI related borrowing in 2027 led by the hyperscalers, but new construction financing will face greater scrutiny around permitting, power availability, and execution. By contrast, existing data centers with stable cash flows could benefit from increased scarcity and stronger lease pricing.
- 3:58
- Unidentified speaker (UNKNOWN): And
- 3:58
- Unidentified speaker (speaker_0): finally, our equity strategy colleagues see investment opportunities broadening beyond infrastructure. to companies actually adopting AI.
- 4:06
- Unidentified speaker (UNKNOWN): So
- 4:06
- Unidentified speaker (speaker_0): the through line here is that midterms have introduced real political and execution risk. But we think that these constraints are more likely to reshape and actually prolong the AI investment cycle than derail it.
- 4:16
- Unidentified speaker (UNKNOWN): And
- 4:17
- Unidentified speaker (speaker_0): with the recent market weakness reflecting a more pessimistic outcome, we see selective opportunities across the AI value chain. Thanks for listening. If you enjoy Thoughts on the Market, please leave us a review wherever you listen and share the podcast with a friend or colleague today.
- 4:32
- Unidentified speaker (UNKNOWN): The
- 4:32
- Unidentified speaker (speaker_0): preceding content is informational only and based on information available when created. It is not an offer or solicitation, nor is it tax or legal advice. It does not consider your financial circumstances and objectives and may not be suitable for
- 4:46
- Unidentified speaker (UNKNOWN): you.
More from Thoughts on the Market
2027 Global Outlook: The Case for a Stronger Dollar, Longer AI Cycle
Episode discussion: Morgan Stanley's 2027 Outlook: Stronger Dollar, AI Cycle, and Global Equity Overweight
Speakers’ claims: Seth Carpenter and Serena Tang discuss Morgan Stanley's 2027 market outlook, with Tang identifying 'embracing risk' as the primary theme due to an intact AI CapEx cycle and robust growth. The firm has moved to a maximum overweight in global equities, particularly the US, Japan, and Europe, while maintaining a neutral stance on investment grade bonds. Tang highlights out-of-consensus views including a stronger US dollar driven by superior US growth and a constructive stance on UK gilts. Risks to this outlook include an abrupt end to the AI investment cycle, rising oil prices, or unrelated inflation reacceleration. Tang argues that US midterm election outcomes are unlikely to significantly impact data center construction, as projects are largely state-level and already permitted.
2027 Global Outlook: Powered by AI, Tested by Oil
Episode discussion: Morgan Stanley forecasts AI-driven US growth and two Fed hikes in 2027 amid oil risks
Speakers’ claims: Seth Carpenter and Serena Tang outline Morgan Stanley's 2027 global outlook, attributing resilient growth to AI investment cycles despite energy and geopolitical shocks. Carpenter forecasts US real GDP growth of 2.5% driven by AI capital expenditure, with Europe at 1.3% and China at 4.3%. He predicts two Federal Reserve rate hikes in December 2026 and March 2027, anticipating an inflation peak in Q1 2027. The analysts highlight that US growth expectations exceed consensus due to anticipated AI productivity gains, though they warn of downside risks if AI CapEx falls short.