Episode 269 argues that gross margin is insufficient for measuring job performance without tracking estimated vs actual margins.

10 min Listen to the original
Profit FadeEstimatingProject ManagementJob CostingMargin AnalysisBusiness OperationsFinancial MetricsConstruction Finance

Summary

The speaker introduces the concept of profit fade, arguing that gross margin alone is an insufficient metric for evaluating job performance. He illustrates how two jobs with identical final margins can have vastly different underlying stories based on estimation accuracy versus execution efficiency. The discussion highlights the importance of establishing an estimating feedback loop where variance data from job costing is fed back into the estimating department to prevent repeating errors. The speaker also warns against misleading metrics like revenue-per-hour, noting that top project managers are often assigned to difficult, misbid jobs while mediocre managers handle easier ones. Finally, he addresses the risks of estimators holding excessive power without visibility into bid breakdowns, suggesting practical implementation steps for legacy jobs using Work in Progress schedules.

Key takeaways

  1. 1
    In construction, measuring job performance goes so much deeper than just tracking gross profit and gross margin.

    Unidentified speaker (speaker_0) · 0:00

  2. 2
    the majority of companies They do not track the starting point of their margin.

    Unidentified speaker (speaker_0) · 1:46

Episode sections

  1. 0:00 – 1:26

    Introduction to Profit Fade

    The speaker introduces the concept that gross margin alone is insufficient for measuring job performance. He argues that two jobs with identical contract values and gross margins can have vastly different underlying stories regarding estimation accuracy and execution efficiency.

  2. 1:26 – 3:07

    The Importance of Estimated vs. Actual Margins

    The speaker explains that companies often fail to track the starting point of their margin. He illustrates how a job estimated at 40% but delivered at 35% represents profit erosion, whereas a job estimated at 30% and delivered at 35% represents a pickup, despite both showing 35% final margin.

  3. 3:07 – 4:47

    Establishing an Estimating Feedback Loop

    A critical system is described where variance data from job costing and project reviews is fed back into the estimating department. This ensures future bids incorporate lessons learned from past execution, preventing the repetition of estimation errors.

  4. 4:47 – 7:04

    Risks of Misleading Metrics and PM Assignment Bias

    The speaker recounts a story where a CEO nearly fired a Project Manager based on poor revenue-per-hour metrics. The speaker clarifies that top PMs are often assigned to the most difficult, misbid jobs, while mediocre PMs are placed on easy jobs, skewing performance data.

  5. 7:04 – 9:27

    Estimator Power and Lack of Visibility

    The speaker discusses the danger of estimators holding excessive power due to their business-generating role. He notes that without visibility into bid breakdowns, owners cannot detect if estimators are padding margins to hide operational execution failures.

  6. 9:27 – 10:27

    Practical Implementation for Legacy Jobs

    For companies with poor historical estimating systems, the speaker suggests using the Work in Progress (WIP) schedule at the time a job was put on the

Do your own research

  • Review the company's job costing system to determine if it tracks estimated vs. actual margins for each job.
  • Analyze the feedback loop process between project management and estimating departments to see if variance data is actually used to adjust future bids.
  • Audit project manager assignments to identify if high performers are consistently given difficult jobs and low performers are given easy ones.
  • Examine bid breakdowns for signs of margin padding by estimators, especially if operational execution has been poor.
  • Verify the accuracy of Work in Progress (WIP) schedules for legacy jobs to assess historical estimation errors.
  • Check if the company has a formal process for post-job reviews that feeds back into the estimating department.
  • Look for conflicts of interest where estimators have excessive power over project assignments or performance metrics.
  • Compare revenue-per-hour metrics against job complexity to ensure fair performance evaluation of project managers.
Full transcriptexpand

0:00Unidentified speaker (speaker_0): In construction, measuring job performance goes so much deeper than just tracking gross profit and gross margin. So today I'm going to walk you through what the best companies do when it comes to crushing the gross margin. Now, obviously, not every single job is the same. And in fact, no two jobs are alike. You know that you're in construction. Even if you have a site and you're building the same building and you're just replicating that and you're doing two of them, those jobs can go wildly different. In fact, when I was CFO, I remember one project, we were seriously building two of the same buildings on one site, and the margins were completely different, which is crazy for a variety of reasons. So we're not getting into the nuances of construction, operations, etc. What I'm referring to is let's say you're a leader, you look at your job profitability report, you see two jobs with the same contract value. and they have the same exact gross margin, and you're like, wow, both of these jobs are really good. And maybe you even have a target. Let's say your gross margin target is 32%. You're like, wow, we're above our gross margin target, all as well. And you high-five your team, you pay out some bonuses. But before you do that, I want to reframe your thinking here because those two jobs can have. completely different stories. And if you don't catch the story behind this, you're going to

1:19keep repeating the same mistakes. And one day it's going to catch up to you and lead to very bad things. Let me explain.

1:26Unidentified speaker (UNKNOWN): So

1:26Unidentified speaker (speaker_0): as a CFO, I spend a lot of time in project reviews. So we do project reviews on a every other week basis with our teams. We'd have our controller in the meeting along with the PMs, with the division leaders. et cetera. And we'd review these projects in detail down to the cost code. And we'd forecast out the estimated cost to complete. We look at hours, throughput, et cetera. So I spent a lot of time in my career going through projects on this type of level. Here's what I've realized: the majority of companies They do not track the starting point of their margin. And this is where your story begins. Let's go back to the example of two jobs, same contract value, 35% margin. What if one of those jobs was estimated at a 40% margin because you had some type of competitive advantage, or there is a barrier to entry, or perhaps you're on a tight time schedule, or maybe there is there's a windfall with materials that you're buying, whatever the case, you're able to market up higher than normal.

2:27But then you executed and you only delivered at a 35% margin. That means you had a 5% profit erosion on the job. That's not good. That's terrible. The opposite is true if you estimate a job at a 30% margin, and then you deliver or execute and end up with a 35% margin. There you have a 5% pickup.

2:50Unidentified speaker (UNKNOWN): So

2:50Unidentified speaker (speaker_0): as you can see, there's two different stories. In one situation, you're yelling at the team, and in another situation, you're praising the team. I'm just kidding, don't yell at your team. All joking aside, that's the pattern that I see over and over again in companies, but they don't have a system in place to track this.

3:07Unidentified speaker (UNKNOWN): So

3:07Unidentified speaker (speaker_0): the job that was bid at 40% and you arrive at 35%, you have to identify that so you could catch it in your feed. feedback loop, in your estimating feedback loop. Because think about it you estimate a job based on certain assumptions, production rates, costs, et cetera, materials, equipment, labor, subcontractors. You go out there, the job starts, you do job costing, then you do a project review, and then you figure out where the variances are from estimated versus actual. If you don't feed that in to a system where that information is feeding back to estimating. So the next time they spit out an estimate, it incorporates this new information, this intelligence. Then you're just going to be repeating the cycle over and over again. And I could tell you this because companies are becoming super savvy and they're moving really fast. If you don't have this feedback system in place, your competitors will. All right. Because they're going to put in place an estimating software. They're going to put in place an estimating feedback loop because they understand to be competitive, especially on razor-thin margins for a lot of scopes. If you don't have this, all it takes is one bad job and you're done.

4:19Unidentified speaker (UNKNOWN): So

4:19Unidentified speaker (speaker_0): they're realizing this and like, okay, we need to get smarter. We need to have more intelligence. We need to have more visibility in this whole entire process. So this is really, really critical. Now, going back to the margin pickup. So you bid at 30%, your team delivers at 35%,

4:37Unidentified speaker (UNKNOWN): you

4:37Unidentified speaker (speaker_0): should be celebrating that. That's what you should be rewarding. So

4:42Unidentified speaker (UNKNOWN): this

4:43Unidentified speaker (speaker_0): is where metrics and numbers could get companies into a lot of trouble.

4:47Unidentified speaker (UNKNOWN): So

4:48Unidentified speaker (speaker_0): when we go into a business, so if a business comes to us and they say, hey, Steve, we need your help. We need help with profit or cash flow. We do this all the

4:54Unidentified speaker (UNKNOWN): time.

4:55Unidentified speaker (speaker_0): We look at all their numbers. But if you don't understand construction, this is why so many clients like working with us, because we understand construction, the nuances of construction. But if you don't understand construction, you can make some serious mistakes with the data. Case in point.

5:10Unidentified speaker (UNKNOWN): I

5:11Unidentified speaker (speaker_0): remember when I was a CFO of this large company

5:13Unidentified speaker (UNKNOWN): and the

5:14Unidentified speaker (speaker_0): CEO was like, hey, I want to do an analysis on our PMs. So I did that and I looked at revenue per hour, gross profit per hour. I looked at it per day. I looked at a variety of metrics. And then I put it together in this nice report. And then I delivered it to the CEO. And I was like, hey, let's talk tomorrow about it. Well, before we had the meeting, he was like fired up. And I thought he was going to go out there and terminate all these PMs. He's like, oh my gosh, I knew it. I knew John was doing a terrible job. I'm just making up. It's not really you, John, that I'm talking about. But he's like, oh my gosh, John's doing a terrible job. Look at his numbers. I can't believe it. I thought he was good. He's going on this rampage. And I was like, okay, hold on, pause. Think about this. Where do we put our best PMs?

6:00Unidentified speaker (UNKNOWN): And

6:00Unidentified speaker (speaker_0): he kind of scratched his head for a minute. He's like, we put them on jobs. I'm like, no, what kind of jobs do we put them on? We put them on our worst jobs. We put our best PMs on our worst jobs because we either misbid them or it's tight or something happened and the job's going south. We put the PMs with the most experience, the ones that could turn around the job have had the biggest impact. We put them on the worst jobs.

6:25Unidentified speaker (UNKNOWN): Where

6:25Unidentified speaker (speaker_0): do we put our worst PMs or our mediocre PMs? We put them on our best jobs because they're it's smooth sailing. It's really easy to execute on these. And he's like, Oh, yeah, true. So I'm like caveat, caveat, caveat, asterisk, asterisk, all over my rapport. I should have included all these. But that's the thing when it comes to our jobs. You can't just look at your margin and say, yeah, we're doing great. We're earning a 35% margin. You can't even look at your TTM margin, your trailing 12-month margin, and say, yeah, it's going up. Unless you understand the starting point. This is where you have to have a tie back to estimating. Here's the problem, though, that most companies have to overcome, and this may be you. Sometimes estimators, they're running the asylum, right? So they have so much power because they're bringing in business, and owners get worried that estimators may leave. So we were working with a company a while back, and the owner was really struggling with this. He had two estimators, and they're bringing in the bulk of the work. And they had a lot of experience, and they had connections with builders and architects, and they're they just had this really good. network. So they brought in really good work, but there's no visibility into their numbers. And so

7:44they're using these models and they're putting out bids, and it was fine, but the owner had no clue what was going

7:50Unidentified speaker (UNKNOWN): on.

7:51Unidentified speaker (speaker_0): And over time, the estimators started engaging in bad behavior, and the owner would get frustrated and he he'd would come to me. He's and

7:57Unidentified speaker (UNKNOWN): like,

7:57Unidentified speaker (speaker_0): Oh my gosh, Steve, I don't know what to do. This person's doing this or doing this or breaking this rule. they're violating this. And he's like, they just have too much power. And I'm like, okay, yeah, that's the problem with the system. Right? You don't want anybody in your company to have too much power. I see this, the same thing happen with CFOs. You know, CFOs will put in an accounting system and they're the only ones who know how to run the system. And they have all these intricate spreadsheets and whatnot. And it's like, if you get rid of the CFO, talk about job security, like the whole thing. blows up. So the same thing is true going back to estimating. If you don't have visibility or if you can't go to your estimators and say, what did you bid this job at? And I need to break down how many hours, give me a materials breakdown, give me all the stuff, give me all the analytics, how much do you

8:42Unidentified speaker (UNKNOWN): have

8:42Unidentified speaker (speaker_0): in overhead recovery? How much do you have in profit?

8:45Unidentified speaker (UNKNOWN): How

8:45Unidentified speaker (speaker_0): much do you have in an overall margin?

8:48Unidentified speaker (UNKNOWN): And

8:48Unidentified speaker (speaker_0): then get that starting point and measure against that starting point. If you can't do that, you'll just be guessing.

8:53Unidentified speaker (UNKNOWN): You'll

8:53Unidentified speaker (speaker_0): just look at your margin, you're like, yeah, I think we're doing good. But what if they're adding more margin into their bids? But you have an operations problem. The operations team can't execute, and therefore you have margin erosion. That's a major problem. And you have to see

9:06Unidentified speaker (UNKNOWN): that.

9:07Unidentified speaker (speaker_0): Or perhaps your production rates are completely inaccurate. You have to have visibility into this. So that's why you have to measure the starting point. And it begins with estimated margins from your bids all the way to your actual margins at the end of the bid. Now, if you're not there, don't worry. A lot of companies don't have this in place, but you don't have to stay stuck here. You could put the system in place. We help companies do this all the time, and it's a game changer. So you could do this in your business today. And if you don't know, let's just say you go back to some jobs and you're like, I don't know what we bid it at. We had a bad estimating system. What you could do

9:44Unidentified speaker (UNKNOWN): is

9:44Unidentified speaker (speaker_0): you could go back to your whip schedule. This isn't always perfect, but you go to your work in progress schedule, go back to when that job went on to the whip, and you could look at what was the cost budget at the time. Now, if your cost budget was just made up, it's not gonna going to help you. But if your cost budget is true, then you can have your starting point. of margin based on the first time it went on the whip, then track it month by month until the job closes out. And then you can see the difference between the two until you get this system more refined. But I would highly encourage you to put this in place right now in your business as a specialty contractor, as a GC, whatever your scope is in construction, it'll make all the difference in to the world. All right. I'll catch you in the next episode. Cheers.