CommBank analysts project AI could boost Australian GDP by 2% via data centers, though import intensity limits domestic gains.
Summary
Host Mandy Drury discusses AI's economic impact with CommBank analysts Ashwin Clarke, Lucinda Jerogin, and Harry Ottley. Clarke estimates AI could increase Australia's GDP by 2% ($58 billion) over five years, comparable to the mining boom, but notes a net benefit of only 1.2% after accounting for $24 billion in annual imported AI service costs. Jerogin highlights a gap between 23 gigawatts of announced data center projects and a 7 gigawatt feasible pipeline, citing regulatory hurdles and energy constraints. Ottley forecasts unemployment holding at 4.7% before rising to 5.1% in 2027, while noting a hawkish shift in Federal Reserve rhetoric.
Key takeaways
- 1 It's a good question, Mandy. And yeah, we we think the potential is is very large for AI to improve the economy's productive capacity. Just over the past 12 months, we've seen a massive increase in not just the usage of AI, but also the potential for AI to do things that it couldn't do. just a little while ago. So we've built an economic model to help us think through these issues. And that economic model suggests that over the next five years, we estimate that AI will increase GDP by about 2%, which is about $58 billion in today's terms, in terms of the level of annual GDP. It might sound like a small number, but it is quite transformative. To give you a sense of comparison, it's about the benefits that we saw during the mining investment boom in the 2010s, which was also very transformative for the Australian economy.
Unidentified speaker (speaker_1) · 1:39
- 2 Data centers are forecast to consume 3% of National Electricity Market (NEM) energy in FY26, rising to 8% by 2030 and over 13% by 2035-2036, requiring substantial grid expansion.
Unidentified speaker (speaker_2) · 22:44
Episode sections
- 0:08 – 2:42
Intro and AI GDP Impact
Host Mandy Drury introduces the topic of AI's potential impact on the Australian economy, specifically regarding data centers and productivity. Ashwin Clarke estimates AI could increase Australia's GDP by 2% ($58 billion) over the next five years, comparable to the benefits seen during the 2010s mining boom.
- 2:42 – 6:05
Data Center Pipeline: Announced vs. Feasible
Lucinda Jerogin explains the gap between 23 gigawatts of publicly announced data center projects and CommBank's 7 gigawatt central case. The discrepancy arises because most projects lack regulatory approval and developers often announce maximum long-run capacity, leading to duplication of demand signals across the supply chain.
- 6:05 – 7:19
Investment Scale and Import Intensity
Jerogin estimates $260 billion in total investment for the 7 gigawatt pipeline, with $150 billion expected by 2030. However, she notes that 70% of construction costs are for imported IT equipment (chips, servers), meaning only ~30% ($78 billion) directly boosts domestic GDP through construction and infrastructure.
- 7:19 – 14:49
Net GDP Benefit and Labor Market Impact
Clarke calculates a net GDP benefit of 1.2% after subtracting an estimated $24 billion annual cost for imported AI services and IP. He addresses concerns about 180,000 reduced labor demand, framing it as a 1.2% labor force reduction over five years, likely absorbed through redeployment and wage gains rather than mass unemployment.
- 14:49 – 22:06
Sectoral Winners and Losers
Clarke identifies IT, telecommunications, finance, and professional services as industries most exposed to AI augmentation due to high digital native status. Conversely, accommodation, food services, and construction are less affected due to physical constraints, though mining is noted as a top adopter due to existing automation.
- 22:06 – 26:15
Constraints: Energy, Social License, and Policy
Jerogin identifies energy availability (forecast to rise from 3% of NEM usage in FY26 to 13% by 2035-36), community opposition (noise, heat, resource competition), and copyright policy uncertainty as the primary constraints hindering data center development in Australia.
- 26:15 – 30:33
Labor Market and Fed Outlook
Economist Harry Ottley discusses upcoming Australian wage and labor force data, expecting unemployment to hold at 4.7% and rise to 5.1% in 2027. He notes a hawkish shift in Fed rhetoric, suggesting further rate hikes are likely as the FOMC focuses on inflation.
Assets discussed
| Asset | Kind | Stance | Context |
|---|---|---|---|
| MicrosoftMSFT | equity | neutral | So an AI lab at the top may contract 100 megawatts of capacity with a hyperscaler, say Microsoft, and then Microsoft may come to an |
| Anthropic | private company | neutral | Lucinda earlier mentioned anthropic and OpenAI. which together account for so much of the global data center demand. |
| OpenAI | private company | neutral | Lucinda earlier mentioned anthropic and OpenAI. which together account for so much of the global data center demand. |
“Stance” is how the speakers talked about the asset, not a recommendation.
Claims worth verifying
AI will increase Australia's GDP by about 2% ($58 billion) over the next five years.
Unidentified speaker (speaker_1) ·1:19
How to verify: Check CommBank's internal economic model or published research report titled 'How Could AI Adoption Change the Australian Economy?' or similar Q3/Q4 2026 macro outlooks from Commonwealth Bank of Australia. For recent events, verify 2026-08-17 through 2026-11-17. Use another period only when the speaker explicitly names it.
More than three-quarters of the 23 gigawatts of publicly announced data center projects have not received regulatory approval.
Unidentified speaker (speaker_2) ·3:33
How to verify: Review Australian government infrastructure approval registries or industry reports from the Data Centre Association of Australia (DCAA) regarding project status as of late 2026. For recent events, verify 2026-08-17 through 2026-11-17. Use another period only when the speaker explicitly names it.
Only about 5.6 gigawatts of data center projects have received regulatory approval or are actively under construction.
Unidentified speaker (speaker_2) ·3:33
How to verify: Cross-reference with infrastructure project trackers or regulatory filings from state planning authorities in NSW, QLD, and NT. For recent events, verify 2026-08-17 through 2026-11-17. Use another period only when the speaker explicitly names it.
Primary sourceThere are around 100 developers seeking connection for data center projects, but only 6-8 major buyers contract the capacity.
Unidentified speaker (UNKNOWN) ·4:21
How to verify: Verify against Australian Energy Market Operator (AEMO) connection queue data or industry analysis from AEMO published between 2026-08-17 and 2026-11-17. For recent events, verify 2026-08-17 through 2026-11-17. Use another period only when the speaker explicitly names it.
OpenAI and Anthropic's global compute requirements equate to around 23 to 28 gigawatts globally.
Unidentified speaker (speaker_2) ·5:55
How to verify: Check public reports from OpenAI and Anthropic on their compute infrastructure investments, or third-party analysis from firms like McKinsey or Goldman Sachs on global AI capex. For recent events, verify 2026-08-17 through 2026-11-17. Use another period only when the speaker explicitly names it.
Australia is expected to capture around 10% of global demand for OpenAI and Anthropic compute, equating to 7 gigawatts.
Unidentified speaker (speaker_2) ·5:55
How to verify: Verify against CommBank's specific economic model assumptions published in their AI/Data Centre research notes. For recent events, verify 2026-08-17 through 2026-11-17. Use another period only when the speaker explicitly names it.
Australia currently has around 2.2 gigawatts of total rated data center capacity.
Unidentified speaker (speaker_2) ·6:12
How to verify: Check industry reports from the Data Centre Association of Australia (DCAA) or energy market operator (AEMO) on current data center load. For recent events, verify 2026-08-17 through 2026-11-17. Use another period only when the speaker explicitly names it.
Total investment for the 7 gigawatt pipeline is estimated at $260 billion, with $150 billion expected by 2030.
Unidentified speaker (speaker_2) ·6:32
How to verify: Verify against CommBank's infrastructure investment forecasts or Australian Bureau of Statistics (ABS) capital expenditure data projections. For recent events, verify 2026-08-17 through 2026-11-17. Use another period only when the speaker explicitly names it.
70% of data center construction costs are for high-value IT equipment (chips, servers) which is imported.
Unidentified speaker (speaker_2) ·12:40
How to verify: Check ABS input-output tables for construction vs. equipment imports, or industry breakdowns from data center operators like NextDC or Microsoft. For recent events, verify 2026-08-17 through 2026-11-17. Use another period only when the speaker explicitly names it.
Data centers consumed around 3% of NEM energy in FY26, forecast to rise to 8% by 2030 and over 13% by 2035-2036.
Unidentified speaker (speaker_2) ·22:44
How to verify: Verify against Australian Energy Market Operator (AEMO) National Electricity Market reports for FY26 and future demand forecasts. For recent events, verify 2026-08-17 through 2026-11-17. Use another period only when the speaker explicitly names it.
Primary sourceDo your own research
- Verify the $58 billion GDP impact figure against CommBank's full research report or official press releases.
- Check the status of the 23 gigawatts of announced data center projects via Australian Energy Market Operator (AEMO) or state government planning registries.
- Review the 70% import intensity assumption by analyzing capital expenditure breakdowns of major hyperscalers (e.g., Microsoft, Amazon, Google) in their SEC filings.
- Monitor the National Electricity Market (NEM) energy consumption forecasts against AEMO's Electricity Statement of Opportunities (ESOO).
- Assess the labor market impact by reviewing Australian Bureau of Statistics (ABS) data on unemployment rates and sectoral employment shifts.
- Investigate copyright policy developments in Australia that may affect AI service costs and IP licensing.
- Compare the 1.2% net GDP benefit against independent economic models from institutions like the Reserve Bank of Australia (RBA) or Treasury.
- Verify the Fed's hawkish shift by reviewing the latest FOMC meeting minutes and Federal Reserve Chair press conference transcripts.
Full transcriptexpand
0:02Mandy Drury: Listener. Hello and welcome to Combank View Economics and Markets, where we unpack all the key issues moving and shaking out there in the global markets and economies every single week. My name is Mandy Drury, and I'm always very happy to be joined by Combank's economists and strategists. So Australia's data center centre pipeline is expensive. expanding at a rapid pace. Of course, this is driven by demand for cloud computing and artificial intelligence. However, increasingly, it also faces constraints around energy, water, and community opposition. So, what can the data centre build out offer the Australian economy? And can all of those gains be realised? Let's ask Ashwin Clark, Senior. economist, and also Lucinda Jerigan, who is economist also at Combank, and thank you both very much for joining us today in the podcast studio. So, Ashwin, let me start with you first of all, because there is, of course, on both sides enormous excitement and then enormous anxiety
1:08about this data centre center build-out build out and what AI could mean for the Australian economy. How big a deal do you think AI could? be for our economy over the next five years?
1:18Unidentified speaker (UNKNOWN): It's
1:19Unidentified speaker (speaker_1): a good question, Mandy. And yeah, we we think the potential is is very large for AI to improve the economy's productive capacity. Just over the past 12 months, we've seen a massive increase in not just the usage of AI, but also the potential for AI to do things that it couldn't do. just a little while ago. So we've built an economic model to help us think through these issues. And that economic model suggests that over the next five years, we estimate that AI will increase GDP by about 2%, which is about $58 billion in today's terms, in terms of the level of annual GDP. It might sound like a small number, but it is quite transformative. To give you a sense of comparison, it's about the benefits that we saw during the mining investment boom in the 2010s, which was also very transformative for the Australian economy. So the gains are potentially very large for AI.
2:22Mandy Drury: I mean, we've also got um the the hope that there could be productivity gains, not just additional. addition to GDP, but also productivity. And we talk a lot about that given the fact that productivity has been so sluggish in Australia for many years. But Lucinda, for those productivity gains to happen through AI, we're going to need an awful lot of compute power. We spoke about data centers, you and I, recently on the podcast, and the numbers since then have actually gotten a whole lot bigger, right? Let me just take a look at the numbers here. We have around twenty-three gigawatts of publicly announced projects, but your central case is only coming in around seven gigawatts. So why that big gap between what's being publicly announced and what you actually think will happen?
3:05Unidentified speaker (speaker_2): Yeah, it's a really good point to highlight, Mandy. Uh publicly announced projects have just continued to increase rapidly.
3:13Unidentified speaker (UNKNOWN): But
3:13Unidentified speaker (speaker_2): what what really distinguishes that 23 gigawatts from our 7 gigawatt central case fundamentally comes down to feasibility and underlying demand. So, first up, most of those publicly announced projects are at very early stages of development. More than three-quarters of that 23 gigawatt pipeline haven't received any sort of regulatory approval. Only about 5.6 gigawatts have received that approval or are actively under construction.
3:42Unidentified speaker (UNKNOWN): Now,
3:42Unidentified speaker (speaker_2): to add to this, developers often seek approval for the maximum long-run potential capacity of their data center, even when only a fraction of that is expected to be built initially.
3:53Unidentified speaker (UNKNOWN): Now,
3:54Unidentified speaker (speaker_2): a second and really important point I want to highlight is that a lot of these publicly announced projects may actually be competing for the same underlying demand. And Australia's energy market operator, AIMO, estimates that there's around a hundred developers or over a hundred developers in Australia that are seeking connection for data center projects, but only about six to eight major buyers contract that capacity.
4:21Unidentified speaker (UNKNOWN): And
4:21Unidentified speaker (speaker_2): it's really a question of why is this happening? It comes down to the structure of Australia's data. center industry. And you can kind of think of it as a sort of delivery pyramid. You have your AI laboratories at the top, and these are the fundamental drivers of underlying compute demand, with layers all the way down to the bottom of Australia's data center providers who design, build, and operate these facilities. In between, you have your hyperscaler companies and your neo clouds that helped provide that computing capacity. to the AI laboratories and other customers. Now, the nature of this structure means that announced projects can actually overlap in the demand that they're servicing. So an AI lab at the top may contract 100 megawatts of capacity with a hyperscaler, say Microsoft, and then Microsoft may come to an Australian data center provider who actually builds and develops that data center. say a next DC. Now, the same 100 megawatt compute requirement can appear multiple times through the layers of that pyramid, but it's still only 100 megawatts of compute capacity needed. And so we suspect that there's some duplication happening in these project announcements without actual rise in
5:35underlying demand. So when we took a look at our S. estimates of underlying demand based on the two major AI laboratories, OpenAI and Anthropic, we found that their global compute requirements equate to around 23 to 28 gigawatts globally. Now, our central case in Australia for that seven gigawatts sees us capture around 10% of that global demand. And
5:59Mandy Drury: we should say that, I mean, 23 gigawatts is one thing, but even central seven gigawatts is still enormous, isn't it?
6:05Unidentified speaker (UNKNOWN): So
6:06Mandy Drury: in in in terms of investment size, what would that draw in? And what would it mean, therefore, for the Aussie economy?
6:12Unidentified speaker (speaker_2): And yes, that's exactly right. Seven gigawatts is still a huge development pipeline for Australia. And it's important that it's additional. So currently Australia has around 2.2 gigawatts of total rated data center capacity. With our 7 7-Gigawatt gigawatts, base case, that would take total rated capacity to 9.2 gigawatts. And we expect this to be delivered by around the mid-2030s.
6:35Unidentified speaker (UNKNOWN): So
6:35Unidentified speaker (speaker_2): this means we're talking about more than quadrupling the size of the data center industry in under a decade, which is massive. So, in terms of dollar figure amounts, we estimate around $260 two hundred and sixty billion dollars in investment, but that will take time to come through. So if the listeners cast their mind back to our podcast we did a few months ago, we said that we expect uh $150 billion in investment to 2030, and we still think that's the case. But then the remainder of the $110 billion will come through in the years following to see the full seven gigawatts delivered by the mid-2030. twenty thirty.
7:09Unidentified speaker (UNKNOWN): And
7:09Mandy Drury: These are all big numbers, but Ashwin, there seems to be a bit of a wrinkle here because you know, even if in theory you know, your research is saying that we could see businesses and workers here in Australia, you
7:19Unidentified speaker (UNKNOWN): know,
7:19Mandy Drury: be enhanced by productivity gains, you know, through AI, at the end of the day, your research also says that Australia doesn't necessarily keep all of the benefit. Can you explain to us and walk us through that?
7:32Unidentified speaker (speaker_1): Sure, yeah. So I mentioned that there will be a kind of gross boost to overall labor productivity and output by about two. 2%. But of course, to get that, we're going to have to pay for the AI services that help generate that boost. So,
7:47Unidentified speaker (UNKNOWN): you
7:47Unidentified speaker (speaker_1): know, we have data centers in Australia. A lot of that is imported. As well as the intellectual property that kind of creates the AI models, that's imported as well. And so a lot of the value chain that creates these AI services, we're going gonna to pay, have to pay over. overseas countries to get that in. So we've done an exercise to think about well, what's the annual kind of capitalized cost of a data center? What's the margin that uh the AI companies will make on that? Uh and based on our estimates, we think the overall cost of AI services in about 2030, in about five years, is is about $24 billion. But there's still a benefit after that. So, like I said, there's a 2% gross benefit, and then you take away about 0.8% of a cost, and you'll get in the end a net benefit to GDP of about 1.2%, which is still pretty large in the overall context of GDP Gry.
8:44Mandy Drury: And there are also questions, aren't there, increasingly in the news about whether or not Australia's labor market labour can handle this transition? Because we've had a number of very high profile companies in recent years which have had la very visible layoffs either through tech transformation or AI, you know, just a few names that come to mind are like, you know, Canva, Atlassian, Qantas, even Banks. So your modelling initially points to lower labour labor demand, equivalent to around 180,000 jobs. How should we be interpreting? that number though? And why doesn't your central case ultimately mean that that 180,000 people are without a job?
9:24Unidentified speaker (speaker_1): So I I acknowledge that 180,000, that number might might be quite shocking to some people. Um it is 1.2% of the labor force, but we really have to put that in context. So um first of all, it's over five years. I think
9:38Unidentified speaker (UNKNOWN): that's
9:38Unidentified speaker (speaker_1): really important.
9:39Unidentified speaker (UNKNOWN): Uh
9:40Unidentified speaker (speaker_1): second of all, we we actually don't think there's gonna be 180,000 job losses. Uh we we use a a little bit of a um uh a softer term, which is a reduction in labor demand. And we th we genuinely think a lot of the jobs that will be transformed will be within firms. Firms will redeploy people, they'll retrain people. I think the other thing to keep in mind is that there's always labor force churn in the economy. So over the past five years, five and a half million people have changed jobs. So when you think about 180,000 in that context, it's not that big. It's less than 5%. And so we do think that the economy will be able to absorb those jobs. And let's not forget that a lot of the gains that we'll get from AI, it will go back into people's pockets and higher into higher wages. It will go back into businesses' pockets, which will re-invest, and that will generate more demand to absorb job losses that come out of AI.
10:38Unidentified speaker (UNKNOWN): Trevor Burrus, Jr.
10:38Mandy Drury: In the near term, though, that lower labor demand, is it being complicated by the fact that we've also got, from a macroeconomic point of view, a slowing environment?
10:47Unidentified speaker (speaker_1): And I I think this is a bit of a worry. Like when we looked at the literature we did see that when you tend to have technological change at the same time as a downturn in the economy, that can exacerbate the job losses that come from it. But we are still expecting the downturn that we expect We to see in 2027 to be relatively shallow. And we still expect the labor market to remain. sort of relatively resilient despite easing a little bit. And so we think that that should ease some of the risks, the downside risks. But you know, we do worry that if if this happens very quickly, it it could create more job losses than we expect. It's definitely a risk, but that's not our base case. We do think it'll take time. When you look at history, it just takes time for technology to fully be. absorbed by businesses and households.
11:41Mandy Drury: That's a good point. We're talking about a multi-year story here, aren't we? And so, Lucinda, to that point, you know, before we really see AI transforming productivity and/or jobs, is the more immediate economic story in the here and now about the actual construction of the data centers? And would you call it a boom at the moment?
12:00Unidentified speaker (speaker_2): I think there's a significant opportunity at And so as I mentioned, we see about $260 billion in investment. But it's important to distinguish, and Ashwin alluded to this earlier, that that's not a direct boost to GDP because of the high import intensity of this construction. So this really comes down to a large portion of data center construction cost costs is spent on actually the high value IT equipment inside it rather than the constructing the building itself. So we estimate that around 30% of the construction cost is on that building and its core infrastructure works. If you take our $260 billion investment figure, then you're looking at around $78 billion. But the larger largest 70% share is on that high-value high value tech equipment. So you can think of a AI chips, servers, processors, networking equipment. And Australia doesn't manufacture most of that equipment. And so this means it has to come through a highly specialized global supply chain. And as a reminder to our listeners, we mentioned this in our previous podcast, but we estimate around two thirds of total data center Centre investment will flow offshore through imports. And that mutes the direct effect to GDP. So there's still work here for construction firms, installation teams, but that
13:20boost to GDP will be far smaller than those investment numbers suggest. Trevor
13:24Unidentified speaker (UNKNOWN): Burrus, Jr.
13:24Mandy Drury: Is the data center construction cycle, though, pulling away from the ability to build residential homes? Obviously, you know, affordability and availability of homes is a big political hot potato. So is is is is a it an argument that is valid that it is sucking away, you know, labour and and capacity from the residential construction sector?
13:47Unidentified speaker (speaker_2): Well, I think more broadly there's just so much work that needs to be done in the Australian economy. Yes, we have to build more housing. We have an Olympics build up in Queensland, we have a renewable energy transition, and then to add on top of this, we're looking at building seven gigawatts of diet. data centers. So there's definitely a lot of work going on. And at the same time, we have a shortage of many construction workers that are pivotal to all these different developments. So it's definitely a piece of the pie that is weighing in on trying to get finite resources.
14:31Unidentified speaker (UNKNOWN): So
14:31Mandy Drury: Ashwin, it's clear that AI and the data center build-out isn't going to affect all sectors in Australia equally. Some might be actually negatively affected to my earlier point. Which industries stand to gain the most from AI and which ones are more negatively exposed, according to your research?
14:49Unidentified speaker (speaker_1): So when we looked into this. um, we we looked at a range of things to help think about the industry level impact. Um I think the first thing is just the jobs in a given industry, how exposed are they to either being augmented or automated by AI? But it's not just that. Um, it also um is determined by how digitally native the companies are in those industries. how much uh you know the other constraints, physical constraints, regulatory constraints might limit that. So we looked at a broad range of those kind of factors. And where we ended up is we think the the industries that'll be most affected.
15:29Unidentified speaker (UNKNOWN): Uh
15:30Unidentified speaker (speaker_1): industries like IT and telecommunications, not no surprises there. I I I think for most people, uh finance as well, um, very very high tech workforce, very large companies which have tech budgets to allow for AI adoption. Um professional services as well. It's a very um uh a sort of a d desk job where you know a lot of tasks can be delegated to to AI. Um on the other s sort of end of the spectrum though, um things like accommodation and food services will be. the least effective. It's really hard to replace a cook in a kitchen currently. For now at least.
16:10Unidentified speaker (UNKNOWN): I'm
16:11Mandy Drury: sure the robots will be cooking
16:12Unidentified speaker (UNKNOWN): our
16:12Mandy Drury: food in the future. They're already serving our food in some
16:14Unidentified speaker (UNKNOWN): restaurants.
16:15Unidentified speaker (speaker_1): And I mean look I I mean Lily's just been to Japan. I mean,
16:18Unidentified speaker (UNKNOWN): I'm not
16:18Unidentified speaker (speaker_1): sure if you
16:18Unidentified speaker (UNKNOWN): saw a
16:19Unidentified speaker (speaker_1): bit more of that there,
16:19Unidentified speaker (UNKNOWN): but uh
16:21Unidentified speaker (speaker_1): Um But um, you know, for now in Australia, like things like construction as well, like very physical jobs where um, you know, we're still a while yet before um AI within the combination of robotics is just gonna start sort of really materially enhancing the sector. Uh but it's pr gonna be pretty mixed. I mean, one interesting finding we did is m mining's actually kind of t at the top of the list. Um uh you know, off people often saying And mining is just digging things out of the ground, but um we have one of the most advanced advan mining sectors in the in in the world. Um, you know, we have a lot of automation already. Um and you know, we do we are optimistic about the the fact that they'll be able to implement AI um perhaps a bit faster than some other industries.
17:01Mandy Drury: I'm really glad that you raised um you know the interesting anecdote about Japan. And it's certainly, you know, the same for other countries like South Korea and China, which have very, very top-heavy populations, you know, aging populations so increasingly you know, we're seeing robotics and automation really come to the fore. But in terms of Australia, we're not quite maybe at that stage, but how transformative AI could be for our economy. And we've also got a fairly pro-data center government, don't we, compared to the restrictive policies of some other jurisdictions around the world. What will determine whether or not AI will be positively beneficial? and transformative for us, Ashwin, you first?
17:42Unidentified speaker (speaker_1): To me, I think the key is is adoption. I think, you know, we're fairly confident that AI has cap uh the potential. But it's whether businesses and households work together and and government work together to adopt and whether we're flexible enough for that. Whether we put in place the right policies to support um retraining, redeployment in the workforces, workforce, I think is a really another important aspect of that. Mm-hmm.
18:11Mandy Drury: What about you, Lucinda? What do you think?
18:12Unidentified speaker (speaker_2): I'd say from the infrastructure side, there there is significant opportunity for Australia. We have key advantages uh in terms of attracting data centres. We have a stable political environment, we have a strong geographic position, we're closely aligned with the US. and enormous renewable potential. But I think what it will really come down to is what role does Australia play in the broader global data center industry? I think servicing our own domestic demand is one thing, but if we become a major location for AI training and large-scale Large scale inference, it's really quite different. And so if Australia can attract strong demand from those global AI labs to train frontier models and supply large amounts of computing power to the world, that's a much greater opportunity for us here.
19:01Mandy Drury: That's such a good point, Lucinda, about whether or not Australia can really become a global AI hub as opposed to just servicing domestic demand. But to that point, um, Ashwin, Lucinda earlier mentioned anthropic and OpenAI. which together account for so much of the global data center demand. There are wobbles though in the AI patch at the moment. Do you think that we will see progress being slowed down?
19:26Unidentified speaker (speaker_1): So we've always expected there w there would be wobbles along the way. This isn't necessarily going to be a smooth ride. I think what it comes down to when you think about the future and what that looks like is will there be underlying demand for compute? And and to that question, I think the answer we think is resoundingly yes. There will be. And that means there's going to be demand to support a data center rollout. And so I think in the medium term, we're fairly optimistic about both AI uptake and the data center rollout. Um, but there are going to be bumps around along the road, and I think there's this, you know, what we're seeing now is a clear example of that.
20:05Mandy Drury: Indeed. And of course, your research shows that there are quite a wide variety of outcomes on this point. So what would what what would be maybe one of the one or two things that you would be watching as to whether or not we're heading towards the more transformative end of the spectrum or a more modest, easier she goes outcome with a few more bumps along the road?
20:25Unidentified speaker (UNKNOWN): You
20:25Unidentified speaker (speaker_1): know, this is a it's it's such a good question. And, you know, I I think I I bring my sort of mind back to the mining boom, um, where things are pretty simple. It was, you know, d is the mining boom happening? Yes, there's more iron or going on ships. I think this time it's gonna be a lot more complicated in what you watch. You're gonna have we're gonna have to put the p pictures together to to understand what's going on. Things that I'm particularly attuned to at the moment, I think labor market data. Um a lot of uh the the official sector of the ABS, as well as some of the other labor market indicators like uh out there, like job advertisements, they're increasingly paying attention to the impact of AI. And that's going to give us a real good insight into whether AI is being adopted, as well as whether it's gonna lead to augmentation or automation. So I think that's one thing. The other thing I'm really paying attention to is just the public reporting by AI companies, which is just such a good uh real time indicator of how the AI rollout globally is going, gives us a sense of, well, is it
21:30is it what it's gonna be promised to be? Um, or are we gonna going to see further bumps along the road? Mm-hmm. Um but, you know, those are two things. but we're really putting the pieces together, looking at really lots of different sources of data to give us an idea how things are going.
21:46Mandy Drury: So sort of circling back right to the beginning of the conversation then, Lucinda, around some of the constraints that might be hampering data center build out at the moment. And uh we mentioned energy and water and yes, they're valid concerns, but are these concerns easily solvable? or are they concerns which do necessarily fuel community opposition because it is something that we need to be worried about?
22:10Unidentified speaker (speaker_2): Yeah, there's definitely many constraints to the data center build-out. And as you've named, energy, water, increasingly community opposition. We are really watching three key main things. And two of them you've you've touched nail on
22:24Unidentified speaker (UNKNOWN): the
22:24Unidentified speaker (speaker_2): head is energy social licensed. license or community opposition, but also interestingly, um just uncertainty around government policy and copyright law. So we think the biggest constraint is energy. And we it's not just about generating enough energy for these data centers, it's about getting reliable energy to the right sites and with the grid connections to support them. So data centers are estimated to have consumed around 3% of NEM energy in FY26. Now that's forecast to rise to 8% by 2030 and then over 13% by 2035-2036. That requires substantial expansion of our energy infrastructure. And without it, we could see delays in projects or withdrawal of investment to other places. overseas. Now, the second issue is social license, and that community opposition is really a growing concern. We've seen uh significant opposition to major developments in Queensland and the Northern Territory, and even some withdrawing of projects here in New South Wales. So we'll be looking to watch how that pans out. And then the final risk is really policy uncertainty related. to copyright law and AI training. So
23:42AI training involves processing large amounts of data and material, and some of that is protected by Australian copyright law. So if there's any uncertainty around permission and licensing costs, that can definitely deter investment here. Um But those three key risks really do sit along a whole host of others. As you've mentioned, water is a key one. one, but also just planning delays and lengthy processes and shortages of construction workers in Australia. So uh there's a definitely a lot that can go wrong and we'll be watching it for sure.
24:14Mandy Drury: Well what do you see as the main reason for community opposition? I mean, obviously there is, you know, concerns around competition for for resources, um, you know,
24:23Unidentified speaker (UNKNOWN): whether
24:23Mandy Drury: that be, you know, water, energy, labour, etc., et cetera, which could therefore push up consumer costs. But is it also something as simple as I don't want to look out over a data center, not in my backyard?
24:34Unidentified speaker (speaker_2): Yeah. And it's also not a unique uh experience of Australia. So this is happening all around the world. And actually, currently we have some of the uh less extreme community oppositions than other places where you've seen memoriums memoratoriums on development put in. What we are hearing is that, yes, electricity. and water use are big ones, but also noise and heat pollution as well
24:56Unidentified speaker (UNKNOWN): are
24:56Unidentified speaker (speaker_2): causing community concerns. And just whether it benefits the community having the data center there. So a few key points.
25:03Mandy Drury: Well to finish up then Ashwin, maybe you can like tie it all up with a nice neat bow for us. In terms of net net positive, net negative, you sort of add up all the various ingredients here, AI for the Australian economy, it's something we should be looking forward to or something we should be fearful of?
25:20Unidentified speaker (speaker_1): So I think no question, we should be looking forward to it. Um history has taught us when we have technology change, it tends to benefit um smaller urban economies like Australia.
25:31Unidentified speaker (UNKNOWN): Um
25:31Unidentified speaker (speaker_1): but we have to work for it. We we have to work for it. We have to make sure that we adopt uh AI in uh in a um uh responsible way. Um and we also may have to make sure that we have the policies uh and the uh infrastructure around us to make sure that transition happens as smoothly as it can.
25:50Mandy Drury: Thank you so much to both of you for joining us today, Ashwin Clark and listening to Jeregan. It's been a pleasure to have you on the show. Thank you.
25:57Unidentified speaker (UNKNOWN): Thanks for having us,
25:57Unidentified speaker (speaker_1): Maddie.
26:03Mandy Drury: Before we let you go, let's take a look at what we can expect in the week ahead with Harry Otley, economist at Combank. Harry, always great of you to join us here in the podcast studio. We've got wages data coming out this week. What can you tell us? Yeah,
26:15Unidentified speaker (speaker_3): it's a big week for the Aussie labor market with a few different data points which we'll touch on. The first one is wage price index, and that'll be out later on today. It's an important one. Obviously, wages are a key input into the inflation dynamics and the RBA's decision-making process. We're expecting wages to pick up a little bit in the quarter from 0.8 to 0.9%. That would leave annual wages growth at 3.3%. Now, what's interesting is the RBA has put in some upgrades to their forecast for wages over the next couple of years because they're concerned around inflation expectations becoming more embedded in the wage setting process. So we are expecting a bit of a pickup from that Fair Work Commission decision to. increase award and minimum wages by 4.75%, which was a bit bigger than people had expected. But interestingly, if we look at our internal data at CBA, we get a really good read on wages growth. And we're seeing a little bit of a bump. So as I said, we're expecting it to jump up a little bit, but we're actually seeing already in our data that's coming back down again. So perhaps some of the wage pressure that the RBA is worried about is already coming out of the system a little bit. So clearly will be important to watch. to to see how wages is tracking in Australia.
27:16Mandy Drury: Yeah of course I mean if your wages aren't keeping up with inflation essentially you're getting a pay cut, aren't you? You said it's not the only data point that we're getting on the labour, uh the labour market. We're also getting the labour force survey.
27:26Unidentified speaker (speaker_3): Yeah that's right. So that's the big one each month for for the labour market in Australia, Labour Force Survey. Very volatile as we know last month we saw a about a 40K drop in employment. Now employment month to month is incredibly volatile. We try to focus on the unemployment rate. It tends to give a bit of a clearer read on what's going on in the labor market. And we've seen that rise a fair bit this year up to 4.7%. So for the data out on Thursday, we're expecting that to stay steady at 4.7%. We're expecting a little bit of a rebound in employment just due to some of the volatility, right? It dropped a lot last month. We'll probably expect it to bounce back this month. We don't think that will change any people's views. on the labor market. It is slowly loosening. And again, our internal CBA data says that we're getting around maybe 18,000 jobs per month. So we're expecting a gain of 30,000 in the seasonally adjusted numbers out tomorrow. But again, we don't think it'll change the overall view on a labor market that is slowly loosening in Australia. And we expect that to continue with the unemployment rate getting up to 5.1% into 2027. Trevor
28:25Unidentified speaker (UNKNOWN): Burrus, Jr.
28:25Mandy Drury: And just a quick follow-on from that. I mean, obviously leading up to the peak holiday buying season and Christmas, how much of those jobs are part-time or just casual?
28:34Unidentified speaker (speaker_3): Well, interestingly, again, this goes to the volatility. A lot of the weakness that we saw last month was pretty much all part-time employment. It dropped by around 70,000 in the month alone. So this just goes to this idea that it is very volatile, and and we hope that the ABS is able to seasonally adjust the data so when we do get these. big uh sales events and probably a little bit of an increase in employment in the retail sector, it's sort of seasonally adjusted so we don't necessarily see it. Uh, but things are changing all the time with those seasonal patterns, and so we might see a bit of a bounce back.
29:02Mandy Drury: Moving offshore, we've had quite hawkish rhetoric lately coming out of a number of Fed speakers. What are we what's going on at the Fed right now?
29:09Unidentified speaker (speaker_3): Yeah, so I think the nother thing to watch this week is certainly just the commentary around the Fed and and the FOMC's decisions that are coming up. We have seen what feels like a little bit of a vibe shift in terms of the communication coming from Fed speakers. Uh we do get the FOMC minutes on Thursday, uh early Australian time. So that will give us a bit more detail on the dissents that we had in the last meeting and some of the discussions that are happening around the table at the FOMC. But we also get another string of speakers towards the end of the week. So clearly we'll be looking to see if the hawkish rhetoric continues, if there's anyone who wants to push back on that sort of hawkish vibe shift that we've seen. But overall, I think that the message here is that it looks like the Fed and the FOMC members are looking to increase rates a few more times and the FOMC minutes and the communication at the end of the week will really uh provide more detail on how high rates are likely to go in the US.
30:00Mandy Drury: It seems that they're also more concerned about inflation than. growth at this juncture, but thank you so much for that look ahead for the week that we're expecting. Harry Ottley joining us there from Combank. And thank you so much for joining us today for this episode of Combank View Economics and Markets. My name is Mandy Drury. Thank you so much for your time. This podcast is not investment research and is for informational purposes only. Please visit combankresearch.com.au for the full report and the full disclaimers.