Property Developer Podcast

Anthony Awkar discusses hidden costs of being both builder and developer, emphasizing cash flow and risk mitigation

1h 8m Listen to the original Episode page
Property DevelopmentConstruction CostsRisk ManagementCash FlowLand BankingVolume BuildingSupply Chain

Summary

Anthony Awkar explains his transition from high-end renovations to volume development, targeting a $280,000 build cost per townhouse by using Chinese materials and subcontracting 90% of work. He highlights the financial risks of acting as both builder and developer, noting that builder's margins are often absorbed into overheads, leaving the developer exposed to cost overruns and market drops. Awkar advises rigorous due diligence, including consulting multiple real estate agents and modeling worst-case scenarios with a 22% profit margin requirement. The discussion also covers land banking strategies during market downturns, with speakers citing examples of significant value appreciation for those who acquired land early.

Episode sections

  1. 0:00 – 3:53

    Intro and Sponsor Read

    Host Justin Getty introduces the episode and shares updates on his own development project, including funding applications and civil works. He promotes his property developer training and mentoring programs.

  2. 3:53 – 6:51

    Guest Background and Restaurant Bankruptcy

    Anthony Awkar discusses his Lebanese background and his experience taking over a struggling family restaurant at age 21, which led to bankruptcy at age 23. He explains how this experience taught him the importance of cash flow management and verifying advice.

  3. 6:51 – 16:37

    Building Company Model and Staffing

    Awkar describes his transition from property management to building, highlighting his company's model of employing 10 full-time builders for high-end architectural renovations rather than using a traditional subcontractor model.

  4. 16:37 – 20:45

    Shift to Volume Development and Four-Townhouse Project

    Awkar explains a strategic shift towards volume work to generate capital, detailing a four-townhouse project on a 726 square meter block. He targets a build cost of $280,000 per home, excluding GST, for 140 square meter dwellings.

  5. 20:45 – 27:37

    Supply Chain and Cost Management

    Awkar discusses the use of materials from China to keep costs down, arguing that Australian suppliers pass through Chinese raw materials with added markups. He emphasizes quality control and the necessity of this approach to deliver affordable housing.

  6. 27:37 – 30:17

    Risk Mitigation and Subcontracting Strategy

    Awkar contrasts his high-end renovation work with the new volume project, noting that he will subcontract 90% of the construction work to manage costs and risks effectively, leveraging his role as both builder and developer.

  7. 30:17 – 32:46

    Feasibility and Due Diligence

    Anthony Awkar explains his rigorous due diligence process, which includes using a custom feasibility calculator, consulting real estate agents for valuation, and modeling worst-case scenarios for holding costs and construction timelines.

  8. 32:46 – 37:03

    Risks of the Builder-Developer Model

    The speakers discuss the hidden costs of being both builder and developer, noting that the builder's margin is often absorbed into overheads during the construction phase, leaving the developer to bear the risk of cost overruns and market price drops.

  9. 37:03 – 45:50

    Market Conditions and Interest Rates

    Awkar attributes current industry struggles to high interest rates (referencing a 4.85% cash rate) and rising operational costs, which have squeezed margins and made it difficult for builders to win work without sacrificing profitability.

  10. 45:50 – 1:00:37

    Contractual Risks and Variations

    The discussion highlights the dangers of variations in building contracts, advising developers to lock in all selections early to avoid PC sums and unexpected costs, while noting that builders face significant financial risk if clients default on final payments.

  11. 1:00:37 – 1:02:07

    Resilience and Planning in Construction

    Speaker_0 discusses the mental toll of construction, noting that while there is always a way through, the work is grueling. He emphasizes the need for a plan and the ability to re-plan when unexpected challenges arise, likening the industry to a situation where one gets 'punched in the face' frequently.

  12. 1:02:07 – 1:03:38

    Land Banking Strategy During Market Downturns

    Speaker_0 advises developers with capital to avoid active development and instead engage in 'land banking' due to panic selling and falling prices. He cites examples of properties selling significantly below asking price and suggests holding these assets for two years to capture market recovery.

  13. 1:03:38 – 1:04:18

    Case Study of Pre-COVID Land Acquisition

    Justin Getty shares a personal anecdote about buying a development site in 2013 at the bottom of a cycle. He notes that while they didn't capture the full upside due to pre-selling, the Gross Rental Value (GRV) increased by $2 million during construction, illustrating the benefit of securing land early.

  14. 1:04:18 – 1:08:11

    COVID-Era Development Profitability

    Speaker_0 describes a client who bought land just before COVID, initially fearing bankruptcy as prices were expected to drop. Instead, the client made approximately $1 million per block over two years as property values rose from $600,000 to $900,000-$1,000,000, highlighting the power of holding land through market shifts.

Claims worth verifying

Awkar went bankrupt at age 23 after taking over a struggling family restaurant at age 21.

Unidentified speaker (speaker_0) ·5:59

How to verify: Public records search for Anthony Awkar's personal bankruptcy history in Australia or biographical verification via Ora Projects/Aura Projects website or LinkedIn profile. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Awkar owed $180,000 to the ATO in estimated BAS statements after two years of not lodging them.

Unidentified speaker (speaker_0) ·10:45

How to verify: Verification requires access to private tax records or confirmation from Awkar via direct inquiry or published case study. Cannot be independently verified without consent. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Primary source

Awkar's building company employs 10 full-time builders.

Unidentified speaker (speaker_0) ·8:13

How to verify: Check company registration documents, LinkedIn employee count for Ora Projects/Aura Projects, or job postings listing staff size. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

The four-townhouse project is on a 726 square meter block.

Unidentified speaker (speaker_0) ·17:33

How to verify: Search land title records or planning permits for the specific development in Adelaide matching the description. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Awkar utilizes materials from China for the project.

Justin Getty ·21:09

How to verify: Check supply chain invoices or procurement records if disclosed. Verify typical import sources for construction materials in Australia. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Awkar's company ran on cash flow for the first three years without significant debt.

Unidentified speaker (speaker_0) ·15:17

How to verify: Review company financial statements or interview with Awkar regarding historical funding structures. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Awkar plans to subcontract 90% of the four-townhouse project.

Unidentified speaker (speaker_0) ·28:46

How to verify: Check subcontractor agreements or project management plans if publicly disclosed. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Anthony Awkar is an Adelaide builder and developer from Ora Projects.

Unidentified speaker (UNKNOWN) ·30:17

How to verify: Company website or LinkedIn profile for Ora Projects and Anthony Awkar. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Awkar consulted eight real estate agents before making an offer on a specific development block.

Unidentified speaker (speaker_0) ·31:14

How to verify: Cross-reference with Awkar's public case studies or Ora Projects' development records if available. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Awkar's feasibility model uses a 14-month timeline for amortized interest calculations.

Unidentified speaker (speaker_0) ·31:34

How to verify: Review Ora Projects' public feasibility templates or case studies detailing their financial modeling assumptions. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Awkar requires a minimum 22% profit margin in his feasibility calculator to proceed with a project.

Unidentified speaker (speaker_0) ·32:29

How to verify: Verify against Ora Projects' public investment criteria or case studies. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

The Australian cash rate was 4.85% at the time of the recording.

Justin Getty ·37:41

How to verify: Reserve Bank of Australia (RBA) monetary policy decisions and cash rate history for November 2026. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Construction finance rates are ranging from 7% to 9%.

Unidentified speaker (UNKNOWN) ·37:44

How to verify: Survey major Australian banks (e.g., CBA, Westpac, NAB, ANZ) for current construction loan interest rates. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Awkar's 'whips' (works in progress) were $420,000 at the end of the last financial year.

Justin Getty ·55:43

How to verify: Ora Projects' financial statements or accounts if publicly filed; otherwise, verify via company press releases. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Awkar has fought with banks for six years to increase the number of progress claims from five to ten.

Unidentified speaker (speaker_0) ·56:05

How to verify: Ora Projects' case studies or client testimonials regarding their contract structures and financing negotiations. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

The building industry market is close to 60% down.

Unidentified speaker (UNKNOWN) ·39:23

How to verify: ABS (Australian Bureau of Statistics) building approval data or Master Builders Australia industry reports for the relevant period. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Awkar lost six jobs in the last six months where his pricing did not go through.

Unidentified speaker (speaker_0) ·45:06

How to verify: Ora Projects' internal sales records or public statements regarding lost tenders. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Speaker_0 advises developers to land bank because people are panic selling and the market is going down, predicting it will continue dropping for the next six months.

Unidentified speaker (speaker_0) ·1:02:41

How to verify: Check local real estate sales data and median price trends in Adelaide for the 6 months following the podcast release (Nov 2026) to see if prices continued to drop and if panic selling occurred. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Speaker_0 cites seeing properties advertised at $3 million selling for $2 million, and auction properties advertised at $2.4 million selling for $1.7 million.

Unidentified speaker (speaker_0) ·1:03:01

How to verify: Search public auction records and real estate listing archives in Adelaide for the period around Nov 2026 to find specific transactions matching these price points and discounts. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Justin Getty bought his first development site in 2013 at the bottom of the cycle.

Unidentified speaker (UNKNOWN) ·1:03:38

How to verify: Check Justin Getty's public professional biography or LinkedIn profile for mentions of his first development purchase date and location. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Justin Getty's 2013 development site saw a $2 million uplift in GRV during construction.

Unidentified speaker (UNKNOWN) ·1:04:11

How to verify: This is a specific financial figure tied to a private transaction; verification would require access to Justin Getty's financial disclosures or public reports on that specific project's financials if published. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

A client bought land just before COVID and made $1 million per block over two years.

Unidentified speaker (speaker_0) ·1:04:40

How to verify: Identify the specific client mentioned (if named elsewhere in the full episode) and check their development project's financial outcomes or public sales data for properties built between 2026-2026. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Primary source

Speaker_0 states property values rose from $600,000 to $900,000-$1,000,000 for the client's project during the COVID period.

Unidentified speaker (speaker_0) ·1:04:54

How to verify: Compare median sale prices for similar residential properties in the relevant Adelaide suburb between early 2026 and late 2026 using CoreLogic or REIV data. For recent events, verify 2026-08-16 through 2026-11-16. Use another period only when the speaker explicitly names it.

Do your own research

  • Verify the current cash rate and construction finance rates (7-9%) against current RBA data and major bank lending terms.
  • Check the specific zoning classification ('deemed to satisfy') and any potential RFIs (e.g., tree protection) for the 726 sqm block in question via local council planning portals.
  • Review the ATO's stance on BAS statements and GST obligations for small business owners to understand the tax risks mentioned.
  • Compare the $280,000 build cost per townhouse against current industry averages for 140 sqm dwellings in the target area, including GST and contingencies.
  • Investigate the supply chain claims regarding Chinese materials and Australian supplier markups by obtaining quotes from multiple local suppliers.
  • Assess the 22% profit margin requirement against historical market volatility, specifically how a 3% price drop impacts profitability on $850,000 exit prices.
  • Verify the land banking examples cited (e.g., 2013 purchase, pre-COVID acquisition) against public sales records and median price trends in the relevant suburbs.
Full transcriptexpand
0:00
Unidentified speaker (speaker_0): Going bankrupt, reset me. I hit rock bottom about a year after that, and then obviously built back up.
0:08
Unidentified speaker (UNKNOWN): You
0:08
Unidentified speaker (speaker_1): are listening to the Property Developer Podcast, your home for tips, ideas, and inspiration to help take your developing to the next level. Now here's your host, Justin Getty.
0:21
Unidentified speaker (UNKNOWN): Hello
0:21
Justin Getty: and welcome to episode 120 of the Property Developer Podcast. I'm your host, Justin Getty. Keddy. How are you going?
0:29
Unidentified speaker (UNKNOWN): I
0:29
Justin Getty: hope you're keeping well and making some great progress with whatever you're working on. Got a terrific show coming up for you again today. Speaking with a builder about the challenges of the construction trade. Before that, here's a quick update on my current project. We're continuing to work through our funding application and just have
0:49
Justin Getty: the a valuation report done.
0:51
Unidentified speaker (UNKNOWN): At
0:51
Justin Getty: the same time, we're finalizing the arrangements for the civil works so that we're ready to get started once the funding is in place.
0:59
Unidentified speaker (UNKNOWN): I'm
0:59
Justin Getty: looking forward to unlocking the funding piece and getting on with the actual building works. Before we get into today's episode, I wanted to share a couple of things for anyone thinking about doing their first development or looking at their next project.
1:15
Unidentified speaker (UNKNOWN): I
1:15
Justin Getty: bought my first development site in 2013 at the bottom of a market cycle.
1:20
Unidentified speaker (UNKNOWN): There
1:20
Justin Getty: wasn't much competition, and I was able to negotiate a good price and a long settlement.
1:26
Unidentified speaker (UNKNOWN): The
1:26
Justin Getty: thing that made the difference was being ready to act when the opportunity came up.
1:32
Unidentified speaker (UNKNOWN): Now, if
1:32
Justin Getty: you're wondering how ready you are to become a developer, take my free property developer quiz at property propertydeveloper developer. training.com forward slash quiz.
1:41
Unidentified speaker (UNKNOWN): And
1:42
Justin Getty: if you want to learn the development process from beginning to end, my online property developer training covers what you need to start and finish your first small scale project.
1:53
Unidentified speaker (UNKNOWN): You
1:53
Justin Getty: can find it at www.propertydevelopertraining.com.
1:58
Unidentified speaker (UNKNOWN): If
1:58
Justin Getty: you'd prefer one-on-one support, I also run my next stage. private mentoring program. We can work through an opportunity you're assessing, a challenge you might be facing on a current project, or whatever you're planning next. Head to propertydevelopertraining.com forward slash mentoring and tell me what
2:18
Justin Getty: you're working towards. Whatever stage you're at, the work you do now can make all the difference when the right opportunity comes up.
2:27
Unidentified speaker (UNKNOWN): So,
2:28
Justin Getty: what are you doing today to make sure you're ready to act when it comes along? Or will you let it pass you by?
2:35
Unidentified speaker (UNKNOWN): The
2:35
Justin Getty: ladder to the next level is waiting for you to climb up it when you are ready.
2:41
Unidentified speaker (UNKNOWN): Okay,
2:42
Justin Getty: on to today's episode. My guest is Next Anthony Orker, Auker, an Adelaide builder and developer from Aura Projects.
2:51
Unidentified speaker (UNKNOWN): I've
2:51
Justin Getty: been following Anthony on Instagram where he's sharing the numbers on a 4 townhouse project that he's doing. He's targeting a build cost of $280,000 per townhouse.
3:03
Unidentified speaker (UNKNOWN): And
3:03
Justin Getty: we get into what that figure covers and what sits outside
3:07
Unidentified speaker (UNKNOWN): it. I
3:08
Justin Getty: was particularly keen to ask Anthony what people don't appreciate about being both the builder and the developer.
3:16
Unidentified speaker (UNKNOWN): From
3:16
Justin Getty: the outside, you might think you get two margins.
3:20
Unidentified speaker (UNKNOWN): In
3:20
Justin Getty: Anthony's case, his building business is putting months into the job without charging a builder's margin, and the payoff depends on how the development turns
3:29
Unidentified speaker (UNKNOWN): out. We
3:30
Justin Getty: also talk about what going bankrupt at 23 taught him about cash flow and what developers can sort out before asking for a build price. to avoid surprises down the track.
3:42
Unidentified speaker (UNKNOWN): So
3:43
Justin Getty: let's get straight to Anthony and find out what his favorite food is. And as it turns out, that's how we got on to the story of how he became a builder.
3:53
Unidentified speaker (speaker_0): It's uh food that no one's gonna know because it's a food from I'm my background's Lebanese.
3:59
Unidentified speaker (UNKNOWN): Um
4:00
Unidentified speaker (speaker_0): in Arabic, it's Wara'anib, but in uh English it translates to vine leaves, so they're they're wrapped vine leaves with uh rice and meat.
4:10
Unidentified speaker (UNKNOWN): I
4:10
Unidentified speaker (speaker_0): would eat that to the day I die.
4:12
Justin Getty: Uh yes. My grandmother used to make these amazing cabbage rolls.
4:16
Unidentified speaker (speaker_0): Yeah.
4:17
Justin Getty: Similar kind of
4:18
Unidentified speaker (UNKNOWN): very
4:18
Unidentified speaker (speaker_0): similar.
4:18
Justin Getty: Yeah.
4:19
Unidentified speaker (speaker_0): If they are they meat?
4:20
Unidentified speaker (UNKNOWN): Yeah,
4:20
Justin Getty: meat and meat.
4:21
Unidentified speaker (speaker_0): rice?
4:22
Justin Getty: Yep. And tomatoes. Yeah, she it was amazing.
4:26
Unidentified speaker (speaker_0): Yeah.
4:27
Justin Getty: Always tastes better the next day.
4:29
Unidentified speaker (UNKNOWN): A
4:29
Unidentified speaker (speaker_0): hundred percent. A hundred percent.
4:32
Unidentified speaker (UNKNOWN): What
4:32
Unidentified speaker (speaker_0): about you? What would you eat until you die?
4:35
Justin Getty: Uh pizza.
4:36
Unidentified speaker (speaker_0): Pizza?
4:37
Justin Getty: Yeah.
4:37
Unidentified speaker (speaker_0): Yeah.
4:38
Justin Getty: Yeah. And I've eaten it many times till I felt I was sick. Still haven't learned my lesson.
4:45
Unidentified speaker (speaker_0): Yep. Yep. Yep. Yep. It gets like that. It's one of those ones that's hard to stop.
4:48
Justin Getty: Actually this year I'm on a mission to uh perfect making my own pizza, so I got a pizza oven at the start of the year and I've been spending this year working on making dough and getting awesome pizzas, which has been fun.
5:02
Unidentified speaker (speaker_0): We had a Italian restaurant up until I was twenty one.
5:06
Justin Getty: Oh did you?
5:08
Justin Getty: Oh well wouldn't when I uh switch off the recording I might have to ask you for your secret tips about the
5:14
Unidentified speaker (speaker_0): dough
5:14
Unidentified speaker (UNKNOWN): recipe.
5:14
Justin Getty: recipes. Yeah. Yeah,
5:17
Unidentified speaker (speaker_0): yeah. Yeah, I know a bit about dough.
5:20
Justin Getty: All right. Well, um I could talk to you about pizza and dough for a a while, but we're here today to talk about property developing. So can you give us a bit of a background about yourself and how you got into building?
5:34
Unidentified speaker (speaker_0): Uh funny enough, it actually segues from the pizza.
5:40
Unidentified speaker (speaker_0): So family restaurant up until we were 21. I took it over at 21. Uh it was struggling when I took it over, and it was struggling beyond repair. But I thought that, like any young, dumb 21-year-old thinks, they can save and fix everything. And um
5:58
Unidentified speaker (UNKNOWN): by
5:59
Unidentified speaker (speaker_0): 23, I was bankrupt. So liquid. liquidated, went into administration on that business, um,
6:08
Unidentified speaker (speaker_0): bounced around for about a year and a half, worked with my brother in uh property um property maintenance uh property management. Sorry, worked with my brother in property management, realized I hated working in an office, which is funny. Um, started going and worked with my brother-in-law. brother in law. He was a general builder,
6:28
Unidentified speaker (speaker_0): did small maintenance work when I started with him. So we did everything. We f did zip rock, we framed, we concreted, we did small bits of tiling, flushing, painting, literally everything that you see is a basically DIY renovation, but we did it in-house because it was a small operation. As we started to get bigger, that obviously started to get
6:48
Unidentified speaker (speaker_0): bigger. I fell in love with building.
6:51
Unidentified speaker (speaker_0): straight away. Started doing my diploma in building construction management. Got that, worked with him for close to six years. When I got my builder's license, I went out and I actually started in demo. I would do strip-outs for other builders. So go do their bathrooms, their kitchens, strip them out, prep,
7:11
Unidentified speaker (speaker_0): floor, do all of that stuff while I was still working with my brother. brother-in-law, then my brother opened a pizza shop. Um and I started going into my own small renovations at that time, but it wasn't enough to really keep us afloat. So I was still working with my brother in law a couple of days a week, and then I would do my own
7:31
Unidentified speaker (speaker_0): jobs a couple of days a week, and at night I would go to the pizza shop. And then by 2021.
7:39
Unidentified speaker (speaker_0): we had stopped working with my brother-in-law. We had enough work on for ourselves: small rentos, kitchens, bathrooms, refits, stuff like that. We landed our first big job in the middle of 2021. I was still working at the pizza shop at nights, then. And then by a couple of months on that job, I had to stop. And then from there we just
7:59
Unidentified speaker (speaker_0): kind of took off. We always had planned to work in the high-end architectural market, extensions, renovations. And we wanted to stay clear of new builds.
8:13
Unidentified speaker (speaker_0): Just because there are a lot of rinse and repeat stuff, like for our for our work, because we run a bit of a different model in our building company. So we've got 10 ten full-time builders that work for us on the board, book, or well that work for me on the board. books, full-time employees. So
8:30
Unidentified speaker (speaker_0): our
8:31
Unidentified speaker (speaker_0): model is different to your traditional subcontractor model.
8:35
Unidentified speaker (UNKNOWN): A
8:35
Unidentified speaker (speaker_0): lot of our labors in-house, we excavate, we form, we do small bits of steel fixing, small bits of slab work, we obviously frame, we clad, we roof, we insulate, we jip rock,
8:46
Unidentified speaker (UNKNOWN): um,
8:46
Unidentified speaker (speaker_0): we with second fix, obviously, and yeah. Uh
8:51
Unidentified speaker (UNKNOWN): that's sounds like the old
8:52
Justin Getty: the old school builders model.
8:55
Unidentified speaker (speaker_0): It is which can be your best friend or your worst enemy when things are good, it's your best friend. When things aren't going well, it is your worst enemy because it strips you quicker than you can blink.
9:11
Unidentified speaker (UNKNOWN): Yeah,
9:12
Justin Getty: where you got all the massive uh overheads that you have. that are fixed, you got to keep paying them.
9:17
Unidentified speaker (speaker_0): Yep.
9:19
Justin Getty: And then
9:21
Unidentified speaker (UNKNOWN): I'm
9:21
Justin Getty: keen to hear about your experience with
9:26
Justin Getty: going insolvent or being bankrupted. What lessons did you learn from that just in terms of
9:33
Unidentified speaker (UNKNOWN): going
9:33
Justin Getty: through a bankruptcy or an insolvency? What did you learn
9:37
Unidentified speaker (UNKNOWN): about yourself? And then
9:38
Justin Getty: what were the lessons? that you've taken forward with
9:40
Unidentified speaker (UNKNOWN): you?
9:42
Unidentified speaker (UNKNOWN): A
9:42
Unidentified speaker (speaker_0): couple of things. Obviously, being young was probably the best time to do it. You didn't h really have anything to lose, no family, no assets. Um it was a reset. Um
9:55
Unidentified speaker (UNKNOWN): I
9:55
Unidentified speaker (speaker_0): wasn't in the best state of mind uh at that time. a Bunch of other different reasons. And going bankrupt reset me. I hit rock bottom about a year after that, and then obviously built back up.
10:11
Unidentified speaker (UNKNOWN): Um
10:12
Unidentified speaker (speaker_0): it was the reason we went bankrupt, like I said, it was already a failing business. So it was already basically going through liquidation, and we thought, well, I thought I could bring it out, and I took some advice that I probably should have verified and listened to some other people, but I didn't know back then what I didn't know. So we weren't paying
10:31
Unidentified speaker (speaker_0): GST, we weren't paying our BAS statements, we weren't even lodging them, which again I I can't blame anyone other than myself. I should have done my research, but at twenty one years old, you only know so much.
10:45
Unidentified speaker (speaker_0): So after two years of training trading, we actually got a knock on the door from the ATO. and they said you owe they had estimated the BAS and they had estimated all of the figures and said you owe $180,000.
11:01
Unidentified speaker (speaker_0): Uh at that point there I went to my grandfather who was a very successful businessman. Said, What do I do here? Uh he said,
11:10
Unidentified speaker (UNKNOWN): Can
11:10
Unidentified speaker (speaker_0): you pay it?
11:11
Unidentified speaker (UNKNOWN): I said
11:12
Unidentified speaker (speaker_0): no. He said, Can you pay it over a year?
11:14
Unidentified speaker (UNKNOWN): I
11:14
Unidentified speaker (speaker_0): said no. there's absolutely no way. He said, Well, I'll put you in contact with back then it was actually Dr. Sir Campbell Rankin. He was one of the best tax accountant lawyers in the country. He looked at it and said, Look, you you can't pay this. You're gonna be, you know, they're gonna want basically
11:34
Unidentified speaker (speaker_0): your left arm, your right toes, and and everything that goes with it. And you know, 200 grand
11:41
Unidentified speaker (speaker_0): twelve years ago, fifteen years ago, you're talking the equivalent of what's probably four hundred thousand now. They would have wanted about thirty-five grand a month. That was our whole turnover. Oh no, that wasn't our whole turnover, sorry, but you know, that was sixty percent of our turnover at that point. It just wasn't possible. So he said, look, go bankrupt,
12:01
Unidentified speaker (speaker_0): reset, clear your debt. debts, pay off whatever creditors you can, and start fresh, start a new life. So that's what we did. I learned a couple of things from that. One, be diligent on your numbers. Be diligent with your taxes. Even if you fall behind on your taxes, talk to the tax man early. Don't let them come for you. Because
12:21
Unidentified speaker (speaker_0): look, like any business, especially now, it's getting harder and harder. You know, not everyone keeps up to date. with their their um tax requirements, but you can put it on a payment plan, on a reasonable payment plan, and move forward and just make sure that you're doing your due diligence in that. The second thing is don't let everyone else advise you, do your own research.
12:41
Unidentified speaker (speaker_0): If you don't know what you're doing, do not do it. Like if you're not you don't have to be an expert in everything, but even if you're getting expert advice, verify that advice. Make sure it is the best advice for you, for your situation. Like speak to two, three, four people that have done it, that have been through it, and that are better at it than you
13:01
Unidentified speaker (speaker_0): are, because one person will tell you advice A, pathway A, doesn't necessarily mean that they're right. There's pathway B, C, and D, and they can all interlink with each other and actually give you a better solution. or outcome than just following the one.
13:18
Unidentified speaker (speaker_0): And the main thing that I really took out of that, to be honest with you, is that no matter your situation, you can always bounce back. Um, whatever you're going through at the time, there is a way out, there is a solution. Um, and that it's not as bad as you think. Like, you know, that was five years of my life made it
13:38
Unidentified speaker (speaker_0): difficult. made it difficult coming out of it, but you know, we were able to rebuild out of the back of
13:43
Unidentified speaker (UNKNOWN): that.
13:45
Justin Getty: And so what have you what lessons have you taken into the building company?
13:49
Unidentified speaker (speaker_0): To be diligent, we track our numbers, we see when there's a gap coming in cash flow, we see when there's a gap coming in capital when we need to deploy, whether that means taking small business funding to get us through a tight period, whether it means potentially talking to clients to move invoices forward if need be, or um, you know, if we have
14:09
Unidentified speaker (speaker_0): to move a job forward to be able to, you know, hit a billing cycle on or whatever that may be, it's just making sure we're diligent with tracking our numbers. Like we cash flow flow for we cash flow forecast quite diligently.
14:24
Unidentified speaker (speaker_0): So we see what we're where you know. what our position is for two weeks, for four weeks, for six weeks, then you know, two, three, four, five months moving forward. And obviously they're forecast, things have to go right for them, but we do model different scenarios at best worst case scenario, and somewhere in the middle,
14:44
Unidentified speaker (speaker_0): just so that we've got a clear position and honestly utilizing utilising debt and leveraging some debt, small business funding. that's what it's there for, especially in construction. Like I talk about this, if we had a million bucks sitting in the bank just to play with, we wouldn't be doing client work. If we had the money sitting there to run a
15:04
Unidentified speaker (speaker_0): job in totality, we wouldn't be doing client work, we'd be doing it ourselves. So a lot of guys get stressed and they're like, Oh, you know, we're tight, we're cash more tight here. We run ran our business on cash. for the first three years.
15:17
Unidentified speaker (speaker_0): Right? And then as we started to grow, we started to have to use line of credit facilities and and other sources of um you know debt leverage for a business. But as long as we maintain them and we're on top of that, then we're okay.
15:34
Unidentified speaker (UNKNOWN): All
15:34
Justin Getty: right. So back to the building you were explaining uh explaining the company. So you got 10 staff.
15:43
Justin Getty: Mainly high-end Renault's, but you've done some full new builds, haven't you?
15:47
Unidentified speaker (speaker_0): Ten full-time staff. Um
15:50
Unidentified speaker (speaker_0): 10 full-time staff. We mainly do architectural led extensions, large extensions, and yes, we we're doing a new build now. Um and then uh we we do try and stick clear of them though, because uh well
16:08
Unidentified speaker (UNKNOWN): the
16:09
Unidentified speaker (speaker_0): the high-end architectural new builds, there's we're in Adelaide, there aren't a whole bunch of them that go on, and it's kind of cornered. The market for that is cornered by a few of the larger names that have been in the industry quite a long
16:22
Unidentified speaker (UNKNOWN): time.
16:23
Unidentified speaker (UNKNOWN): Um
16:24
Unidentified speaker (speaker_0): but quite frankly, to be honest with you, the way the market market's going now,
16:28
Unidentified speaker (speaker_0): that niche that we're in is suffering quite a
16:31
Unidentified speaker (UNKNOWN): bit.
16:33
Justin Getty: So where where are you looking to next?
16:37
Unidentified speaker (speaker_0): Um we've made a shift into some oh
16:42
Unidentified speaker (speaker_0): we've made a shift into just um
16:46
Unidentified speaker (speaker_0): other volume work. So uh well we work for in the insurance sector basically, keeps the numbers turning, it's consistent and it's um consistent work while we weather the storm, which everyone's gonna be weathering the storm.
17:02
Unidentified speaker (UNKNOWN): Yeah,
17:02
Justin Getty: and I think on some of your socials you have started on a four unit project that you're sharing with your audience. Can you tell us
17:11
Unidentified speaker (UNKNOWN): a bit
17:11
Justin Getty: about that?
17:12
Unidentified speaker (speaker_0): Yeah, so that's uh a block that we bought there. It's in a high density neighborhood or high housing diversity. It depends which way you look at it, but neighborhood zone. It's actually quite a small block, but it's subdividable into four. So it's a seven hundred and twenty six square meter block, subdividable into four. Um
17:33
Unidentified speaker (speaker_0): I don't I don't agree with the the lot sizes, but we've got a housing crisis. We have to build homes where twenty thousand plus homes a year out from what we need to hit. So the real only way to do that is build up or or reduce block sizes. Um that's like I said it's
17:53
Unidentified speaker (speaker_0): gonna be a one into four. They're all street facing, they're townhouses, and we aim on building them for 280,000 two hundred and eighty thousand X XGST, GST. 140 square meter. They're nothing special. They're going to be decent builds. Like they're not, we're not going to cut corners with them and do what your volume builders do. But because we're
18:13
Unidentified speaker (speaker_0): building in that volume and because they're basically rinse and repeat, you're able to utilize some better rates.
18:22
Unidentified speaker (UNKNOWN): And
18:22
Justin Getty: it sounds like it's a bit of a shift for you, though, you're going from this high-end architectural. renovation to suddenly a four-unit project.
18:31
Unidentified speaker (speaker_0): Yeah, look, our
18:33
Unidentified speaker (speaker_0): our goal was always to build for ourselves, right? And
18:39
Unidentified speaker (speaker_0): the way to do that is you do a few of these and you build up enough capital so you can buy, call it your blue chip suburb one into two higher end development. You can't start with that. To start with that, you're talking four, five, six million dollars in outlay, whether it be through development financing or whether it be through
18:58
Unidentified speaker (speaker_0): you having the capital, but even on development financing, which you would understand this better than anyone, you're still tipping in about twenty seven percent for land acquisition, subdivision fees, um, your water augmentation, your electrical, your demo, your pegging, your, you know, getting your uh deposited land titles and everything done.
19:19
Unidentified speaker (speaker_0): So on a four or five million dollar project, you're still having to tip in a million plus.
19:26
Unidentified speaker (speaker_0): But that's that is the end goal. The end goal is getting to that uh one into two higher in subdivisions, but you've got to start somewhere. So we're starting there, and hopefully we roll this over a few times.
19:39
Unidentified speaker (speaker_0): and you know that becomes our bread and butter and that becomes our our main source of income and wealth generation. And then the building company sits on the side.
19:52
Justin Getty: Two eighty XGST for hundred and forty square meters. Sounds a bit t tight, but I guess you've got to, you know, the builder's rates. to help you with.
20:04
Unidentified speaker (speaker_0): Where we're able to utilize that, because a lot of people do say it's tight. Look, if you look at a volume builder when they're putting their margin into the job and they're putting in their risk assessment and their contingency and all the rest of that, they're building at 2600 a square, right? Um obviously where this
20:23
Unidentified speaker (speaker_0): estimation comes into,
20:26
Unidentified speaker (UNKNOWN): we
20:26
Unidentified speaker (speaker_0): are the builders builder. We're not taking margin, we're not taking a wage on this. That's when that 280,000 X GST, it doesn't include contingency, it doesn't include land division, it doesn't include the demolition, it doesn't include any of that. Those costs are outside of that. This is pure build cost. And when we're
20:45
Unidentified speaker (speaker_0): talking four homes, they're all the same homes. So when we are actually getting these priced up, you're obviously getting volume rates for it, you're getting volume material rates. And to be honest with you, we will utilize some material from China. And I know that's a dirty word at the moment,
21:05
Unidentified speaker (speaker_0): but the fact of the matter is is
21:09
Justin Getty: it Is a dirty word? I'm not sure.
21:11
Unidentified speaker (speaker_0): Well, a lot of people get their back backup. up, like they say, you know, you you're taking away from the Australian market, you're taking away from the Australian suppliers. The fact of the matter is
21:22
Unidentified speaker (speaker_0): building construction costs here have gone through the roof. The cost of doing business here has gone through the roof. And if you want to build affordable homes, you have to be smart about it. And in the end of the day, Australian suppliers are getting their raw material from China, anyways. So they're getting their raw material from China. they're putting their markup on it, and then we're paying Australian
21:42
Unidentified speaker (speaker_0): fabrication rates. Now I understand, yes, you're taking some out of the market from there, but if you want to build an affordable product, and in the end of the day, that one into four is in an affordable area. If we were to use all Australian suppliers for that and top end materials, we're going gonna to lose money on the project. It's not feasible. No one will buy it.
22:02
Unidentified speaker (speaker_0): Like we're talking about an eight to eight fifty exit price there, right, per dwelling. If we were to not utilize what we have at hand, which is, like I said, some important supplies and volume rates, we're talking million dollar sale prices. We'd be breaking suburb records for that type of house there. It's just not gonna going to
22:22
Unidentified speaker (speaker_0): happen.
22:24
Unidentified speaker (speaker_0): And if it's you manage managed. there's someone that said, something to me a while back. They said the problem isn't the Chinese supply, it's when it gets installed. So obviously, we will go to China, we will verify the materials that we're getting used that are getting used, the factories that they're being made in, and all of that. We'll make
22:44
Unidentified speaker (speaker_0): sure we still go over there and we quality control the procurement. It's when it gets here and it gets installed. Is it being installed to Australian standards? Has it had those checks done? If so, then I don't see what the problem is. But a lot of people like to scream and shout, you're killing the Australian market, and I think the Australian market in regards to that is already
23:04
Unidentified speaker (speaker_0): dead.
23:05
Justin Getty: Yeah, well, I've looked at uh prefab modular product from China and the price the onshore pricing in terms of being from China is pretty good. Like
23:18
Unidentified speaker (speaker_0): spend
23:19
Justin Getty: eighty to a hundred Aussie dollars to get a you know eighty to a hundred square meter dwelling.
23:26
Unidentified speaker (speaker_0): Yeah.
23:27
Unidentified speaker (UNKNOWN): But
23:27
Justin Getty: by the time you land it in Australia, pay all your landing fees, get it shipped to site, get it installed. I mean you're up over 200k already. So the savings sort of get dwindled pretty quickly.
23:40
Unidentified speaker (speaker_0): I think in the prefab, well, yeah, it's too large a thing to prefab in. It saves you time. But when you can utilize aspects like core, your tiles, your flooring, your windows, even your joinery, which are probably your largest aspects of a construction outside of your foundations and your concrete,
24:00
Unidentified speaker (speaker_0): then just for example, you're gonna say save yourself 50% on the windows. You're gonna save yourself 50% on the joinery. Two aspects which, quoted here in Australia, are gonna cost you 100 grand, if not 80, you're getting them done for 30 or 40,000.
24:16
Unidentified speaker (speaker_0): And you obviously make concessions in how the things are built, right? We're not talking high-end high end architectural homes. They're not floor-to-ceiling floor to ceiling tiles, they're not stone bench top. tops throughout. They're they're they're simple builds that are built for people that are either looking for an investment in property, a first home buyer, or you know,
24:36
Unidentified speaker (speaker_0): a young family that are looking to just move into a home. So you want to provide that housing for that target market. You have to build with that in mind.
24:49
Unidentified speaker (UNKNOWN): So how
24:50
Justin Getty: it
24:50
Unidentified speaker (UNKNOWN): comes up,
24:51
Unidentified speaker (speaker_0): I guess, with that two, like that's called that two thousand dollars a square meter, like I said, there's no margin on that. So if we were putting margin on 2,000 a square meter, we're already at 2400 a square meter. You've got contingency at 5%, which then takes you to $2,500 a square meter, risk, preliminaries, supervisor, wage. That's basically
25:11
Unidentified speaker (speaker_0): your $26,000, twenty-six, $2,700 twenty seven hundred a square meter. So, yes, we are. saving twenty six or twenty seven hundred a square meter, but we're not actually saving it. We're deferring it.
25:22
Justin Getty: Mm-hmm. Well I always work on a turnkey per square meter rate myself, um, because that includes everything for the project. So I don't think you get a I get a better idea of what
25:34
Unidentified speaker (UNKNOWN): the
25:35
Justin Getty: overall total cost is for the dwelling. Um
25:40
Justin Getty: it's always cheaper when people just talk about the building costs.
25:44
Unidentified speaker (speaker_0): Yeah.
25:45
Justin Getty: Um
25:45
Unidentified speaker (UNKNOWN): because
25:46
Justin Getty: there's still a lot more cost to add in, as you just outlined, the land, the demo, all the other
25:51
Unidentified speaker (speaker_0): and all of that, if you put all of that into it, we're looking at so if we go land man procurement of 900,000 stamps and fifty, 50. our subdivision cost costs on it. are 110,000, right? So call it 25,000 a house. You've already added a couple of hundred dollars a
26:11
Unidentified speaker (speaker_0): square meter. Your demo cost is 20, 22,000 on that block there. So you know, you've got 150,000 on that cost that goes on top of it, that is not in the build cost, but we're talking build cost. Because in the end of the day we're showing what you can build the house for. If this was a
26:31
Unidentified speaker (speaker_0): one site, that's what you could build the house for. Now no, that's probably not correct because we are getting volume rates, it being a one into four. But it's more so just to show the general public this is what can actually be done for us. It'd be very hard for a mum and dad to do it. and They'd have to then manage this whole thing themselves,
26:51
Unidentified speaker (speaker_0): and that's where a lot of people become unstuck.
26:55
Unidentified speaker (UNKNOWN): But
26:55
Unidentified speaker (speaker_0): yeah, you get guys out there that are quoting three, three and a half, four thousand square meter now for development blocks, and it's ridiculous. Because I know their costs aren't there, but they're building a lot of risk into it right now. And I know a lot of developers that are pure property developers, they they're not builders, they don't have builders' licenses. They're selling stock
27:15
Unidentified speaker (speaker_0): now and they're they're holding off because it's too risky for them. And that's where we save as well. Being a builder developer, our risk mitigation is on us.
27:25
Unidentified speaker (UNKNOWN): Yeah,
27:26
Justin Getty: I want to come back to the builder developer question because I've got a couple of questions I want to ask you about that. But I just want to go back to
27:34
Unidentified speaker (UNKNOWN): the
27:34
Justin Getty: four-unit four unit site.
27:37
Justin Getty: How do you prepare? yourself to go to do a multi-unit project when you haven't done that before?
27:44
Unidentified speaker (speaker_0): It's easy.
27:47
Unidentified speaker (speaker_0): That's easy. It's rinse and repeat. The thing is, the the niche market that we're in is probably the hardest market to work in. It's super heavy detailed. It's obviously very involved with client and architects. Um When you're talking the actual construction application, you're using materials that are going
28:07
Unidentified speaker (speaker_0): to be nowhere near this project, right? So it's fine details. We've got in the projects that we do now. You know, you're talking rake ceilings and curved walls and these little niche details where you're doing P50 finishes to everything in shadow lines, and you've got all these special trims that go in and post.
28:26
Unidentified speaker (speaker_0): polished concrete. The actual construction process that we go through on our work is very detailed and very difficult. Whereas when you're talking a one into four, the subdivision's the easy part. Building it becomes much, much easier because we won't actually use our guys for.
28:46
Unidentified speaker (speaker_0): We will subcontract out 90% of the work, and our guys will be there for a few. if there's any overflow that needs to get done quick. Because what is sounds counterintuitive, me using my guys on that project would actually be more expensive. We are set up for that
29:06
Unidentified speaker (speaker_0): fine detail architectural work where the details need to be really thought out, programmed, and and and the process needs
29:14
Unidentified speaker (UNKNOWN): to be.
29:15
Unidentified speaker (speaker_0): be like
29:17
Unidentified speaker (speaker_0): diligent. Whereas with this stuff here, it's you dig your footings, obviously the same, but it's like one after another, and someone that's going there to dig four slabs is going to be much cheaper than it cost me, for example, to sit there. They'll dig them in a day. It takes me three days to dig Sitting. them. When they're knocking these frames up, you get a crew, a chippy crew out there, a first
29:37
Unidentified speaker (speaker_0): fix fixed crew, they go on they and they smash these things up in two days. It would take my guys a week and a half. Right? So when you're talking at that volume at that pace, it is much easier to do it with subcontractors and manage them and just say, all right, guys, one after another, one after another, one after another. And funny enough, the risk on that is
29:57
Unidentified speaker (speaker_0): actually less because we're not, you know, we've got these guys, they will price up the job before it starts.
30:03
Unidentified speaker (speaker_0): Here's the plants, here's the uh timber framing documentation, here's the structural engineering, price it up. Okay, this is the price, bang, go and do it. This is your time, program it, it's done. It's just pure construction management.
30:17
Unidentified speaker (UNKNOWN): Well,
30:17
Justin Getty: what about the due diligence on the site before you then go and buy it? Because obviously buying a development site is different to a multi-unit multi unit development site side is different.
30:27
Justin Getty: Yeah, like it's very different to buying a block of land and building a single house. There's different due diligence that you have to do.
30:34
Unidentified speaker (speaker_0): I've got a very diligent I'm a numbers guy. I've got a very diligent feasibility calculator that I've built. So I do my research on what we can put on there first, and I make sure. And this one here it's a deemed dean to satisfy block, so we don't have to worry about anything being performance assessed and town planners, whether or
30:54
Unidentified speaker (speaker_0): not the council will still want to come back with some RFIs, but essentially it's a deemed to satisfy block. So there should not be too many questions. I'm pretty sure they've got a question about a tree protection zone there, but it doesn't actually fall in the tree protection zone, so that one's an easy one to do. But we look at the block, we look at what's sold in the area, and we speak to, you know, I spoke to
31:14
Unidentified speaker (speaker_0): eight age. agents before we even put an offer in on this block. This is a product we're looking at building. What do you think it's worth? Take an average of that, put in to my calculator. This is the purchase price, this is the holding costs, this is what because with development financing, obviously, you have your amortized interest that comes in at the end. So we model it on 14
31:34
Unidentified speaker (speaker_0): months, and I don't think it's my estimate for it is it's going to be closer to 10 months, but we might. model it worst case scenario from once we start building it 14 months, and that's where your 10% amortized interest will come into that on your vote total development cost, land acquisition and your development cost, and that comes into the feasibility as
31:52
Unidentified speaker (UNKNOWN): well.
31:52
Unidentified speaker (speaker_0): We then take out about four months of holding cost for the land acquisition, which we've already done, so that's a servicing loan.
31:59
Unidentified speaker (UNKNOWN): The
31:59
Unidentified speaker (speaker_0): subdivision fees, which we had estimated to be from talking an SA water demo, all of that, $28,000 a block, and we'll bang on on
32:08
Unidentified speaker (UNKNOWN): that.
32:09
Unidentified speaker (speaker_0): Then what it costs to build. So I know what market rates are and I know what these things cost. And with some of them, I would obviously speak to subcontractors and be like, hey, look, this is what we're looking at doing. Give me a rough estimate. Here's Is the rough estimate, add 10% for contingency. I already know how to do takeoffs for the footings, for the concrete, for all of that. So that there I do it the same as I
32:29
Unidentified speaker (speaker_0): did anything else. And we still add about five or ten percent contingency into it. Do that as our total build cost, put that into the feasibility calculator, it spits out yes or no. If it's not over twenty two percent, we won't bother looking at
32:43
Unidentified speaker (UNKNOWN): it.
32:46
Justin Getty: I want to come back to this question about builder developer, because I've had this conversation a fair bit in the last couple of weeks and months with um clients that I work with.
32:58
Unidentified speaker (UNKNOWN): And
32:59
Justin Getty: I'm always curious because from the outside looking in, people just think, oh builder developer, they've got this built-in margin, they've got the builder's margin, then they've got the developer's margin.
33:12
Unidentified speaker (UNKNOWN): But
33:13
Justin Getty: what is it that people don't understand or what are the risks that they don't see around being the builder developer?
33:20
Unidentified speaker (UNKNOWN): The
33:20
Unidentified speaker (speaker_0): cost we talked about is pure cost. There's no margin in that. We have a five percent contingency in the feasibility. So let's say that this project has a million bucks profit in it, we've got 5% five percent contingency on the total development cost. So that could end up being 900,000, for
33:40
Unidentified speaker (speaker_0): example, or 950.
33:42
Unidentified speaker (UNKNOWN): Um,
33:43
Unidentified speaker (speaker_0): the risk associated is that we are doing it for no margin, we are taking time, effort, and resources away from our company at zero cost, right? So when you do a building job project for a client, you got 15, 20, 25% into that, that helps you flow. float and
34:03
Unidentified speaker (speaker_0): that covers administration and your running costs and your supervision. We are covering that for the course of 10 months. So
34:11
Unidentified speaker (speaker_0): or while we are managing the risk of the build
34:16
Unidentified speaker (UNKNOWN): and
34:16
Unidentified speaker (speaker_0): the cost and the risk associated with that, the actual resources that we are outlaying and the resources that we are, the the output of resources is where the risk comes into it. So
34:28
Unidentified speaker (speaker_0): we're working for free for 10 months. If it doesn't get the sale price we're estimating, that comes off what it is. If we get a COVID, if we get an oil thing, and all of a sudden our estimated costs are 300,000 and now 350, that's money we've lost out of the profit, out
34:48
Unidentified speaker (speaker_0): of the back
34:49
Unidentified speaker (UNKNOWN): end.
34:51
Unidentified speaker (speaker_0): And inevitably, we bought this block. Well, we we um
34:57
Unidentified speaker (UNKNOWN): we
34:57
Unidentified speaker (speaker_0): had the contract on this block four months ago. House prices have dropped since
35:01
Unidentified speaker (UNKNOWN): then.
35:02
Unidentified speaker (speaker_0): So our end product feasibility is probably down about three percent. So on an 850,000 exit price, we're talking close to 40 grand per block. So It's about 160 grand. We're talking that was in that initial feasibility model. That's probably not there anymore.
35:21
Justin Getty: So, how does that make you feel?
35:25
Unidentified speaker (speaker_0): Uh, it is what it is. It's the course of doing business. Development is risky. Um, that is why you make sure when you do your feasibility, if you're wanting to develop, you have a bulletproof feasibility that has contingency. built in, and that isn't a 12%, 15%, 18% margin, because
35:45
Unidentified speaker (speaker_0): you need to allow for these things, costs of construction going up and/or house prices going down. I know everyone thinks that house prices never go down, but the last six months have shown us that, haven't it? So, you know, So as long as and look, the the the we're in a market where it's affordable housing. I don't think it can drive. drop too much. People are going to have to
36:05
Unidentified speaker (speaker_0): start buying again in six months. By the time we've built this out, we're probably going to end up back to where our feasibility was, anyways. Because the fact of the matter is there isn't enough housing out there. There has to be
36:17
Unidentified speaker (speaker_0): policy has to do something. There right now new homeowners aren't purchasing, investors aren't purchasing, and the government can spit on all they want about how that's helping the cost of living crisis, but it's damaging the housing market. And the more they damage the housing market, the more builders are going to go bust, the more it's going to affect
36:37
Unidentified speaker (speaker_0): the sh the uh housing crisis.
36:41
Unidentified speaker (speaker_0): So I think something will happen in the next six months that's gonna bring some confidence back into the market. And by that time, we'll probably be getting close to you know six to eight months. from January. We'll be close to hopefully having a built product and at which point there'll be some recovery. And if not, we lose 160 grand on it. As long as we don't lose
37:01
Unidentified speaker (speaker_0): money on it, it is what it is.
37:03
Justin Getty: You've been quite outspoken on s your social channels about the challenges of being a builder recently.
37:12
Unidentified speaker (speaker_0): Yeah.
37:13
Justin Getty: How can uh what's the reasoning behind that?
37:17
Unidentified speaker (speaker_0): Because it's getting more and more difficult. Um, it is very easy to run a sustainable business in a growing market. Anyone can do it. And when cash is flowing and when money is cheap, as I like to call it. So, right now, what's the interest
37:37
Unidentified speaker (speaker_0): rate that they bumped it to? yesterday? 4-6 or 4-8?
37:41
Justin Getty: 4-8-5.
37:44
Unidentified speaker (UNKNOWN): When
37:44
Unidentified speaker (speaker_0): you're talking 485 cash rate, right? Construction, development, finance goes up to 7%, 8%, 9%.
37:54
Unidentified speaker (speaker_0): Money's no longer cheap. So people tighten up, banks tighten up. And when you have a market that is working on tight market, margins and on expensive money, everything starts to tighten up, and you basically have to drop your pants to win work. So it's getting increasingly difficult
38:14
Unidentified speaker (speaker_0): for jobs to go through, or they're being severely value managed, and you're having to cut profit margin just to win the work. And then on top of that, you've got rising costs for doing business, insurance. has gone up, work cover has gone up, fuel has gone up, cars have gone up. Like literally
38:34
Unidentified speaker (speaker_0): every aspect of construction has gone up. And then if you are not being diligent in your operations, it gets very, very, very difficult to actually operate sustainably. And that's where a lot of guys are going to become unstuffed. unstuck now is through COVID, there was so
38:54
Unidentified speaker (speaker_0): much stimulus pumped into the industry that you could have thrown a dart outside, hit a project, wanted at 25%. It was all gravy, you didn't have to run it that well, didn't have to be run that efficiently because you had enough risk management into the contract to be able to operate. Right now, rate ra uh margins are razor thin. thing And the actual, like I said,
39:13
Unidentified speaker (speaker_0): cost of doing business. is expensive. So you have to be diligent. Margins aren't there anymore for us to be able to just run the job willy nilly and be
39:23
Unidentified speaker (UNKNOWN): like,
39:23
Unidentified speaker (speaker_0): it'll be fine, you've got another job starting next week and another one next month and another one in three months. I personally, from my experience, the market's close to sixty percent down.
39:35
Unidentified speaker (UNKNOWN): Yeah,
39:35
Justin Getty: well it's interesting 'cause interesting because in Victoria they
39:39
Justin Getty: state government claims that they want to build more houses, yet the tax policy settings
39:46
Justin Getty: actually encouraging the opposite.
39:50
Justin Getty: They have this magic putting idea that you can tax property more and somehow get more of it.
39:57
Unidentified speaker (speaker_0): Yeah, it's um look, I think
40:02
Unidentified speaker (UNKNOWN): I
40:03
Unidentified speaker (speaker_0): think the government have a part to play in where we're currently at now, but I also don't think it is totally their fault they just uh put the cherry on top of the cake. A lot of this is back end from COVID. I said in 2023 that come 26-27, the building industry is gonna going to feel it because you cannot
40:22
Unidentified speaker (speaker_0): pump that much stimulus into an industry. and not have a backfall of it. Like there was so much work going on. There comes a time where one that work dries up, 80% of people were doing work on their house. Like there was a time in 24 where you would drive down the
40:42
Unidentified speaker (speaker_0): blue chip suburbs, and not even just the blue chip suburbs, but every second house had construction going
40:48
Unidentified speaker (UNKNOWN): on.
40:49
Unidentified speaker (speaker_0): Because, like I said, house prices were going up, money was cheap, so people were capitalizing on a growing market. Now, half those people are probably in negative equity because they've gone and spent two million dollars on a house that's just dropped half a million, right? And people now are like, Well, we're not going to leverage ourselves.
41:09
Unidentified speaker (speaker_0): So all of a sudden, we're in this very weird and awkward stage in the in building and construction world where the work's not there, it's more expensive to do, it's more expensive to run. Guys' wages are more expensive. You go buy a bottle of water and it costs you three bucks.
41:28
Unidentified speaker (speaker_0): It's a it's it's gonna be a difficult time, and I think we're gonna see a lot of guys struggle over the next eighteen 18 months.
41:36
Justin Getty: So what's your advice then for developers out there working with builders at the moment in this environment? And what's what's the best way to get the best outcomes?
41:47
Unidentified speaker (speaker_0): The I call it mom and dad developer model, but you can be a pure property developer. It's going to be increasingly hard because builders are going to be putting in larger margins. So you either have to buy the block at an exponentially
42:02
Unidentified speaker (UNKNOWN): grow.
42:02
Unidentified speaker (speaker_0): great rate, which is the opportunities are actually there now.
42:08
Unidentified speaker (speaker_0): Um
42:09
Unidentified speaker (speaker_0): and I guess if I were a mum and dad developer, you've got to try and lock in some good volume builders because there's a lot of shit volume builders out there that are going to cost you more than they're worth. But if you can get a good relationship with a good volume builder that you can work with, that's probably your
42:29
Unidentified speaker (speaker_0): only way because
42:31
Unidentified speaker (speaker_0): relying on builders is unfortunately one of the biggest risks that's associated with the development. It's not the house prices going down. And it's not when you procure the land, it's the build.
42:45
Unidentified speaker (speaker_0): So if you've got a builder that's going to slap you with 20 or 30 percent investment. in variation cost throughout the build, and or tell you it's an eight-month build and take 20 months to build it, you know, you're getting slapped with costs that you can't control or holding costs that you can't control.
43:05
Justin Getty: Yes, well, I have personal experience with what happens when it goes wrong with the builder and it's not great. I can assure
43:13
Unidentified speaker (UNKNOWN): you
43:14
Justin Getty: of that. that
43:15
Unidentified speaker (speaker_0): and the thing is it's like that now I think that model is going to struggle over the next again 12 to 18 months and think until things stabilize. I know a lot of pure property developers right now, like I said, they've sold stock and they're selling stock aggressively. They're taking their
43:34
Unidentified speaker (speaker_0): capital
43:35
Unidentified speaker (UNKNOWN): and
43:35
Unidentified speaker (speaker_0): they're sitting it aside for the next two years.
43:40
Unidentified speaker (speaker_0): But again, that's a double-edged sword because we need housing. Pure property developers, the ones with the big capital, if they're all of a sudden saying, well, we're just not going to do the land developments and we're not going to build the houses,
43:56
Unidentified speaker (speaker_0): it almost adds to the crisis, and it's going to do the opposite of what the government are actually. trying to do by decrease housing price and helping that um first home buyer get into the into housing into the housing market. Because if twenty, thirty percent of developers shut up shop now for the next two years and live
44:16
Unidentified speaker (speaker_0): off the millions they've got sitting in the bank because they're not sitting in a piece of land, guess what? The stock that is out there is gonna going to go up.
44:25
Unidentified speaker (UNKNOWN): Yeah,
44:26
Justin Getty: it m there's much of it. Um, but you mentioned that builders are putting up their margin to uh accommodate extra risk. Doesn't that just actually make them less likely to win the work?
44:40
Unidentified speaker (speaker_0): 100%.
44:42
Unidentified speaker (speaker_0): Right now I lost
44:45
Unidentified speaker (UNKNOWN): um
44:46
Unidentified speaker (speaker_0): well, and this wasn't purely us putting up our margin,
44:49
Unidentified speaker (UNKNOWN): but
44:50
Unidentified speaker (speaker_0): it was just making sure we were very diligent with everything that was quoted inside our margin, all of our preliminaries, our site supervision, the whole lot. And this isn't us, but out of the last six jobs that we've priced, six of them have not gone through.
45:06
Unidentified speaker (speaker_0): And
45:07
Unidentified speaker (speaker_0): two of them I maybe could have got to gone through if I had reduced my margin significantly
45:14
Unidentified speaker (UNKNOWN): and
45:14
Unidentified speaker (speaker_0): made. maybe taken some concessions in site supervision and stuff like
45:18
Unidentified speaker (UNKNOWN): that.
45:19
Unidentified speaker (speaker_0): But inevitably stuff goes wrong in building. Time blows out, scope changes, and anytime we've done that in the past where we've made concessions in our pricing to meet a client's budget, it's ended up costing us money or we've worked for free. So builders are sick of it. They're not doing it anymore. This is the cost. This is the
45:39
Unidentified speaker (speaker_0): value of the project. If you can't afford it, we won't do it because it's getting to the point where it's better not to have the work them to do the work that costs you money.
45:49
Unidentified speaker (UNKNOWN): So
45:50
Justin Getty: you touched on variations before
45:53
Justin Getty: it's sort of a bane of I know builders always say they don't like variations. Developers always say they don't like variations, but invariably they come up
46:04
Justin Getty: What's the best way to minimize the likelihood of them happening?
46:08
Unidentified speaker (UNKNOWN): And
46:08
Justin Getty: how what's your advice on managing variations with builders?
46:12
Unidentified speaker (speaker_0): Extensions, renovations impossible. It's just not possible. When you're talking with existing structure that you don't know what's going on in a under an old slab, in the walls, in the roof, is there asbestos cladding, etc.? etc. They are inevitable. Any project that we do that is an extension or
46:32
Unidentified speaker (speaker_0): renovation, we tell every single client, allow for 20%. New builds should be less, but where I find what happens is
46:42
Unidentified speaker (UNKNOWN): if
46:42
Unidentified speaker (speaker_0): you've got a solid selection schedule, you know what's going on, this is the build, the engineering's been done the site survey has been done. You've got all your bore logs, you
46:53
Unidentified speaker (UNKNOWN): know
46:54
Unidentified speaker (speaker_0): what's going on on the ground. Unless you're knocking out an old uh uh you know, a knockdown rebuild and you don't know what's under the slab and in the dirt, there shouldn't be variations in the build where variations come into the build is you want to change A, you want to change B, you want to change D, you want
47:14
Unidentified speaker (speaker_0): to change C. This selection hasn't been made yet. If you can knuckle down all your selections, if you can knuckle down all your finishes, and then when the job starts,
47:24
Unidentified speaker (UNKNOWN): just
47:24
Unidentified speaker (speaker_0): say, hey, Mr. Builder, you go ahead and build what we've selected. We're not going to come here until it's done or until you ask us to.
47:31
Unidentified speaker (UNKNOWN): You
47:32
Unidentified speaker (speaker_0): shouldn't have any variations. Not to say that that doesn't happen because there are builders out there that will price low. and they'll put a lot of PC sums into their quotes and then all of a sudden you don't know what a PC sum is as a client.
47:46
Unidentified speaker (UNKNOWN): And
47:46
Unidentified speaker (speaker_0): it comes to it, they say, oh, we have $30,000 in joinery allowance, but you're a hundred grand. Like that's just unethical, but it does happen. But that's why I said if you can really knuckle down your selections, have full joinery design done, have a tile layout done, have tile set out, the whole lot. then
48:04
Unidentified speaker (speaker_0): you shouldn't limit the amount of variations that are chargeable.
48:10
Justin Getty: Yeah. That's a whole other discussion about uh builders deliberately
48:17
Justin Getty: underestimating things in their pricing and then seeking it back through variations. I've seen that happen.
48:25
Unidentified speaker (UNKNOWN): Oh,
48:25
Justin Getty: we missed the uh some retaining walls here and here.
48:31
Unidentified speaker (UNKNOWN): Missed.
48:31
Justin Getty: Yes.
48:32
Unidentified speaker (UNKNOWN): We actually
48:33
Unidentified speaker (speaker_0): had a big one where this it wasn't missed, but it was um the engineer had left out
48:40
Unidentified speaker (speaker_0): a bunch of retaining. And I said to them, Hey, I think this needs retaining.
48:47
Unidentified speaker (UNKNOWN): And
48:47
Unidentified speaker (speaker_0): they said, No, just batter it, it's on the engineering. And then when we actually got to it, I said, it's impossible to batter. It's four and a half meters. Like you you can't batter
48:57
Unidentified speaker (UNKNOWN): it.
48:58
Unidentified speaker (speaker_0): Ended up costing the client 35 grand.
49:03
Unidentified speaker (speaker_0): So yeah.
49:05
Justin Getty: But that's okay. That's not a builder missing something.
49:09
Unidentified speaker (speaker_0): No. But a lot of the time builders will. I had actually an no old friend, he built
49:15
Unidentified speaker (UNKNOWN): and
49:15
Unidentified speaker (speaker_0): the builder had in a very, very, very uh detailed document, right? One minor clause in there that said no structural steel allowance on a double story six hundred square meter house.
49:27
Unidentified speaker (UNKNOWN): And
49:27
Unidentified speaker (speaker_0): then when it came to it, builder hits them up for thirty five grand of structural steel.
49:33
Unidentified speaker (UNKNOWN): And
49:33
Unidentified speaker (speaker_0): my friend was like, Hold up,
49:35
Unidentified speaker (UNKNOWN): what
49:35
Unidentified speaker (speaker_0): are you talking about? Oh I have a check at clause, cause you of know, whatever. 75.1B, no structural steel, and they're like, but it's in the engineering. Oh, yeah, but we didn't allow for
49:46
Unidentified speaker (UNKNOWN): it.
49:49
Unidentified speaker (speaker_0): So knowing your contract is a big one. I if I was a client,
49:54
Unidentified speaker (speaker_0): and builders are gonna hate me saying this, all right.
50:00
Unidentified speaker (speaker_0): Spend a thousand bucks to get a construction law. lawyer to look over the contract because builders might not want to hear me say
50:08
Unidentified speaker (UNKNOWN): that.
50:08
Unidentified speaker (speaker_0): But most of the issues that arise on a build are from clients not understanding what they're actually getting. If that can be clarified from day one, it makes for the whole process a lot less hostile as it goes on. Because if they know what they're getting and what they're not getting, they may be okay with structural. still not being in there
50:28
Unidentified speaker (speaker_0): because they'll plan for it when and if it comes. But if it's like you've pulled the wool over their eyes and then it comes to it, you end up fighting with
50:36
Unidentified speaker (UNKNOWN): them.
50:37
Unidentified speaker (UNKNOWN): Yeah
50:38
Justin Getty: well I've been having a few conversations with my mentoring clients at the moment about
50:43
Justin Getty: contracts and going through them. Um
50:47
Unidentified speaker (UNKNOWN): So
50:48
Justin Getty: yes there's some vagaries in the standard industry build contracts that um I think tend to favor
50:55
Unidentified speaker (UNKNOWN): the
50:55
Justin Getty: builders, but you need to be aware of what you're signing up to when you enter into those contracts.
51:01
Unidentified speaker (speaker_0): There are, and I think they should, because I think the builder does need to be protected in a way because
51:08
Unidentified speaker (speaker_0): there's not a lot of recourse for a builder to claim money back, for example, from a client that just decides not to pay. right? Whereas if a builder does something wrong, there's a lot of recourse for a client to be able to chase them. You've got the BPCC, whatever it is in Victoria. Here we've got CBS, you've got small business claims. All of that
51:28
Unidentified speaker (speaker_0): is is you know client to builder that will get the we'll will will we'll get the wind choked out of us by one of those regular. regulatory bodies if it's correct. The amount of builders I'm talking to lately that have gone under, that have nearly gone under, or you know, that have been
51:49
Unidentified speaker (speaker_0): facing voluntary administration or bankruptcy because they get to the end of a job, or they get a client that puts in $100,000 worth of variations, or they've got a $50 or $80,000 $80 or $100,000 fund. final claim, and the client basically just says, tough shit, we're not paying.
52:09
Unidentified speaker (UNKNOWN): The
52:09
Unidentified speaker (speaker_0): builder has no recourse. Their only recourse is go hire a lawyer,
52:14
Unidentified speaker (speaker_0): sue that person, and by the time it gets anywhere near you being able to get your money back, if you can get your money back, you spent fifty $50,000 thousand dollars in legal fees that are non uh
52:26
Unidentified speaker (UNKNOWN): uh
52:26
Unidentified speaker (speaker_0): that are non-claimant. So I think the builder needs to be protected. Not to say that the client doesn't need to
52:34
Unidentified speaker (UNKNOWN): be,
52:36
Unidentified speaker (UNKNOWN): but
52:36
Unidentified speaker (speaker_0): the builder does need protection because in the end of the day, the risk is on the builder, right? Yes, the risk is on the client, but unless the client's paying the builder in full and then saying, see you later, we'll see you when the job's done, the
52:50
Unidentified speaker (UNKNOWN): risk.
52:51
Unidentified speaker (speaker_0): is on the builder, the financial risk is on the builder. Building a home, the risk literally lies on the principal contractor until it's done and that final completion payment has come through. And a lot of guys don't understand this, especially non-builders. The whips of a builder at any given time
53:09
Unidentified speaker (UNKNOWN): is
53:09
Unidentified speaker (speaker_0): in the hundreds of thousands. And for those that don't know what whips are, it's your works in progress. So, yes, you take a deposit of five, ten percent, whatever it may be. That gets you through your preliminary stages. By the time you've gotten to pouring a slab, you're a hundred grand in work, 150 grand. You may claim 150, so now your whips is
53:29
Unidentified speaker (speaker_0): zero. You still have to then go from slab to lockup and it costs cost you 200 grand to get to the lockup. Where's that 200 grand come from?
53:37
Unidentified speaker (UNKNOWN): That
53:37
Unidentified speaker (speaker_0): 200 grand comes from the builder. Comes from the builder financing that portion of the work until they get paid. So the builders need protection because
53:50
Unidentified speaker (speaker_0): it's a risky job. And you know, you'd rather your builder have protection and have a job that runs efficiently, cash flow-wise, structure-wise, because when it doesn't, that's when the builder goes bust halfway through a job, and then all of a sudden you're left there with a half-done house. And I don't know if you've ever had to, you probably haven't. I know people that have
54:10
Unidentified speaker (speaker_0): had to. You go deal with a half-built house, try and get someone else to come build it, they're gonna slog you two times what it costs for the house to be built originally.
54:26
Unidentified speaker (UNKNOWN): I
54:27
Justin Getty: think the issue with the housing industry contracts is that they're vague. And around some of the issues that you've talked about, variations, it's vague, um, dispute resolution, super vague, extensions of time, quite vague.
54:42
Unidentified speaker (speaker_0): Yep. And
54:43
Justin Getty: these are the issues this is where the issues tend to arise in most building contracts. So that's where
54:48
Unidentified speaker (UNKNOWN): I think.
54:49
Unidentified speaker (speaker_0): Builders are bad at documentation. Okay. They're they're horrible. I don't funny enough that you say that, and this is why we've got here, but I've built a software that actually helps with that, and we're about to release it to the market because it covers all of everything you just said, your variations, your extension of time delays. Basically, everything that builders missed, we
55:09
Unidentified speaker (speaker_0): built a software that covers it all and makes it very easy to do.
55:14
Unidentified speaker (UNKNOWN): Yeah.
55:14
Justin Getty: and then just going
55:17
Justin Getty: on
55:18
Unidentified speaker (UNKNOWN): with
55:18
Justin Getty: the costs, I think that's a hangover for builders from a bygone era where the amounts of money involved in those different stages were nowhere near as big as what they are today. So I don't think builders ever had to carry the vast sums of money.
55:35
Unidentified speaker (speaker_3): When you
55:36
Unidentified speaker (UNKNOWN): were
55:36
Unidentified speaker (speaker_3): talking $250,000
55:38
Unidentified speaker (speaker_0): to build a big home,
55:40
Unidentified speaker (UNKNOWN): you
55:40
Unidentified speaker (speaker_0): might have been helding $50 grand between those claims.
55:43
Justin Getty: Yeah.
55:43
Unidentified speaker (speaker_0): Our whips at the end of the finer last financial year was $420,000.
55:50
Justin Getty: So there's been no adaptation to the rising costs and maybe having multiple payment stages rather than just the old school
56:01
Unidentified speaker (UNKNOWN): Yeah, your
56:01
Unidentified speaker (speaker_0): method B contract but um
56:05
Unidentified speaker (speaker_0): you know how hard it is to get anything through that is a different indication of your standard HIA or master builder's contract through to a bank. I have fought tooth and nail with banks for six years because we've always tried to add in more progress claims than then is shown on the thing for that reason,
56:24
Unidentified speaker (speaker_0): right? They have five. We want 10. I think the perfect model is for however many months the project's um schedule is, is how many progress claims you should have throughout the course of that build. So if it's a 12-month project, there should be 12 progress claims. Not to say that they're going to hit
56:44
Unidentified speaker (speaker_0): every month, but you should be hitting, you know, if you're not hitting one a month, you might hit two in the next.
56:52
Unidentified speaker (speaker_0): Because
56:53
Unidentified speaker (speaker_0): the regulators and the banks and the and the industry actually need to do something about helping builders cash flow. Because most builders are profitable. Most go bank m most builders are profitable. Most go bus because they don't have the cash flow to get them through the next month.
57:10
Justin Getty: I totally agree. I think they should do that. I think the challenge. is for builders being organized, as you said. I think for a lot of them they're like they can't be bothered going through that monthly claim process.
57:24
Unidentified speaker (speaker_0): I just think they're not used to it. I think if they do it a couple of times and realize they can claim money every month and not have their suppliers chasing them and their subcontractors Contractors chasing them because they don't have the cash in the bank because they're waiting for a $300,000 payment six weeks away.
57:39
Unidentified speaker (speaker_0): they'll get used to it quick.
57:43
Justin Getty: And like it.
57:44
Unidentified speaker (speaker_0): Yeah.
57:45
Unidentified speaker (UNKNOWN): You
57:45
Justin Getty: touched on provisional costs, and I know that's an area where a lot of builders at the moment are sort of putting generous numbers in for a for a developer out there looking at a build cost or an estimate and or a in contract. by the builder, what can they do to
58:05
Justin Getty: nail down those provisional sums?
58:09
Unidentified speaker (speaker_0): Exactly what I said. Have your selections bulletproof. So, you know, don't just say we've got some concepts here for joinery. This is what we want, and they're gonna, you know, put a PC sum or a or a provisional sum
58:25
Unidentified speaker (UNKNOWN): in. Um
58:27
Unidentified speaker (speaker_0): of thirty grand lock down
58:31
Unidentified speaker (speaker_0): what you're doing literally have it so it's we want this run of joinery this island bench this here we're gonna have this draw units go and spend 10 grand on interior designer or a joinery um like an interior architect or a joinery designer so that you can go to the builder and say hey this is absolutely actually what
58:51
Unidentified speaker (speaker_0): we're building, this is what we want, price it.
58:55
Unidentified speaker (UNKNOWN): Not,
58:56
Unidentified speaker (speaker_0): oh yeah, the concepts are a two-meter island bench and this and that, and um, probably gonna cost you about 30 grand.
59:05
Unidentified speaker (speaker_0): Having your selections locked down, select your tiles, select your taps, select your curtains if you're putting them in. It might make the process and the in preliminary. stages a couple of months longer, but it's going to save you headache. Because once you've provided that, the builder shouldn't be PCing
59:22
Unidentified speaker (UNKNOWN): it.
59:24
Unidentified speaker (UNKNOWN): Yeah,
59:24
Justin Getty: because I've seen builders doing PC sums for landscaping.
59:29
Unidentified speaker (speaker_0): We PC landscaping.
59:32
Justin Getty: How come you can't lock that down?
59:34
Unidentified speaker (speaker_0): Because 99% of clients refuse to get a landscape design done.
59:39
Unidentified speaker (speaker_0): So are you doing gravel? Are you doing concrete? Are you doing uh turf? Are you doing fencing? What's the fencing? Is it colour bond? Is it steel? Is it a rendered plinth? Is it A B C? And most clients will say, Oh, we'll just figure it out at the end when we know how much money we've got left. So, you know,
59:59
Unidentified speaker (speaker_0): you put a PC in there for 20 and 30 grand
1:00:02
Unidentified speaker (UNKNOWN): and say,
1:00:02
Unidentified speaker (speaker_0): look, there's this allowance in there, you can work up to this, anything above that is a variation.
1:00:09
Unidentified speaker (speaker_0): Unless we're doing our real high-end architectural stuff where it normally has a landscape design in there, 99% of clients will not do it. We suggest it to them, not will figure it out at the end.
1:00:23
Justin Getty: Interesting.
1:00:25
Unidentified speaker (UNKNOWN): So
1:00:25
Justin Getty: tell me, Anthony, what have you learned about your yourself along the way through all this uh building and developing?
1:00:34
Unidentified speaker (speaker_0): That no matter what
1:00:37
Unidentified speaker (UNKNOWN): is
1:00:37
Unidentified speaker (speaker_0): happening, no matter how bad you think it is, there is always a light at the end of that tunnel. There is always an endpoint that you can get through if you're willing to work through
1:00:49
Unidentified speaker (UNKNOWN): it.
1:00:50
Unidentified speaker (speaker_0): I have thought about giving up
1:00:54
Unidentified speaker (speaker_0): more times than you can imagine. Uh when things get tough, I don't want to get out of bed. I don't want to go to work. I don't want to do the work. I don't want to sit there and look at cash flow analysis and say, Hey, if everything goes to shit over the next six weeks, we're done. But you have to and you have to work
1:01:14
Unidentified speaker (speaker_0): towards it. And
1:01:16
Unidentified speaker (speaker_0): we
1:01:18
Unidentified speaker (speaker_0): as people
1:01:19
Unidentified speaker (UNKNOWN): are
1:01:19
Unidentified speaker (speaker_0): much stronger than we think, and we can get through it. You literally just have to work to that goal, right? You have to have a plan in place because, like Mike Tyson said, everyone's got a plan until you get punched in the face, and you get punched in the face a lot in building. But just re-plan, replan and work to it.
1:01:39
Unidentified speaker (UNKNOWN): Yeah,
1:01:39
Justin Getty: I like to ask people what's your success rate like at getting through life so far?
1:01:46
Justin Getty: That's a percent.
1:01:47
Unidentified speaker (UNKNOWN): Well,
1:01:47
Unidentified speaker (speaker_0): 15 years, it's 100%.
1:01:49
Unidentified speaker (speaker_0): Right? I say this to people all the time: think of the worst thing that you've ever gone through, and at the time, how you felt about it, right? You never thought you could get through it, but you've gotten through every single one of those things. Why is now any different?
1:02:07
Justin Getty: And what about your advice for property developers out there who would be looking to take their business to the next level?
1:02:17
Unidentified speaker (speaker_0): That's a tough one to be honest with you. Because right now, if you want you're my honest answer, I would say don't. Or if they've got capital,
1:02:28
Unidentified speaker (speaker_0): someone's got a lot of capital deployed to deploy right now, I would be land banking. I would be land banking like no tomorrow, because
1:02:41
Unidentified speaker (speaker_0): there's an old saying when there's blood on the streets, there's money to be made. And right now there is blood on the streets. And if you had millions. sitting there, I would be buying land because people are panic selling. The market is going down. And for the next six months, it's going to continue dropping, and you're getting below
1:03:01
Unidentified speaker (speaker_0): market, it's current market, but we, you know, people like to use that below market term. You'll be buying, I've seen properties that people wanted three million dollars for, and they're willing to take two, four.
1:03:13
Unidentified speaker (UNKNOWN): I've
1:03:14
Unidentified speaker (speaker_0): seen properties that have gone to auction that were advertised at 2.4 and they've sold for 1.7.
1:03:22
Unidentified speaker (speaker_0): That's opportunity. It's not immediate opportunity, but it is opportunity for two years time. So any developer that's out there that's got capital to deploy, Employee buy those opportunities and hold 'em. Sit on 'em.
1:03:38
Unidentified speaker (UNKNOWN): Yeah,
1:03:38
Justin Getty: I mean I bought my first development site in two thousand thirteen at the bottom of the cycle and had no competition, got a really good price, really great terms, a really long settlement.
1:03:50
Unidentified speaker (UNKNOWN): And
1:03:50
Justin Getty: then by the time we came to build from when we started the building to when the building was complete, the GRV went up two million dollars.
1:04:02
Unidentified speaker (UNKNOWN): Yeah. I
1:04:03
Justin Getty: mean we didn't pick all that up because we were pre-selling,
1:04:06
Unidentified speaker (UNKNOWN): but
1:04:06
Justin Getty: from the start of the build, what we thought the GRV would be to
1:04:11
Unidentified speaker (UNKNOWN): when it
1:04:11
Justin Getty: was
1:04:14
Justin Getty: two million dollar uplift.
1:04:18
Unidentified speaker (speaker_0): Um
1:04:19
Unidentified speaker (UNKNOWN): they
1:04:20
Unidentified speaker (speaker_0): bought just before COVID.
1:04:24
Unidentified speaker (speaker_0): And they well were
1:04:26
Unidentified speaker (UNKNOWN): I
1:04:26
Unidentified speaker (speaker_0): like, we're about to go broke. We're done because everyone was talking about the house prices going down.
1:04:33
Unidentified speaker (UNKNOWN): So
1:04:33
Unidentified speaker (speaker_0): he had, like I said, five sites between them. There was about 19 homes to be built on them.
1:04:40
Unidentified speaker (speaker_0): He made a million bucks a block
1:04:44
Unidentified speaker (speaker_0): over two years by doing nothing. He basically made, you know, wasn't exactly a million a block, but he
1:04:54
Unidentified speaker (speaker_0): overnight turned four million bucks for just because of obviously through COVID and everything went.
1:05:02
Unidentified speaker (speaker_0): And by the time he had built these things, that new product had gone from a six hundred thousand dollar property, uh big built product to a nine $900,000 hundred thousand dollar built product. You got four of them on one site. It's a million bucks you just made overnight.
1:05:18
Unidentified speaker (UNKNOWN): Yeah,
1:05:18
Justin Getty: so there's opportunities when the market's bottoming out.
1:05:23
Unidentified speaker (speaker_0): There is. And I know, like I said, land banking, land bank, land bank, land bank, and hold
1:05:30
Justin Getty: get
1:05:31
Unidentified speaker (speaker_0): approvals in place, get everything in place, and then once the time comes, yep, the market's starting to go up. Execute, subdivide that land, start building, and as the market starts to go up, it takes you six to ten months to build 'em. By that time the market's climbing again. You're laughing.
1:05:49
Justin Getty: Well, I think that's where people get caught out.
1:05:58
Justin Getty: You're a bit late on the wave.
1:06:00
Unidentified speaker (speaker_0): Yeah.
1:06:02
Unidentified speaker (UNKNOWN): So
1:06:02
Justin Getty: getting in when things are not great
1:06:06
Justin Getty: is usually the best time. Because you secure secure the properties at the better prices with the better terms. You don't have as much competition.
1:06:15
Unidentified speaker (speaker_0): Yeah, exactly. Exactly.
1:06:16
Justin Getty: So there's opportunity out there.
1:06:18
Unidentified speaker (speaker_0): Yep.
1:06:19
Unidentified speaker (UNKNOWN): You just
1:06:20
Justin Getty: gotta go find it.
1:06:22
Unidentified speaker (speaker_0): Yep, exactly.
1:06:24
Justin Getty: Any other tips or advice? for people before
1:06:28
Unidentified speaker (UNKNOWN): we
1:06:28
Justin Getty: wrap it up and let you get back out on site?
1:06:31
Unidentified speaker (speaker_3): That's me for the day.
1:06:32
Justin Getty: Is it? I gotta ask you, are you one of these builders that always wears shorts round year round regardless of the weather?
1:06:39
Unidentified speaker (speaker_0): I wear shorts in winter and uh long sleeves in summer.
1:06:46
Unidentified speaker (speaker_0): My wife always makes a joke about it, she goes, It'll be a hundred degrees outside and you'll be in a jumper and and jeans and it will be raining and thunder and you'll be in shorts and a single.
1:06:58
Unidentified speaker (UNKNOWN): So
1:06:59
Justin Getty: there's a strange strange proof when it comes to clothing and weather.
1:07:03
Unidentified speaker (speaker_0): Yep.
1:07:05
Justin Getty: Alright, people want
1:07:06
Unidentified speaker (UNKNOWN): to
1:07:06
Justin Getty: find out more about you, Anthony, where should they go?
1:07:09
Unidentified speaker (speaker_0): Um so my personal page, Instagram, we've got a YouTube that we've just started where we do some more long form content and break down numbers and processes. Uh a software company which is Ask Nikolai, so that's construction tech that we've built for builders. Um and then my other business page is
1:07:29
Unidentified speaker (speaker_0): Aura Projects, O R A.
1:07:31
Unidentified speaker (UNKNOWN): Well,
1:07:32
Justin Getty: you're pretty active on Insta, and I'm guessing people can follow along on this four unit site that we were talking about.
1:07:38
Unidentified speaker (speaker_0): Exactly.
1:07:39
Justin Getty: Alright, well they'll see you in your shorts through winter.
1:07:43
Justin Getty: Inspecting rains or building programs.
1:07:45
Unidentified speaker (speaker_0): That's it. That is it.
1:07:48
Justin Getty: All right, Anthony.
1:07:50
Unidentified speaker (UNKNOWN): It's
1:07:50
Justin Getty: great having you on the Property Developer Podcast.
1:07:53
Unidentified speaker (speaker_0): Thank you. Pleasure.
1:07:54
Unidentified speaker (speaker_1): You've been listening to the Property Developer Podcast. Tune in next time for more tips, ideas, and inspiration to take your developing to the next level.
1:08:04
Unidentified speaker (UNKNOWN): For
1:08:04
Unidentified speaker (speaker_1): more developing love, make sure to visit Property Developer Podcast.com.