FactSet Insight

Texas regulators review $11B Permian Basin transmission projects amid political shifts and regulatory delays

12 min Listen to the original Episode page
Texas EnergyTransmission InfrastructureRegulatory ProceedingsUtility FinanceERCOTPermian Basin

Summary

Texas regulators are evaluating five proposed 765 kV transmission projects, estimated at $11 billion, to transport power into the Permian Basin. The Public Utility Commission of Texas (PUCT) has approved Import Paths 1 and 3, but Import Path 2 faces denial recommendations from Administrative Law Judges and remains under review. Political changes following the November 3 election, including a new governor and divided legislature, introduce uncertainty regarding the projects' future. ERCOT is implementing stricter load growth verification, requiring notarized attestations for demand projections. Landowner opposition and bipartisan political criticism have further complicated the proceedings.

Key takeaways

  1. 1
    Texas regulatory regulators are deliberating on whether to approve the state's first 765 kilovolt transmission lines, five proposed projects totaling roughly 1,200 miles with an estimated cost of $11 billion, designed to carry power from the state's other regions into the Permian Basin.

    Unidentified speaker (speaker_0) · 0:21

  2. 2
    The PUCT approved Encore projects on Import Path 1 on August 28 and the AEP Texas/CPS Energy project on Import Path 3 on September 11, while Import Path 2 remains undecided.

    Unidentified speaker (speaker_0) · 0:41

Episode sections

  1. 0:01 – 1:01

    Introduction and Project Overview

    Texas regulators are reviewing five proposed 765 kV transmission projects totaling 1,200 miles with an estimated cost of $11 billion to carry power into the Permian Basin. The Public Utility Commission of Texas (PUCT) has approved Import Paths 1 and 3 but has not yet decided on Import Path 2, where Administrative Law Judges recommended denial.

  2. 1:01 – 1:41

    Import Path 2 Status and Regulatory Delays

    Import Path 2 projects (Bell County East to Big Hill and Big Hill to Sand Lake) face unresolved proceedings after the Commission remanded them to Administrative Law Judges for further findings on need and congestion savings. The Commission voted on November 12 to not rehear Import Path 1 approvals, leaving them on track to become final, while Import Path 3 rehearing motions remain pending.

  3. 1:41 – 2:21

    Political Context and Legislative Impact

    The November 3 election shifted the Texas House to Democrats and replaced the Governor and Lieutenant Governor, creating a divided legislature that convenes in January 2027. This political shift introduces uncertainty regarding the build-out, as lawmakers have the power to reshape how or whether the projects proceed.

  4. 2:21 – 2:44

    Project Applicants and ERCOT Load Growth Concerns

    The five projects are filed by Encore Electric Delivery, LCRA Transmission Services, AEP Texas, and CPS Energy to address load growth in the Permian Basin identified by ERCOT. ERCOT's 'batch zero' large load study now requires notarized attestations for demand, reflecting concerns that previous load growth figures included unconfirmed demand from data centers and crypto mining.

  5. 2:44 – 5:42

    Import Path 2 Denial Recommendations and Remand

    On August 20, 2026, an ALJ recommended denying Import Path 2 projects due to inadequate load forecasts, insufficient generation proof, and failure to provide public meeting notice to 1,400 landowners. On September 9, 2026, Commission Chairman Thomas Gleason deemed the proposal incomplete for not addressing reliability standards and congestion savings, remanding the dockets to the State Office of Administrative Hearings.

  6. 5:42 – 7:02

    Landowner Opposition and Bipartisan Criticism

    Landowners and officials from both parties have criticized the projects over property rights and agricultural impacts. Republican officials including Dan Patrick and Ken Paxton, as well as Democratic Governor-elect Gina Hinojosa, have called for pauses or denials, with Hinojosa campaigning against rapid construction that tramples property owners' rights.

  7. 7:02 – 8:31

    Legislative Framework: HB 5066

    The proceedings are based on House Bill 5066, signed in June 2023, which directed the PUCT to require ERCOT to develop reliability plans for regions with insufficient transmission capacity, specifically the Permian Basin. The law mandates final orders on Certificate of Convenience and Necessity applications within 180 days of filing.

  8. 8:31 – 12:01

    Financial Implications for Utilities

    Approved transmission investments are added to a utility's rate base, allowing investor-owned utilities like Encore (subsidiary of Sempra) and AEP Texas to earn returns. Municipally owned utilities like LCRA and CPS Energy do not have this earnings growth dynamic. Shares of exposed utilities have traded weaker due to concerns about the scope of approved investment.

Claims worth verifying

Five proposed 765 kV transmission projects total roughly 1,200 miles with an estimated cost of $11 billion.

Unidentified speaker (speaker_0) ·0:01

How to verify: FactSet Insight article linked in podcast summary; PUCT docket filings for the five projects. For recent events, verify 2026-08-19 through 2026-11-19. Use another period only when the speaker explicitly names it.

Primary source

The PUCT approved Encore projects on Import Path 1 on August 28.

Unidentified speaker (speaker_0) ·0:41

How to verify: PUCT meeting minutes or order documents from August 28, 2026, available on the PUCT website or SEC EDGAR if filed as a regulatory submission. For recent events, verify 2026-08-19 through 2026-11-19. Use another period only when the speaker explicitly names it.

Primary source

The PUCT approved the AEP Texas and CPS Energy project on Import Path 3 on September 11.

Unidentified speaker (speaker_0) ·0:41

How to verify: PUCT meeting minutes or order documents from September 11, 2026, available on the PUCT website. For recent events, verify 2026-08-19 through 2026-11-19. Use another period only when the speaker explicitly names it.

Administrative Law Judges recommended denying both Import Path 2 projects.

Unidentified speaker (speaker_0) ·1:21

How to verify: Administrative Law Judge Proposal for Decision documents for Docket Nos. 59475 and 59182, available via PUCT or SOAH records. For recent events, verify 2026-08-19 through 2026-11-19. Use another period only when the speaker explicitly names it.

The Commission voted on November 12 not to take up rehearing motions on Import Path 1 projects.

Unidentified speaker (speaker_0) ·1:41

How to verify: PUCT meeting minutes or order from November 12, 2026, available on the PUCT website. For recent events, verify 2026-08-19 through 2026-11-19. Use another period only when the speaker explicitly names it.

The November 3 election replaced the governor and lieutenant governor and shifted the Texas House majority to Democrats.

Unidentified speaker (speaker_0) ·2:01

How to verify: Texas Secretary of State election results for November 3, 2026. For recent events, verify 2026-08-19 through 2026-11-19. Use another period only when the speaker explicitly names it.

ERCOT's batch zero large load study requires developers to substantiate projected demand through notarized attestations.

Unidentified speaker (speaker_0) ·5:42

How to verify: ERCOT published guidelines or rules for the 'batch zero' large load study, available on the ERCOT website. For recent events, verify 2026-08-19 through 2026-11-19. Use another period only when the speaker explicitly names it.

House Bill 5066 was signed into law in June 2023.

Unidentified speaker (speaker_0) ·7:02

How to verify: Texas Legislature bill history for HB 5066, available on the Texas Legislative Reference Library website. For recent events, verify 2026-08-19 through 2026-11-19. Use another period only when the speaker explicitly names it.

The law directed the Commission to issue a final order on transmission line CCNs no later than 180 days after the application is filed.

Unidentified speaker (speaker_0) ·7:52

How to verify: Text of Texas House Bill 5066, Section [relevant section], available on the Texas Legislative Reference Library website. For recent events, verify 2026-08-19 through 2026-11-19. Use another period only when the speaker explicitly names it.

Shares of the most exposed utilities have traded weaker amid investor concern about the scope of approved Texas transmission investment.

Unidentified speaker (speaker_0) ·10:12

How to verify: Stock price performance data for Sempra (SRE) and AEP (AEP) from financial data providers like Bloomberg or FactSet, compared to broader market indices over the relevant period. For recent events, verify 2026-08-19 through 2026-11-19. Use another period only when the speaker explicitly names it.

Do your own research

  • Review PUCT Docket Records for Import Paths 1, 2, and 3 to verify approval statuses and pending motions.
  • Examine ERCOT's 'batch zero' large load study report due in December 2026 for updated demand forecasts.
  • Check Texas legislative session minutes from January 2027 for any bills impacting HB 5066 or transmission approvals.
  • Analyze Sempra (SRE) and AEP (AEP) financial filings for exposure to Encore and AEP Texas transmission investments.
  • Verify landowner opposition statements from officials like Dan Patrick, Ken Paxton, and Gina Hinojosa.
  • Review LCRA and CPS Energy municipal utility reports for any impact on their rate base or earnings dynamics.
  • Check for any updates on the Administrative Law Judges' findings regarding Import Path 2 reliability standards.
  • Monitor ERCOT's notarized attestation requirements for data center and crypto mining demand in the Permian Basin.
Full transcriptexpand

0:01Unidentified speaker (speaker_0): Hello, and welcome to the article audio series, featuring our top human-written blog articles from experts at FactSet, voiced with AI. In this episode, the Permian Basin Reliability Plan and Status of the 765-kilovolt transmission line proceedings, written by Leo Kelser, Officer, Senior Utility Analyst and Associate Director of Content. Let's begin. Texas regulatory regulators are deliberating on whether to approve the state's first 765 kilovolt transmission lines, five proposed projects totaling roughly 1,200 miles with an estimated cost of $11 billion, designed to carry power from the state's other regions into the Permian Basin. The Public Utility Commission of Texas, PUCT, has so far acted on these applications in three groups, known as import paths. It approved both Encore projects on Import Path 1, Dinosaur to Longshore and Longshore to Drill Hole on August 28, and the AEP Texas and CPS Energy project on Import Path 3, Howard to Solstice, on September 11. It has not decided the other two Encore and LCRA projects on import path 2: Bell County East to Big Hill and Big Hill to Sand

1:21Lake. Administrative law judges, ALJs, have recommended denying both, and the Commission sent the cases back to the judges for further findings rather than accept or reject that recommendation. None of these recommendations is yet final. On November 12, 12th, the Commission voted. not to take up rehearing motions on both Import Path 1 projects, which leaves those approvals on track to become final, while rehearing motions on Import Path 3 remain pending. The projects have drawn intense opposition from landowners and criticism from officials of both parties. And a larger uncertainty is now the 2027 legislative session. The November 3 election replaced the governor and lieutenant governor and shifted the Texas House majority to Democrats, while Republicans kept the Senate. So a divided legislature will convene in January with the power to reshape how or whether the build-out proceeds. Each of the five projects is the subject of a Certificate of Convenience and Necessity

2:24application filed by Encore. Electric Delivery, LCRA Transmission Services, AEP Texas, or CPS Energy. Together, they form three import paths to carry power from generation-rich parts of the state into a region ERCOT has identified as having substantial load growth, but very little local generation of its own. In our blog article, which is linked in this podcast episode summary, you can view a chart that shows the status and geography of each of these proposed projects. Both proceedings for import path two remain unresolved. On August 20, 2026, the ALJ is assigned to Docket No. 59475 issued a proposal for decision, PFD, recommending the Commission deny both the Bell County East Big Hill Project. and its companion Big Hill Sandlake Project, Docket No. 59182, consolidated with 59475 on the question of need. The ALJs found the applicants had not adequately substantiated the load forecast underlying the projects, had not shown that sufficient generation would be available in central Texas to serve as a source for the westward power track. transfer and had failed to provide required public meeting notice to approximately

3:441,400 landowners, an independent basis for denial in its own right. In a memorandum circulated September 9, 2026, Commission Chairman Thomas Gleason concluded the PFD A CFD was incomplete, stating it had not addressed two issues the Commission's March 30, 2026 preliminary order directed the ALJs to resolve: whether the projects are necessary to meet state or federal reliability standards, and what congestion cost savings they might provide to consumers. At its September 11th meeting, the Commission remanded both dockets to the State Office of Administrative Hearings, SOAH, to address those questions. That defers any decision on need and, by extension, on the ALJ's denial recommendation until the ALJs issue a supplemental PFD. The Commission has not indicated when that might occur. Okay, let's move into the broader political and regulatory context. The proceedings are unfolding alongside two related controversies. The first is a rapid rapidly intensifying statewide debate over large load growth, particularly data centers and cryptocurrency mining. In June 2026, Governor Abbott directed the PUCT and

5:03ERCOT to ensure data centers and other large loads fund their own interconnection costs rather than shifting them to residential ratepayers, and he has since halted new data center grid connections. pending an audit. Governor-elect Gina Hinojosa, who defeated Abbott on November 3, said Texas will have laws to protect residents and that data center expansion should stop until laws are enacted. So the direction of travel continues through the change in administration. ERCOT's batch zero large load study now requires developers to substantiate projected demand through notorized. notarized attestations, with a report due in December 2026. That effort reflects the same concern behind the import path 2PFD, that ERCOT's load growth figures have included a substantial share of unconfirmed demand, and that regulators should tighten the evidentiary standards used to justify major infrastructure built on those figures. The second controversy is landowner opposition to the 765 kilovolt transmission lines, a significant political issue independent of the load forecast. Beyond the notice violations found in the 59475 PFD, farmers, ranchers, and rural landowners across the affected counties

6:22have raised concerns about permanent effects on agricultural land, property values, and the time and information provided to participate in the CCN process. The criticism has crossed party lines. Before the election, outgoing Lieutenant Governor Dan Patrick, Attorney General Ken Paxton, more than 30 members of the Texas House, and several senators asked the Commission to pause or deny further approvals until the legislature could act. Republican Senate Senator Charles Schwertner called for denying all pending applications, and Hinojosa campaigned on the principle that the state cannot trample property owners' rights to build 765 kilovolt lines, quote, in record time. Some legislators, including the House author of HB 5066, have said the 765-kilovolt 765 kilovolt buildout exceeds what the legislature intended to authorize in 2023. Next, we pivot to the background on HB 5066.

7:22The legal and regulatory framework for all five dockets traces back to House Bill 5066, signed into law in June 2023.

7:32Unidentified speaker (UNKNOWN): The

7:32Unidentified speaker (speaker_0): legislature passed HB 5066 out of concern that ERCOT's existing transmission planning. process was too reactive, and that new large loads, particularly in oil and gas and industrial areas, often weren't incorporated into planning until they had posted financial security, too late to support transmission projects with multi-year development timelines. The law directed the PUCT to require ERCOT to identify regions where existing transmission capacity is insufficient to serve current and forecasted load, and to develop a reliability plan for each region, specifically requiring a Permian Basin reliability plan addressing mineral resource areas, forecasted load growth, and interconnection delays. The law also directed the Commission to issue a final order on transmission line CCNs no later than 180 days after. the application is filed. A chart in our blog article, linked in this podcast episode summary, shows the estimated cost of Permian Basin reliability projects. The costs are drawn from each docket's proposal for decision, which separately itemizes the transmission line construction cost and the associated substation, station work, cost. Figures are stated in millions of dollars.

8:51Where a PFD provided a cost range rather than a single figure for the approved or recommended route, the midpoint of that range is used. Okay, now we move on to the financial implications for utilities in Texas. Whether these projects proceed carries direct financial consequences for the state's investor investor-owned owned utilities. Transmission investment approved through the CCN project. process is added to a utilities rate base, the pool of assets on which regulators permit it to earn a return. So approval of the Permian Basin projects translates into future earnings growth for the parent companies involved. Of the applicants on the five dockets. Encore, a subsidiary of SEPRA, Sempra and AEP Texas are investor-owned and stand to benefit from rate-based growth. if their respective projects are approved. LCRA Transmission Services and CPS Energy, by contrast, are municipally owned utilities, so the earnings growth dynamic does not apply to their share of the

9:52investment. Center Point Energy Houston Electric, another major investor-owned Texas utility, does not appear as an applicant on any of the five Permian-facing Permian facing dockets. likely reflecting that its service territory lies well south and east of the Permian import paths. Shares of the most exposed utilities have traded weaker amid investor concern that the ultimate scope of approved Texas transmission investment could come in smaller than previously anticipated. And finally, looking ahead, the commission approval may not be the last word on how or where. whether these projects are built. The legislature convenes january twelfth, twenty twenty seven, with a Democratic House, a Republican Senate, and a new governor and lieutenant governor. Members of both parties have criticized the Commission's handling of the dockets, and the governor elect has said she will push for data center laws while promising a bipartisan transition. The legislature is not bound by the Commission's decisions, and any bill must clear both chambers. Lawmakers could respond by leaving the approvals undisturbed, targeting adjustments such as stronger landowner notice and participation requirements, or different cost recovery conditions, or more fundamental changes in how such lines are approved. ERCOT has

11:11reported unprecedented load growth in the Permian, and the problem HB 5066 was meant to address has not gone away, so the region will likely need additional transmission or generation in some form. The commission's time to act on the rehearing motions will run out by the end of December, while import path 2 remains in remand with no announced date for a response from the ALJs. And that wraps up this article audio. Thanks for listening. This narrated blog content is for informational purposes only. The information contained in it is not legal, tax, or investment advice. FactSet does not endorse or recommend any investments and assumes no liability for any consequence relating directly or indirectly to any action or inaction taken based on the information contained within this content.