Critical Minerals Journal

Meridian secures $400M finance for Cabasal; Rare Earths USA, Graphite 1, UCor, Masan updates

7 min Listen to the original Episode page
Critical MineralsRare EarthsProject FinanceMiningBattery MaterialsEmerging Markets

Summary

Meridian Mining announced over 20 indicative finance offers totaling up to $400 million for its Cabasal project in Brazil, appointing AFRY as EPCM contractor. The speaker criticized the project's 108% IRR as dependent on optimistic copper and gold price assumptions, noting missing EPC contracts and off-take agreements. Rare Earths USA (Serra Verde) reported Q3 2026 revenue of $3.0 million and began commercial shipments under a 15-year agreement. Graphite 1 received an Ohio EPA air permit for its $80 million Phase 1 plant, targeting an investment decision in April 2027. UCor commissioned its Louisiana complex with 50 tons of feedstock, while Sojits Corp signed an MOU for a 5% stake in Masan High-Tech Materials.

Episode sections

  1. 0:00 – 1:11

    Meridian Mining Cabasal Project Finance and Pre-Construction

    Meridian Mining announced over 20 indicative finance offers totaling up to $400 million for its Cabasal project in Brazil, with a feasibility study showing $322 million pre-production capex. The company appointed AFRY as EPCM contractor and committed $30.9 million to pre-construction contracts, including infrastructure and mill equipment.

  2. 1:11 – 1:42

    Cabasal Project Constraints and Valuation Skepticism

    Despite a reported 108% IRR and $2.1 billion NPV5, the speaker argues the valuation relies on a copper price of $5.03/lb and gold price of $3,570/oz. Key binding constraints remain: no EPC contract for the 24.3 km power line and no signed off-take buyer for concentrate.

  3. 1:42 – 3:03

    Rare Earths USA (Serra Verde) Production and Guidance

    Rare Earths USA (Serra Verde) reported Q3 2026 revenue of $3.0 million and an operating loss of $141.4 million, with $1.16 billion in cash. It began commercial shipments of heavy mixed rare earth carbonate to USSIIE LLC under a 15-year take-or-pay agreement, guiding Q4 sales of at least 325 tons TREO.

  4. 3:03 – 4:42

    Graphite 1 Ohio Anode Plant Permitting and Strategy

    Graphite 1 received an Ohio EPA air permit for Phase 1, a $80 million plant using purchased synthetic graphite to coat anode material. The company targets an investment decision in April 2027 and first sales in Q4 2028, with a non-binding $1.4 billion LOI from the Export-Import Bank for expansion.

  5. 4:42 – 5:48

    UCor Rare Metals Commissioning and Feedstock Analysis

    UCor received 50 tons of mixed rare earth carbonate to commission Machine A at its Louisiana complex, which has a 600 tons/year TREO capacity. The speaker notes this lot covers less than a month of operation and highlights risks regarding unnamed feed suppliers and off-takers.

  6. 5:48 – 7:09

    Sojits Corp Investment in Masan High-Tech Materials

    Japan's Sojits Corp signed an MOU to acquire a 5% stake in Vietnamese tungsten producer Masan High-Tech Materials from Masan Horizon. The purchase price is no lower than that paid by Elmet, but the deal is characterized as a 'seat' rather than a supply contract until volumes are defined.

Claims worth verifying

Meridian Mining said on November 9 that its Cabasal project has entered pre-construction.

Unidentified speaker (UNKNOWN) ·0:10

How to verify: Check Meridian Mining's press release dated November 9, 2026, on their investor relations page or SEC EDGAR if they file there; verify via Mining Weekly or similar industry news archives. For recent events, verify 2026-08-09 through 2026-11-09. Use another period only when the speaker explicitly names it.

Primary source

Meridian appointed AFRY as EPCM contractor and committed $30.9 million to pre-construction contracts.

Unidentified speaker (UNKNOWN) ·0:18

How to verify: Review Meridian Mining's November 9, 2026 announcement for details on AFRY appointment and contract values. For recent events, verify 2026-08-09 through 2026-11-09. Use another period only when the speaker explicitly names it.

Meridian holds the declaration of public utility and installation license for a 24.3 km, 138 kV power line from the Araputanga substation.

Unidentified speaker (UNKNOWN) ·0:35

How to verify: Verify with Brazilian regulatory bodies (ANEEL) or Meridian's project documentation regarding the Araputanga substation license. For recent events, verify 2026-08-09 through 2026-11-09. Use another period only when the speaker explicitly names it.

Feasibility study puts pre-production capex at $322 million, after-tax NPV5 at $2.1 billion, and IRR at 108%.

Unidentified speaker (speaker_0) ·1:03

How to verify: Access Meridian Mining's Feasibility Study for the Cabasal project, typically filed with securities regulators or available on the company website. For recent events, verify 2026-08-09 through 2026-11-09. Use another period only when the speaker explicitly names it.

Primary source

Rare Earths USA (Serra Verde) reported Q3 2026 revenue of $3.0 million, operating loss of $141.4 million, and $1.16 billion in cash.

Unidentified speaker (speaker_0) ·2:03

How to verify: Check Rare Earths USA's Q3 2026 financial report or press release, verifiable via their investor relations page or SEC EDGAR if public. For recent events, verify 2026-08-09 through 2026-11-09. Use another period only when the speaker explicitly names it.

Primary source

Serra Verde began commercial-scale shipments of heavy mixed rare earth carbonate in October to USSIIE LLC under a 15-year take-or-pay offtake.

Unidentified speaker (speaker_0) ·2:22

How to verify: Verify via Rare Earths USA press releases from October 2026 detailing the USSIIE LLC offtake agreement. For recent events, verify 2026-08-09 through 2026-11-09. Use another period only when the speaker explicitly names it.

Serra Verde guides Q4 sales of at least 325 tons TREO and targets a Stage 1 run rate of 4,000 TPA in Q2 2027.

Unidentified speaker (UNKNOWN) ·2:35

How to verify: Review Rare Earths USA's production guidance statements from late 2026. For recent events, verify 2026-08-09 through 2026-11-09. Use another period only when the speaker explicitly names it.

Primary source

Graphite 1 said on November 9 that its Ohio EPA Air Permit clears the main environmental hurdle for Phase 1.

Unidentified speaker (speaker_0) ·3:17

How to verify: Check Graphite 1's November 9, 2026 press release and Ohio EPA permit records. For recent events, verify 2026-08-09 through 2026-11-09. Use another period only when the speaker explicitly names it.

Graphite 1 Phase 1 has an estimated initial capex of $80 million and targets an investment decision in April 2027.

Unidentified speaker (speaker_0) ·3:37

How to verify: Verify via Graphite 1's project updates or press releases regarding Phase 1 capex and FID timeline. For recent events, verify 2026-08-09 through 2026-11-09. Use another period only when the speaker explicitly names it.

Export Import Bank of the United States issued a non-binding $1.4 billion letter of interest for Graphite 1's expansion.

Unidentified speaker (UNKNOWN) ·4:01

How to verify: Check Export Import Bank of the US announcements or Graphite 1's disclosures regarding the LOI. For recent events, verify 2026-08-09 through 2026-11-09. Use another period only when the speaker explicitly names it.

Do your own research

  • Verify Meridian Mining's feasibility study assumptions for copper ($5.03/lb) and gold ($3,570/oz) prices against current market rates.
  • Check for the existence of a signed EPC contract for the 24.3 km power line and a definitive off-take agreement for Cabasal concentrate.
  • Review Rare Earths USA's (Serra Verde) Q3 2026 financial filings for cash burn rate and revenue recognition under the 15-year take-or-pay agreement.
  • Confirm Graphite 1's Ohio EPA air permit status and the non-binding nature of the $1.4 billion Export-Import Bank LOI.
  • Assess UCor's feedstock supply chain risks given the unnamed suppliers and off-takers for its Louisiana complex.
  • Investigate the terms of Sojits Corp's MOU with Masan High-Tech Materials to determine if it constitutes a binding supply contract or merely a strategic 'seat'.
  • Compare Meridian's $322 million pre-production capex against industry benchmarks for similar-sized copper-gold projects in Brazil.
  • Check if Serra Verde's Q4 guidance of 325 tons TREO aligns with actual production volumes reported in subsequent filings.
Full transcriptexpand
0:00
Unidentified speaker (speaker_0): CMJ Daily Tape Project Finance. Copper Meridian lines up $400 million
0:07
Unidentified speaker (speaker_0): finance offers for Cabasal Meridian Mining,
0:10
Unidentified speaker (UNKNOWN): said
0:10
Unidentified speaker (speaker_0): on November 9 that its Cabasal Copper Gold Silver Project in Mato Grosso, Brazil, has entered pre-construction.
0:18
Unidentified speaker (UNKNOWN): It
0:18
Unidentified speaker (speaker_0): appointed AFRY as EPCM PCM contractor and committed 30.9 million US dollars to pre-construction contracts.
0:27
Unidentified speaker (speaker_0): including power transformers, bridge and road upgrades, a SAG mill, Jameson cells, and an ISA mill.
0:35
Unidentified speaker (UNKNOWN): It
0:35
Unidentified speaker (speaker_0): holds the declaration of public utility and installation license for a 24.3 kilometer, 138 kilovolt power line from the Araputanga substation. Station. Of more than 20 indicative finance proposals, several offered fully financed. packages of $400 million
0:53
Unidentified speaker (speaker_0): covering debt, overrun funding, equity, and offtake.
0:57
Unidentified speaker (UNKNOWN): The
0:58
Unidentified speaker (speaker_0): feasibility study puts pre production capex at $322 million,
1:03
Unidentified speaker (speaker_0): after tax NPV5 at $2.1 billion,
1:08
Unidentified speaker (speaker_0): and IRR R at 108%.
1:11
Unidentified speaker (speaker_0): Meridian gave no FID date. More than 20 indicative finance offers for a $322 million US dollar build say more about a $5.03 US doll
1:22
Unidentified speaker (UNKNOWN): per
1:22
Unidentified speaker (speaker_0): pound copper and $3,570 US doll per ounce gold price deck than about Cabasol's schedule. The binding constraint sits elsewhere. The 24.3 kilometer km 138 kilovolt kV line still has no EPC contract. contractor, and Meridian names no buyer for its concentrate.
1:42
Unidentified speaker (speaker_0): Until the line contract is awarded and an off taker signs, the 108% IRR is a price deck number, not a construction date. OFFTAKE RARE Earth SUSE RARE Earth Ships Serra Verde Heavy Carbonate under a 15-year take or pay USA.
2:03
Unidentified speaker (speaker_0): Rare Earth reported third quarter 2026 revenue of USD 3.0 million, an operating loss of USD 141.4 million, and USD 1.16 billion in cash and restricted cash at September 30. Serra Verde, acquired in September,
2:22
Unidentified speaker (speaker_0): began commercial-scale commercial scale shipments of heavy mixed rare earth carbonate in October. to USSIIE LLC under a 15-year 100% take-or-pay offtake priced on non-China prices.
2:35
Unidentified speaker (UNKNOWN): The
2:35
Unidentified speaker (speaker_0): company guides fourth quarter Serra Verde sales of at least 325 tons TREO and a stage one run rate of 4,000 TPA in the second quarter of 2027.
2:48
Unidentified speaker (UNKNOWN): With
2:48
Unidentified speaker (speaker_0): a 100% take-or-pay, take or pay, Sara Verde's risk is no longer price. It is tons. Fourth quarter guidance of 325 tons
2:59
Unidentified speaker (speaker_0): annualizes to about 1,300 tons per annum.
3:03
Unidentified speaker (UNKNOWN): A
3:04
Unidentified speaker (speaker_0): third of the 4,000 tons per annum stage 1 rate the company targets for Q2 2027.
3:10
Unidentified speaker (UNKNOWN): The
3:10
Unidentified speaker (speaker_0): carbonate is an intermediate, and the basket values are quoted after contracting. contracted separation costs.
3:16
Unidentified speaker (UNKNOWN): The
3:17
Unidentified speaker (speaker_0): number to track is the separation counterparty's throughput, not the floor price. Permitting. Graphite Graphite 1 plans Ohio. Anode sales on purchased graphite before its Alaska Mine Graphite 1 said on November 9 that its Ohio Environmental Protection Agency Air Permit clears the main environmental
3:37
Unidentified speaker (speaker_0): hurdle for Phase 1 and Connote in Connote, O. Ohio. Phase 1 is a 10,000 tons per year plant coating synthetic graphite anode material using purchased synthetic graphite, not Alaskan ore, at an estimated initial capex of 80 million US dollars.
3:53
Unidentified speaker (UNKNOWN): It
3:54
Unidentified speaker (speaker_0): targets an investment decision in April 2027 and first sales in Q for 2028.
4:01
Unidentified speaker (UNKNOWN): The
4:01
Unidentified speaker (speaker_0): Export Import Bank of the United States issued a non-binding $1.4 billion letter of interest for expansion to 100,000 TPA. Phase 1 makes Graphite 1 a coder of someone else's synthetic graphite, not a miner. That puts the schedule on two things the air permit does
4:21
Unidentified speaker (speaker_0): not touch:
4:22
Unidentified speaker (UNKNOWN): who
4:22
Unidentified speaker (speaker_0): sells it the feedstock, and how long battery makers take to qualify its. anode. Samples are out, and the only named buyer, Lucid, holds non-binding agreements. With an investment decision in April 2027 and first sales in Q4 2028, qualification has to close inside that window
4:42
Unidentified speaker (speaker_0): or the plant starts without an order book. Commissioning. Rare Earth Sucor takes 50 tons of carbonate to commission its Louisa. Louisiana separation line. UCor Rare Metals said on November 9th that it received more than 50 tons of basnecyte-derived mixed rare earth carbonate from a North American source to
5:02
Unidentified speaker (speaker_0): commission Rapid SX machine A at its Louisiana Strategic Metals Complex in Alexandria. Machine A has 600 tons per year of TREO capacity across 125. solvent extraction stages. UCOR produced 99.5% NDPR oxide from the
5:22
Unidentified speaker (speaker_0): same feed at its Kingston, Ontario demonstration facility in August 2026. Installation, testing, and commissioning of enhanced machine A is set for the first half of 2027. 50 tons of carbonate is a commissioning lot, not a supply line. At 600 TPATREO,
5:42
Unidentified speaker (speaker_0): it covers less than a month of nameplate, and carbonate carries less oxide than its own weight.
5:48
Unidentified speaker (UNKNOWN): The
5:48
Unidentified speaker (speaker_0): feed supplier is unnamed, the planned samarium europium gadolinium feed has no named source, and the release names no off taker. Machine A's test is whether a second repeatable feed contract exists before commissioning. ends in the first half of 2027. MA
6:08
Unidentified speaker (speaker_0): Tungsten Sojits signs MOU for 5% of Masan High-Tech Materials at Elmet's price floor. Japan's Sojits Corp has signed a memorandum of understanding to acquire a 5% stake in Vietnamese tungsten producer Masan High-Tech High Tech Materials. Masan Group said on November 19th. 9th, according to
6:28
Unidentified speaker (speaker_0): Mining Weekly.
6:29
Unidentified speaker (UNKNOWN): The
6:29
Unidentified speaker (speaker_0): stake will be bought from Masan Horizon, a wholly owned Masan Group subsidiary, at a price no lower than the one paid by Pentagon backed Elmet in its investment in Masan High Tech Materials, the parent company said. A 5% stake bought at Elmet's price floor is a seat, not a supply contract.
6:49
Unidentified speaker (UNKNOWN): What
6:49
Unidentified speaker (speaker_0): matters to a Japanese trade? trading house is tonnage. Whether the MOU carries an offtake right on Masan High-Tech Materials tungsten, in which product form, and for how long. Until a definitive agreement states volumes, the stake changes who sits at the table, not where the concentrate goes.
This page was produced automatically: the audio was transcribed with nvidia/parakeet-tdt-0.6b-v3+sortformer-v2.1 and interpreted by Qwen3.6-35B-A3B-UD-IQ3_S.gguf. Transcription and interpretation can contain errors; always confirm against the original episode. Nothing here is investment advice.

More from Critical Minerals Journal

Critical Minerals Journal

Zimbabwe projects 208,000 t of lithium sulphate as miners seek export ban delay

Episode discussion: Zimbabwe miners seek lithium export ban delay amid production surge; rare earth profits soar

Speakers’ claims: Speakers report that Zimbabwe projects 208,000 metric tons of lithium sulfate output in 2027, prompting miners to request a delay in the January 2027 concentrate export ban to July 2027 to avoid a 1.4 million ton stockpile. In China, rare earth profits doubled in 2026, and magnet exports rose 20.7% despite controls, with oxide prices increasing 62% since April 2025. American Tungsten and Antimony secured exclusive rights to 20% of tungsten concentrate from Mammoth Minerals' Kilba project, though refinery qualification is delayed until September 2027. PT Freeport Indonesia plans to refinance debt via U.S. dollar notes to address operational risks and extend mining rights. Sigma Lithium closed a $125 million convertible bond offering to refinance secured debt, shifting cash flow visibility to contracted volumes.

LithiumRare EarthsTungsten
8 min1 assets10 claims to verify
Critical Minerals Journal

Sigma Lithium swaps an 11.45% loan for a 7% convertible

Episode discussion: Sigma Lithium issues $125M convertible bonds to refinance debt; updates on MMG, Urenco, and critical mineral deals.

Speakers’ claims: The episode details Sigma Lithium's issuance of $125 million in senior unsecured convertible bonds due 2031, priced at a 7% coupon with a conversion price of $6.51, to repay higher-cost debt and fund growth. It also covers the extension of the long-stop date for MMG's acquisition of Anglo-American's Brazilian nickel business to December 31, 2026, pending European Commission review. Additionally, the speakers discuss Urenco USA's first commercial production of LEU Plus, ACG Metals' acquisition of the Nusir Copper Mine, Ramaco Resources' rare earth recovery results, and Crate Critical Minerals' tungsten option in Nevada.

Convertible BondsCritical MineralsM&A
8 min0 assets10 claims to verify