EPRI CEO Mansoor argues grid infrastructure is the primary bottleneck for AI growth due to permitting and labor constraints.
Summary
Arshad Mansoor, CEO of EPRI, explains that the US power grid is transitioning from a period of flat demand to significant growth, driven largely by AI and data centers. He highlights a structural mismatch where tech companies can deploy compute capacity in months, but grid infrastructure takes years due to permitting and labor shortages. Mansoor notes that tech firms like Google and Microsoft are now directly financing infrastructure, bypassing traditional utility rate models. He identifies skilled labor as the top constraint, followed by supply chain and permitting, while noting that current battery storage is insufficient for long-duration backup.
Key takeaways
- 1 New York electricity demand was flat from 2010 to 2026 but is projected to rise 25% in the next 15 years.
Unidentified speaker (speaker_1) · 3:17
- 2 Google can build 100 MW data centers in 18 months, whereas grid infrastructure historically took 10-15 years to permit and build.
Unidentified speaker (speaker_1) · 4:50
- 3 Skilled labor is ranked as the number one constraint for grid growth, followed by parts/supply chain and permitting.
Unidentified speaker (speaker_1) · 7:51
Episode sections
- 0:00 – 1:32
EPRI Background and Mission
Arshad Mansoor explains EPRI's founding after the 1965 blackout and its current role with global tech and power companies.
- 1:32 – 2:54
Grid Structure and Current Stress
Mansoor describes the grid's complexity and notes the shift from flat demand to growing stress on infrastructure.
- 2:54 – 4:50
Demand Growth and Financing Shifts
Citing New York's projected 25% demand rise, Mansoor highlights tech companies directly financing infrastructure.
- 4:50 – 5:56
Speed to Power vs. Speed to Trust
Contrasting rapid tech deployment with slow grid timelines, Mansoor identifies 'speed to trust' as a key constraint.
- 5:56 – 8:08
Permitting Acceleration and Labor Constraints
Mansoor argues permitting is speeding up due to necessity but ranks skilled labor as the primary bottleneck.
- 8:08 – 10:10
Grid Efficiency and Storage Limitations
Mansoor explains grid reserve capacity and notes batteries are currently limited to short-duration backup.
- 10:10 – 11:27
CEO Advice on Grid Integration
Mansoor advises CEOs to prioritize grid access alongside chip procurement for new facilities.
Assets discussed
| Asset | Kind | Stance | Context |
|---|---|---|---|
| MicrosoftMSFT | equity | neutral | We have uh Microsoft, Google, Hitachi. GE, all of the folks we work with them. |
| AlphabetGOOGL | equity | neutral | We have uh Microsoft, Google, Hitachi. GE, all of the folks we work with them. |
“Stance” is how the speakers talked about the asset, not a recommendation.
Claims worth verifying
EPRI was born out of the 1965 New York blackout and created in 1973.
Unidentified speaker (speaker_1) ·0:38
How to verify: EPRI corporate history page or SEC filings if publicly traded (check status); historical records of the 1965 blackout. For recent events, verify 2026-08-22 through 2026-11-22. Use another period only when the speaker explicitly names it.
Primary sourceEPRI works in 45 countries with almost 500 power companies and tech companies, including Microsoft, Google, Hitachi, and GE on its board.
Unidentified speaker (speaker_1) ·0:58
How to verify: EPRI website 'About' or 'Members' section; corporate press releases from Microsoft, Google, Hitachi, GE regarding EPRI board membership. For recent events, verify 2026-08-22 through 2026-11-22. Use another period only when the speaker explicitly names it.
Primary sourceNew York electricity demand was flat to slightly down from 2010 to 2026, with a projected 25% increase in the next 15 years.
Unidentified speaker (speaker_1) ·3:17
How to verify: New York ISO (NYISO) historical load data; NYISO or NYPSC long-term demand forecasts. For recent events, verify 2026-08-22 through 2026-11-22. Use another period only when the speaker explicitly names it.
Google can get 100 MW of compute ready in a data center in 18 months.
Unidentified speaker (speaker_1) ·4:50
How to verify: Google/Alphabet construction permits, press releases on data center build-out timelines, or industry reports on hyperscaler deployment speeds. For recent events, verify 2026-08-22 through 2026-11-22. Use another period only when the speaker explicitly names it.
Germany built an LNG terminal in nine months (permitted and built) two to three years ago due to the Ukraine war.
Unidentified speaker (speaker_1) ·6:30
How to verify: German government announcements or news reports on the Wilhelmshaven LNG terminal construction timeline and permitting dates (2026-2026). For recent events, verify 2026-08-22 through 2026-11-22. Use another period only when the speaker explicitly names it.
Primary sourceAP1000 nuclear power plants are being built in New York with NYPA.
Unidentified speaker (speaker_1) ·6:59
How to verify: NYPA press releases or project announcements regarding AP1000 reactor deployments in New York. For recent events, verify 2026-08-22 through 2026-11-22. Use another period only when the speaker explicitly names it.
Grid permitting and construction can take five to seven years if done right.
Unidentified speaker (speaker_1) ·7:18
How to verify: FERC or state utility commission records on transmission line permitting and construction durations. For recent events, verify 2026-08-22 through 2026-11-22. Use another period only when the speaker explicitly names it.
Current batteries can run the US grid for only about 30 minutes at full load.
Unidentified speaker (UNKNOWN) ·9:45
How to verify: EIA or NERC data on total US battery storage capacity vs. peak load; technical specifications of grid-scale battery duration. For recent events, verify 2026-08-22 through 2026-11-22. Use another period only when the speaker explicitly names it.
US natural gas storage can run the entire US gas need for one to ten days.
Unidentified speaker (UNKNOWN) ·9:39
How to verify: EIA (Energy Information Administration) weekly natural gas storage reports and US daily consumption data. For recent events, verify 2026-08-22 through 2026-11-22. Use another period only when the speaker explicitly names it.
Do your own research
- Verify EPRI's membership list and board composition via their official website or annual reports to confirm tech firm involvement.
- Check US Energy Information Administration (EIA) data for historical and projected electricity demand trends in New York and other key regions.
- Review SEC filings of major tech companies (Google, Microsoft) for capital expenditure disclosures related to energy infrastructure or direct power purchases.
- Analyze permitting timelines for recent transmission projects in states like New York or Texas to assess regulatory bottlenecks.
- Consult labor market reports from the Bureau of Labor Statistics or industry associations for data on skilled electrician and engineer shortages.
- Evaluate battery storage duration capabilities by reviewing technical specifications from major manufacturers versus grid load profiles.
- Research Germany's LNG terminal construction timeline and regulatory framework post-2022 to validate claims about permitting acceleration.
- Assess the financial models of direct power purchase agreements (PPAs) versus traditional utility rate base structures for infrastructure financing.
Full transcriptexpand
0:00Michael Johnson: Today I'm so happy to be joined by Arshad Mansoor, who's president and CEO of the Electric Power Research Institute, which we call EPRI. In this role, he deals with utilities, technology providers, policymakers, some of the most urgent challenges for the grid. And one of the things I noticed in your background is you and I both share something that we went to the University of Texas, although in your case you have both a master. master's and a PhD in electrical engineering. So that puts you in the perfect spot to answer the question about the grid. So but first let's start with EPRI. Tell us about what EPRI is and what they do.
0:38Unidentified speaker (speaker_1): EPRI was born out of a blackout in 1965. That was a New York blackout. And as a result of the blackout there was a lot of investigations what could be done better. And one of the things that came up was we got a lot of electric companies in the United States for the them to embrace new technologies and do it in a reliable way, instead of each one of them trying to do it on their own, why can't we create a group? And that's how EPRI was created in 1973. Today we work in 45 countries with more than almost 500 power companies, now tech companies, and video is in our board. We have uh Microsoft, Google, Hitachi. GE, all of the folks we work with them. Our focus is one focus. We will be independent, we'll be trusted, we'll be saying the way we see it, and we will advance technology so it can be scaled up and deployed at scale globally.
1:32Michael Johnson: Can you explain for people? We always talk about the grid. What is the grid? Is it a grid? How does it work? And how close are we to blackouts? So
1:42Unidentified speaker (speaker_1): the grid, when you flip the switch and the light turns on, there is something that you don't see, which is somewhere you're making the electricity. You don't even see that anywhere here. You're making the electricity in big generation plants and gas turbines. Sometimes you see large solar plants, you see wind turbines. That's all where we make electric
2:02Unidentified speaker (UNKNOWN): plants.
2:02Unidentified speaker (speaker_1): electricity. And when you turn the switch on, that electricity that was generated somewhere in the United States comes and lights you in that entire interconnected system, which is the generators are everywhere. New York has generation, California has generators, transmission, which is taking those electricity, bringing close to cities, that's everywhere. And then you distribute it, which is now you bring house by house by house. And inside the building, you also distribute it at every socket.
2:35Michael Johnson: So it's a it's a complicated piece of machinery.
2:38Unidentified speaker (speaker_1): The most complicated piece of machinery, but it is made very simple for people to use it. You just plug in your computer, you don't worry where the electricity is coming from. How is it coming from? You just flip this. the switch and magically the light turns on.
2:54Michael Johnson: So let's let's talk about the magic. We had load growth pretty flat in this country for a 20-year period, and now it's taken off again. And a lot of the latent pockets of power have been stopped up, right? And now we feel like we're at getting to a point where we're stretching stressing the grid more than we have been. How does that show up? What happens when we stress the grid like that?
3:17Unidentified speaker (speaker_1): New York is a great example. For the last 15 years, 2010 to 2026, the amount of electricity that you use in New York is actually flat to slightly go have gone down. In the next 15 years, 25% up. All of a sudden, an In industry 120, 140 years old, sees that the enabler for growth. prosperity, is how fast and how reliably can we bring more electricity to power the growth.
3:47Michael Johnson: So this complex machine that had a long period of no growth and now it's it's exploding. What are the critical ways that we're going to serve that growth?
3:56Unidentified speaker (speaker_1): I think the step one is
3:59Unidentified speaker (UNKNOWN): you
3:59Unidentified speaker (speaker_1): gotta got to make sure that the lights are on for everybody. that the grid serves. So that trust with the society that I need my lights to be on and I don't want my electric bill to go up, I think that's the first constraint that has to be met before you look at how do you meet the demand. How do you meet the demand? And We're seeing new ways how you finance that. So you're not just financing off the electric bill that you are paying every month on your electricity. It's being financed directly by Google, by Microsoft. And maybe Micron will come in, and Micron will take some share of all the new infrastructure that you will build. So that's a brand new way of we are seeing, which is helping. In areas where permitting can be done quickly. We are seeing what used to take 15 years, 10 years,
4:49Unidentified speaker (UNKNOWN): are
4:50Unidentified speaker (speaker_1): now actually starting to happen more quickly. It's two different clocks at running at two different speeds. If I am Google, I can get compute 100 megawatt ready in a data center in 18 months. That's their speed. That's their clock. You want transmission and power and everything ready for that. That clock five years ago would take 10 to 15 years. What's missing though in this growth era, we are in our second year, let's have the growth era, is
5:19Unidentified speaker (UNKNOWN): the
5:19Unidentified speaker (speaker_1): speed to trust. I think that clock is running slow.
5:25Unidentified speaker (UNKNOWN): The
5:26Unidentified speaker (speaker_1): speed to trust of people, that my bill will not go up, that the infrastructure will remain reliable. I will still get power, it will be reliable, and my bill will not go up. I think that needs to be addressed
5:43Unidentified speaker (UNKNOWN): in
5:43Unidentified speaker (speaker_1): the near term for making sure that we come to another era where once again electricity is driving prosperity and is the growth.
5:56Michael Johnson: I've read before that the average time to permit a a longer transmission line is fifteen. to seventeen years. You're actually seeing it come down to what? Say that again? How many
6:07Unidentified speaker (UNKNOWN): of you are So
6:07Unidentified speaker (speaker_1): I would say that was then, this is now.
6:09Unidentified speaker (UNKNOWN): Yeah.
6:10Unidentified speaker (speaker_1): And I also say necessity is the mother of invention. And I give the example in Germany, because of all the right reasons, sustainability, you gotta look at environmental protection, their permitting time was even longer. We want to do an L LNG and G terminal that's fifteen 15 to twenty 20 years. And two, three. years ago, because of the Ukraine war, they had a winter that they could have to turn the lights on. They built flat out in nine months a terminal to bring LNG.
6:38Michael Johnson: Permitted and built.
6:39Unidentified speaker (speaker_1): Permitted and built. So where there is a will, there is a way. And we are now seeing that will. We're now seeing that will in New York. Two years ago, I'll come to New York. Nuclear power, you don't even say that. the word nuclear power. We're now working with NIPA, New York Power from one of the utilities. And we want to build large AP 1000 nuclear power plants in New York. The rising tide will float everybody's boat, the amount of jobs that it will create. Electricity cannot be the bottleneck. So how long does it take to pour me the transmission line today? Depends where you are, but if things are done right I think we can get permitted built five years, seven years. It could be done quicker if the permitting process is even more shrinked. When I say about speed to power, I see that as
7:30Unidentified speaker (UNKNOWN): I
7:31Unidentified speaker (speaker_1): think the number one constraint is going to be people. The amount of skilled labor that you would need. I mean, building a one gigawatt micron, all your electricians in New York is going to go there. High-paid job, great job. And now you're going to be building transmission lines. Now you're going to be building data centers. And people is number one constraint that we will have to address. Parts are the number two. The supply chain is going to be huge. And then permit. So I call it people, parts, permit. We've got to fix all those three. And I think we can. I think we can, we will, because the opportunity is huge.
8:08Michael Johnson: The other two ways that we think about to debottleneck the grid are enhancing grid efficiency because we only use half the power we make on any given day. And behind the meter power. Can you talk about those?
8:24Unidentified speaker (speaker_1): On the hottest day in New York, I'm using everything. that the grid has. Today is a beautiful day. I'm maybe using 50% of the grid. So does that mean 50% of the grid is empty, inefficient, not used? No, they are kept for the hottest day. They are kept for contingency. Can we flex on the hottest day? Let's use the batteries to supply. That is happening now at a much faster pace. Because when growth comes in, you already have an existing infrastructure. Can I use that more to fuel that growth while I'm building new? You have to build. And now Google and Microsoft, they're all working with us to come up with ways that they can actually back off from the grid.
9:09Michael Johnson: How close are we at any given month, at every given August day or where the the power loads most by having either rolling brownouts or somebody tripping a wire somewhere?
9:21Unidentified speaker (speaker_1): So you can never say never. How close are we, you know, but if you look at the way the grid is evolving, I think the reliability you have in New York ISO here, you have the utilities. I don't think we are close closed just because the demand is going up. We got enough gas stored in the US.
9:39Unidentified speaker (UNKNOWN): that
9:39Unidentified speaker (speaker_1): I can run the entire gas need for US one day, two days, five days, ten days.
9:45Unidentified speaker (UNKNOWN): The
9:45Unidentified speaker (speaker_1): amount of electricity that we have stored, I cannot run it for one minute. And so it's coming to a point where are we going to have enough parodies so that the US grid can run on batteries for one day? I said, Yeah, I will have enough parodies batteries for the US grid to run on batteries for maybe 30 thirty minutes. So it's never going to be natural gas. Right. So today's batteries, they're sprinters, they're doing 100 meter, 200 meter sprint. They will never run marathon.
10:10Michael Johnson: Arshad, can I ask you for the C-suit for the CEOs of companies in America when they think about the grid? What's one or two areas that they should focus on?
10:19Unidentified speaker (speaker_1): I think right now they should focus on the grid is as much important for us as anything else that we have. Speak to power. I need to build relationships with grid companies. I need to find out can I get power in the time that I need? And I need to find out where power is available that I can bring my new factories in. See, all of a sudden we have entered an era where energy, electricity, and
10:46Unidentified speaker (UNKNOWN): if
10:47Unidentified speaker (speaker_1): you call data center or AI, they are two sides of the same coin. So if you're a CEO,
10:53Unidentified speaker (UNKNOWN): you
10:53Unidentified speaker (speaker_1): thought grid is somewhere there, you don't even think about
10:56Unidentified speaker (UNKNOWN): it.
10:57Unidentified speaker (speaker_1): You need to think about it at the same time you're thinking about where are you going to get the chips?
11:02Unidentified speaker (UNKNOWN): Or
11:03Unidentified speaker (speaker_1): where are you going to build the micron factory? So that's, I think, what the CEO is. The grid is becoming number one bottleneck, but number one enabler for what you're trying you to do. try
11:15Michael Johnson: Arshad, Dr. Grid, I want to thank you so much for joining us here today. Thank you.
11:20Unidentified speaker (speaker_1): Thank you. Thank you for having me
11:22Unidentified speaker (UNKNOWN): here.