China's data center boom shifts to western regions for cheap power, targeting 46 GW by 2030
Summary
Speakers note that China is the second-largest global data center market, with live IT capacity projected to double from 20 GW in 2025 to 45-46 GW by 2030. The 'East Data, West Computing' strategy directs latency-sensitive workloads to eastern hubs while moving power-intensive AI training to western regions with cheaper renewable energy. National computing hubs mandate strict green power usage, requiring 80% green power and a PUE of 1.2, often met through a mix of direct procurement and green certificates. Analysts highlight that Northwest China holds over half of the development pipeline and is expected to account for one-third of live capacity by 2030. The episode also discusses innovations like Shanghai's underwater data center powered by offshore wind and the grid constraints developers face in the west.
Episode sections
- 1:21 – 4:19
Market Scale and Growth
China is the second-largest data center market globally, with live IT capacity projected to double from 20 GW in 2025 to 45-46 GW by 2030.
- 4:19 – 5:18
National Computing Hubs Strategy
Launched in 2021, 10 national hubs provide integrated infrastructure for better capacity control compared to market-led approaches.
- 5:18 – 9:31
East-West Computing Divergence
The strategy directs latency-sensitive workloads to eastern hubs and power-intensive AI training to western regions with cheaper power.
- 9:31 – 10:33
Underwater Data Center Innovation
Shanghai hosts the first 'Under the Sea' data center powered by offshore wind, integrating renewables with urban computing.
- 10:33 – 11:40
Northwest China as Growth Engine
Northwest China holds 14% of current capacity but over half of the pipeline, expected to account for one-third of live capacity by 2030.
- 11:40 – 21:56
Power Availability vs. Grid Constraints
Western China has abundant renewables but grid bottlenecks; developers use behind-the-meter generation or direct supply to bypass delays.
- 21:56 – 25:34
Green Power Compliance Mechanisms
National hubs mandate 1.2 PUE and 80% green power, met via direct procurement and certificates due to intermittency.
- 25:34 – 29:14
2030 Demand Projections
Power demand is projected to rise 151% to 330 TWh by 2030, with the Northwest absorbing half the incremental demand.
Claims worth verifying
China is the second-largest data center market in the world after the US and the largest in Asia Pacific.
Unidentified speaker (speaker_3) ·3:06
How to verify: BNEF report 'China Data Center Market Prospects'; IDC or Synergy Research Group data center capacity rankings. For recent events, verify 2026-08-05 through 2026-11-05. Use another period only when the speaker explicitly names it.
Live IT capacity in China is expected to double from about 20 gigawatts in 2025 to about 45-46 gigawatts in 2030.
Unidentified speaker (speaker_3) ·3:26
How to verify: BNEF report 'China Data Center Market Prospects'; cross-reference with China's 14th Five-Year Plan for digital infrastructure targets. For recent events, verify 2026-08-05 through 2026-11-05. Use another period only when the speaker explicitly names it.
China launched 10 designated national computing hubs in 2021.
Unidentified speaker (speaker_3) ·4:39
How to verify: NDRC (National Development and Reform Commission) official announcement of 'East Data West Computing' project clusters in 2026. For recent events, verify 2026-08-05 through 2026-11-05. Use another period only when the speaker explicitly names it.
Shanghai is currently the biggest area in China for data center capacity.
Unidentified speaker (speaker_3) ·8:48
How to verify: BNEF report 'China Data Center Market Prospects'; regional capacity breakdowns in industry reports. For recent events, verify 2026-08-05 through 2026-11-05. Use another period only when the speaker explicitly names it.
North and Northwest China has about 14% of China's current live capacity but more than half of the development pipeline.
Unidentified speaker (speaker_3) ·10:33
How to verify: BNEF report 'China Data Center Market Prospects'; project pipeline databases from BNEF or local government planning documents. For recent events, verify 2026-08-05 through 2026-11-05. Use another period only when the speaker explicitly names it.
Northwest China is expected to overtake the Yangtze River Delta around 2028.
Unidentified speaker (speaker_3) ·10:53
How to verify: BNEF report 'China Data Center Market Prospects'; track capacity commissioning schedules in the region. For recent events, verify 2026-08-05 through 2026-11-05. Use another period only when the speaker explicitly names it.
The Northwest region's power demand is projected to go sixfold due to data centers.
Unidentified speaker (speaker_3) ·26:03
How to verify: BNEF report 'China Data Center Market Prospects'; regional power demand forecasts from State Grid Corporation of China. For recent events, verify 2026-08-05 through 2026-11-05. Use another period only when the speaker explicitly names it.
China aims to add another 370 gigawatts of wind and solar in the Northwest over the next five years.
Unidentified speaker (speaker_3) ·26:44
How to verify: NDRC or National Energy Administration (NEA) renewable energy development plans for Northwest provinces (Gansu, Xinjiang, etc.). For recent events, verify 2026-08-05 through 2026-11-05. Use another period only when the speaker explicitly names it.
National hubs mandate a PUE target of 1.2 and 80% green power usage.
Unidentified speaker (speaker_3) ·22:16
How to verify: NDRC guidelines for National Computing Hubs; local government regulations for the 10 designated clusters. For recent events, verify 2026-08-05 through 2026-11-05. Use another period only when the speaker explicitly names it.
Direct green power supply typically covers only around 50% of a data center's annual consumption.
Unidentified speaker (speaker_3) ·24:58
How to verify: BNEF report 'China Data Center Market Prospects'; interviews with developers cited in the report; industry analysis on renewable intermittency vs. 24/7 operations. For recent events, verify 2026-08-05 through 2026-11-05. Use another period only when the speaker explicitly names it.
Do your own research
- Verify the 2025-2030 capacity projections (20 GW to 45-46 GW) against official Chinese government or industry association reports (e.g., CAICT).
- Check the specific regulations and enforcement mechanisms of the 'East Data, West Computing' policy for compliance risks.
- Research the operational status and energy source of Shanghai's 'Under the Sea' data center to verify the offshore wind integration claim.
- Assess the actual grid transmission capacity and bottlenecks in Northwest China by reviewing State Grid Corporation of China investment plans.
- Confirm the 80% green power mandate and PUE 1.2 requirements by examining recent MIIT (Ministry of Industry and Information Technology) guidelines.
- Analyze the cost structure of green electricity certificates versus direct renewable procurement in China's power market.
- Review the development pipeline data for the Northwest region to validate the claim that it holds over half of new capacity.
- Investigate the 330 TWh demand projection source and the 370 GW wind/solar capacity addition plan for the Northwest region.
Full transcriptexpand
- 0:00
- Unidentified speaker (speaker_0): The Climate Pledge, co founded by Amazon and Global Optimism, is a commitment to reach net zero carbon emissions by 2040. Seven years after its launch, the community has grown to more than 700 signatories across 62 industries and 49 countries and territories, reducing emissions, scaling emerging climate solutions, and addressing
- 0:19
- Unidentified speaker (speaker_0): challenges across operations and value chains. Learn more about the collective impact in the 2026 Climate Pledge Report at AMC. Amazon.com/slash sustainability.
- 0:29
- Unidentified speaker (speaker_1): Breaking story from Alpine News Network. Sandra and Kabir are celebrating 50 years of marriage by turning their boring bedroom into a spicy one. Oh my. Alpine Credits sent a super strength hero to help with a home renovation loan.
- 0:45
- Unidentified speaker (UNKNOWN): New
- 0:45
- Unidentified speaker (speaker_1): floors, windows, a heart-shaped button that plays this tune.
- 0:51
- Unidentified speaker (speaker_1): Okay, I think that's quite enough. Own your home, need alone, Alpine Credits can help.
- 0:56
- Unidentified speaker (speaker_0): Alpine Credits, where homeowners get approved.
- 1:00
- Unidentified speaker (UNKNOWN): This
- 1:00
- Unidentified speaker (speaker_0): is Kamala Schelling, and you're listening to Switched On, the Bloomberg NEF podcast. When future generations look back on the energy transition in 2026, one story is likely to stand out: Data Centers. This story is so big that at times it feels like nothing in the energy world can resist its gravitational pull. But here's the
- 1:20
- Unidentified speaker (speaker_0): thing: that data
- 1:21
- Unidentified speaker (speaker_1): center story isn't one single story at all. Data center strategy, it turns out, can vary dramatically. Take China, for instance. It's the largest data center market in the Asia Pacific region, and the second largest in the world after the US. Its IT capacity is expected to more than double by the end of this decade. a growth rate more or less in line with that
- 1:41
- Unidentified speaker (speaker_1): in the US as well. But how China is building its data centers, where it's building them, its strategies for coordinating clean power supply and demand, all these things differentiate it from many of its peer markets in the West. With me in the studio today to discuss China's data center strategy is Fauzia Marzuki, BNEF's head of Asia Pacific Research. Our
- 2:01
- Unidentified speaker (speaker_1): conversation is based on the recent report China Data Center Market Prospects, which is part of an ongoing series exploring data center build-out around the globe. BNEF clients can find this and other related material by heading to BNEF Data Centers Go on the Bloomberg Terminal or at BNEF.com.
- 2:18
- Unidentified speaker (UNKNOWN): If
- 2:18
- Unidentified speaker (speaker_1): you'd like to learn more about how BNEF approaches strategy research on the energy transition, including developments in commodity markets, trends across different sectors, and the cross-cutting technologies shaping the future. You can find more information on bnef.com. And if you'd like to speak with a member of our team about becoming a client, email us at sales.bnef at
- 2:38
- Unidentified speaker (speaker_1): bloomberg.net. But for now, let's talk Chinese data centers with FAWs.
- 2:51
- Unidentified speaker (speaker_1): Fows, welcome to Switched On.
- 2:53
- Unidentified speaker (UNKNOWN): Thanks,
- 2:53
- Unidentified speaker (speaker_3): Kamala, for having me. Um,
- 2:55
- Unidentified speaker (speaker_1): and you're back to talk about data centers. So just sort of lay the groundwork for this conversation. Let's start with the scale of the market. Um, how quickly is China's data center sector growing?
- 3:06
- Unidentified speaker (speaker_3): Okay, well, firstly, let's uh just say this is the first thing that China is not number one in. It is second in terms of data center capacity to the US, but it is the largest market in the entire Asia Pacific. We are expecting the live IT capacity to double from about 20
- 3:26
- Unidentified speaker (speaker_3): gigawatts in 2025 to about 45, 46 in 2030. So we're talking a In huge market here, Kabbalah. Kamala.
- 3:35
- Unidentified speaker (speaker_2): That is huge. It's funny you said that this is the one time when China's finally number two. You know, we always come in and say, oh, solar China's so far ahead, investment China's so far ahead. And finally we found something where it's number two to the US. And I think that's such a fascinating comparison because aside from data center capacity, aside from rate of growth, and by the way, like we're actually
- 3:55
- Unidentified speaker (speaker_2): basing our US numbers and our China numbers on different scenarios. So I don't want to like give you a gigawatt number for the US, but I've talked to our data center analysts and they say it's a very similar rate of change. between the two. But whereas the US seems to be basically wild west, go for broke, build wherever you want, maybe now we're getting a little bit of regulation. China has this really, really coordinated
- 4:15
- Unidentified speaker (speaker_2): approach to data center development. So how does its strategy work?
- 4:19
- Unidentified speaker (speaker_3): Well, so what China's actually done in its usual coordinated manner, it's launched very specific national computing hubs. that was launched in 2021. It's got 10 designated clusters, which are the, let's call them the hotspots, primary locations for the large hyperscale projects and the data center development, at least
- 4:39
- Unidentified speaker (speaker_3): the growth of it. This is where it's a it's an all-in-one package. You get the LAN, you get the power, the fiber connectivity is there, you get that development support, and it's all around. package and encouraging data centers to actually build in these locations where they can screen them better, control the capacity build out, and
- 4:59
- Unidentified speaker (speaker_3): just monitor that particularly.
- 5:01
- Unidentified speaker (speaker_2): So I would imagine that part of what's determining where they build these centers is where do they have power available, where do they have connections available. But it also seems that there is starting to be a differentiation between what they're building in the east part of the country and what they're building in the west. So talk us through that strategy, that divergence.
- 5:18
- Unidentified speaker (speaker_3): So that is the uh China East data, West computing strategy. So it's not so much a wild, wild west. It's just that a lot of the demand centers, so you're talking Hong Kong, Shanghai, the capital Beijing area, these were in the eastern area. So that's where a lot of the original computing was, near the demand centers,
- 5:38
- Unidentified speaker (speaker_3): whereas out.
- 5:39
- Unidentified speaker (speaker_3): west and northwest that area, big open land, lots of renewable capacities getting built out there. So what we're seeing is that the eastern hubs in particular are starting to accommodate the workloads that require that proximity to users. It's got a lot more dense and built out fiber
- 5:59
- Unidentified speaker (speaker_3): connectivity, whereas the western hubs, now that's increasingly handling the compute that can operate further away from customers in the middle of large open spaces and take advantage of that cheaper power and LAN availability. So anything that's uh more power intensive, they're kind of keeping in the more
- 6:18
- Unidentified speaker (speaker_3): established centers, anything that's less sensitive, uh has uh less latency uh sensitivity, that's what's going out in these uh bigger spaces. It is not different than what's being uh than than what we're seeing in other parts of the world, in the US, even other parts of Asia as well. We're seeing a similar strategy almost uh adopt
- 6:38
- Unidentified speaker (speaker_3): in Japan. Not so much a coordinated national strategy, but uh in the Tokyo area. Pretty congested. Pipelines a little bit less there, less space. It's a metropolitan area. So where we're seeing new data centers crop up are in areas like northern Japan, which is the Tohoku area. Lots of wind there.
- 6:58
- Unidentified speaker (speaker_3): And also in like the Hokkaido area. Um we've also got more data centers in uh the Kyushu Island, which is lots of sunshine, lots of solar generation there. It's a trend that we're seeing globally pan out. More space for more computing power. If you need things that are closer to demand centers for like
- 7:18
- Unidentified speaker (speaker_3): cloud storage, that's being built up by the existing centers and hotspots.
- 7:23
- Unidentified speaker (speaker_2): What's so interesting to me about what you just said is this differentiation we're seeing of types of work you need done in these AI data centers, right? So you were just talking about latency and how stuff with relatively low latency needs you have to put close to where it's being used and stuff with the longer latency. you can put farther away. But what exactly kind of projects are
- 7:43
- Unidentified speaker (speaker_2): we talking about that are low versus high latency needs? Like what does that mean in layperson terms?
- 7:48
- Unidentified speaker (speaker_3): Sure. Um, how fast do you need the response to be? If you need it fast, okay, maybe you kind of want that closer to demand centers. But if you're just running a facility that just needs to train models, so AI training. you can probably put that in the middle of a desert. Basically, anything that uh can be remote, it's
- 8:08
- Unidentified speaker (speaker_3): not something that a customer or somebody needs, like that immediate response. And it's just about just churning, training, and kind of running things. Yeah, that can just be a bit further up. Now, some of that stuff also does need to be closer to demand centers. It's just the trend that we're seeing that big compute power. you kinda only
- 8:28
- Unidentified speaker (speaker_3): have the opportunity to do that far away in where there's a lot of land. So they just compartmentalize the demand like those types of functions accordingly. But of course, it's a mix really, really everywhere. Think where the largest data center current concentration is in China is in the uh Yangxi Delta area. Now that's kind
- 8:48
- Unidentified speaker (speaker_3): of the area around Shanghai, right? So as you can imagine. financial area, big hub. You needed a lot of stuff to be done there. Everything from storage, cloud, keeping uh, you know, any other kind of services going. So Shanghai is currently the biggest area in China for data center capacity. It is actually also,
- 9:08
- Unidentified speaker (speaker_3): I think, only second to Virginia, which we know is the
- 9:11
- Unidentified speaker (speaker_2): which is huge.
- 9:12
- Unidentified speaker (speaker_3): Which is huge, right? So once again, number two. But oh, Kamala, you're gonna love this one, actually. Guess what? Shanghai has.
- 9:20
- Unidentified speaker (UNKNOWN): Uh
- 9:21
- Unidentified speaker (speaker_2): a cat-based theme park.
- 9:23
- Unidentified speaker (speaker_3): Shanghai. Well, I wish they had something. You know what? Maybe they do. Maybe they do. I'm not sure.
- 9:28
- Unidentified speaker (UNKNOWN): My
- 9:28
- Unidentified speaker (speaker_2): crazy cat lady energy
- 9:29
- Unidentified speaker (UNKNOWN): comes
- 9:29
- Unidentified speaker (speaker_2): with me everywhere I go.
- 9:31
- Unidentified speaker (speaker_3): They'll love this one. Shanghai's He's got the very first Ender under the Sea Data Center. No! No, no,
- 9:39
- Unidentified speaker (UNKNOWN): no.
- 9:39
- Unidentified speaker (speaker_2): Like actually though.
- 9:40
- Unidentified speaker (speaker_3): It has an under the sea data center. Please
- 9:43
- Unidentified speaker (speaker_2): tell me there is a little mermaid theme
- 9:45
- Unidentified speaker (UNKNOWN): going on here.
- 9:47
- Unidentified speaker (speaker_3): It is powered by offshore wind.
- 9:50
- Unidentified speaker (speaker_2): That's absolutely amazing. So the whole thing is underwater.
- 9:53
- Unidentified speaker (speaker_3): It is underwater.
- 9:55
- Unidentified speaker (speaker_2): Okay, that that's really, really cool.
- 9:57
- Unidentified speaker (speaker_3): Yeah. Um,
- 9:58
- Unidentified speaker (speaker_2): I know this is not a visual medium we're on, but my Bloomberg badge has an Ursula the sea. Seawitch pin that Fows gave me. So I think we need to go have a little mermaid party after this.
- 10:08
- Unidentified speaker (UNKNOWN): We absolutely
- 10:09
- Unidentified speaker (speaker_3): do. To
- 10:09
- Unidentified speaker (UNKNOWN): celebrate. You've
- 10:10
- Unidentified speaker (speaker_2): broken my brain a little bit. I I love this fact so
- 10:12
- Unidentified speaker (UNKNOWN): much.
- 10:13
- Unidentified speaker (speaker_2): Um leaving the watery realm of Shanghai and the United States Delta, let's go to north and northwest China, which is dry and arid and beautiful deserts up there. How much new capacity is being built? in that part of the country now that there is this big push to build more like the intense compute power kind of data center?
- 10:33
- Unidentified speaker (speaker_3): All right. So this region, so north, northwest China, it's got about uh 14% of China's current life capacity, but it's got more than half of the development pipeline. So the upcoming project. So it's huge. So and it is expected to overtake. the Yangtze River Delta around by
- 10:53
- Unidentified speaker (speaker_3): our full costs, around 2028 or so. And it's uh supposed to account for a third of the life capacity that we anticipate by 2030. So it's gonna be big. So it's all about lower electricity costs over there. There's huge uh generation growth, particularly in renewables. It's cheaper. Power
- 11:13
- Unidentified speaker (speaker_3): prices are cheaper there. than they are around Shanghai, around Hong Kong, around Beijing. So it is absolutely one of those growth areas.
- 11:22
- Unidentified speaker (speaker_2): So since you mentioned that the power is cheaper, and we actually a couple years ago did an episode of switched on about these megabases in the desert regions of China where they're building
- 11:31
- Unidentified speaker (UNKNOWN): just
- 11:31
- Unidentified speaker (speaker_3): huge
- 11:32
- Unidentified speaker (speaker_2): solar and wind farms. How important is access to cheap and plentiful power in determining where? these data centers are getting built?
- 11:40
- Unidentified speaker (speaker_3): It's such a huge, I mean, you need power, right? A lot of what we're seeing around the world is uh it's not about how fast the data center can be built, it's how fast it can get access to power, i.e. energize, right? So it's everything from like how quickly can it be connected to a grid, how quickly
- 12:00
- Unidentified speaker (speaker_3): can you build all of this power generation? So one of the things when we look at in our assessment about where it's attractive to site data centers is how quickly can you build out all this power or how quickly you can get connected to the grid? Now, particularly in the north and northwest area. So you've got a lot of available energy, less
- 12:20
- Unidentified speaker (speaker_3): infrastructure from a grid perspective. This is a lesser populated area of China, so you have less of that infrastructure built out. This is actually why this region's been particularly attractive for direct power supply, right? So you actually build renewable generation or clean power sources with the data center,
- 12:40
- Unidentified speaker (speaker_3): or specifically connect it to that data center.
- 12:42
- Unidentified speaker (UNKNOWN): So
- 12:43
- Unidentified speaker (speaker_2): sort of a behind the meter source. You're
- 12:44
- Unidentified speaker (UNKNOWN): building
- 12:45
- Unidentified speaker (speaker_2): it for you're building the the solar array or the wind farm to power the data center.
- 12:49
- Unidentified speaker (speaker_3): Or there's
- 12:50
- Unidentified speaker (UNKNOWN): just already
- 12:51
- Unidentified speaker (speaker_3): so much there. Actually, so this part uh in the western part of China, uh and and this area of China, it's actually a power surplus region. So they already export power to the eastern region. So it's about also creating some of that demand in that area in that province to actually soak up
- 13:11
- Unidentified speaker (speaker_3): some of that excess generation capacity.
- 13:13
- Unidentified speaker (UNKNOWN): Oh,
- 13:13
- Unidentified speaker (speaker_2): that's fascinating because we talked talk so often about the problems with renewables of times of day where there's extra power and there's extra generation. And so in a way, they're they've built the supply, now they need the demands to come. So this is a way to build that demand.
- 13:26
- Unidentified speaker (speaker_3): Absolutely. It also happens the other way around. Of course, you have a you have a data center proposal and you propose that it comes with that generation source. Either way, this is just an area with power generation potential, particular. particularly renewables. Actually, I think uh it's uh it must be wind and solar supplied a third of the region's
- 13:46
- Unidentified speaker (speaker_3): generation last year. And this is about, you know, China's got a decent share of renewables in it. So this region on its own already renewables are a third of its generation. Now that's a sizable amount.
- 13:57
- Unidentified speaker (speaker_2): That's a sizable amount. I was talking to um our data analyst Lola earlier today when I was prepping. for this conversation. And she mentioned that when they developed this rubric for deciding where are the best places to build data centers. And they've they've applied it in the US, they've done it in Europe, they've done it in China now, she said, you know, we very specifically designed it so that you can't max out
- 14:17
- Unidentified speaker (speaker_2): points in any category. And she said, and even with that design, China just kept maxing out points in the power availability category. She said, you know, it completely it broke this thing we built because there's just so much power available. And yet there's always a twist, which is that actually getting power to any given data center
- 14:37
- Unidentified speaker (speaker_2): can still be a bottleneck. So what's going on there?
- 14:41
- Unidentified speaker (speaker_3): So it's uh it's it comes back to that local power delivery. It could be actually a constraint in the sense that it may some of these uh larger data centers, they actually require new or expanded transmission lines or distribution lines. You need more substations. These are additional high voltage lines. I need to carry the power, right?
- 15:00
- Unidentified speaker (speaker_3): So it's uh it's not always going to be as easy as put the solar next to the data center. You might actually still need it to be connected to things. And some of it needs to actually be near infrastructure, right? Like
- 15:11
- Unidentified speaker (UNKNOWN): people need
- 15:11
- Unidentified speaker (speaker_3): to get to it, like and whatnot. So it could be that that's where we still see a little bit of a bottleneck, even though there's so much power. It's also, you know, grid operators are scrutinizing some of these requests more. As we've seen in other parts of the world, you can have phantom projects, right? Just like ride the high, propose a
- 15:31
- Unidentified speaker (speaker_3): whole bunch of large scale data centers. But when you do that, the grid operator does need to plan how to power. all of these things and in some cases actually build these new lines and substations. And it's harder sometimes to also d uh understand really how much power the data center is going to use, because there's a bit of a ramp
- 15:51
- Unidentified speaker (speaker_3): up as well. It could ramp up slower, it could ramp up faster, and that all has implications to how we build out the grid and how the grid serves it.
- 15:59
- Unidentified speaker (speaker_0): The Climate Pledge, co-founded by Amazon and Global Optimism. is a commitment to reach net zero carbon emissions by 2040. Seven years after its launch, the Climate Pledge has grown to a community of more than 700 signatories across 62 industries and 49 countries and territories. Signatories are transforming
- 16:18
- Unidentified speaker (speaker_0): operations, investing in decarbonization, accelerating progress toward net zero carbon, and working together to overcome shared barriers. across their operations and value chains. The potential impact of that collaborative action is significant. Once climate pledge signatories reach net zero carbon, we estimate that 2.6
- 16:38
- Unidentified speaker (speaker_0): billion metric tons of carbon dioxide equivalent emissions will be avoided annually. That equates to removing all gasoline-powered Gasoline powered vehicles in the U.S. for nearly three years. Discover more about the collective impact and the in the 2026 Climate Pledge Report at Amazon.com/slash sustainability.
- 16:55
- Unidentified speaker (speaker_1): Eating well shouldn't be complicated, but somehow it turns into recipes, prep, cleanup, and half your Sunday gone. Factor solves all that. These are fresh, ready-to-eat meals designed by dietitians, delivered to your door and ready in just minutes. No prep, no cleanup, no excuses. And it's not just about convenience. You're
- 17:15
- Unidentified speaker (speaker_1): getting real food, balanced nutrition, and zero artificial stuff. Meals that help you stay on track for all of your goals without the grind of doing it all yourself. Grilled chicken, roasted veggies, steak plates, pasta bowls. They taste like something you'd get in a restaurant, but they come out of your microwave in two minutes flat. If time, cost, or effort have been holding you back from eating
- 17:35
- Unidentified speaker (speaker_1): better, factor just took those off the table. Right now, get up to 9%. $90 off and free shipping. Hurry, this offer won't last long. Go to factormeals.ca and use code FIT. That's up to $90 off and free shipping, but only with the code FIT at factormeals.ca. Factor, Canada's number one meal delivery
- 17:55
- Unidentified speaker (speaker_1): service.
- 17:56
- Unidentified speaker (speaker_2): I feel like you have just gone through, in the context of data centers, the list of all the problems we see with any of the projects we talk about getting built. here at BNF. There's, okay, fine, you can build a lot of solar or you can build a lot of data center capacity, but you have to worry about infrastructure, you have to worry about phantom projects that are not actually going to get built, you have to worry about the rate of ramp up. So it's almost like, yep,
- 18:16
- Unidentified speaker (speaker_2): everything we've seen, we are going through again. It's just now we're talking about data centers. Let's go back to the Yangtze River Delta for a moment. We just talked about how like a lot of capacity is. moving into Northwest China. Yangtze River Delta remains our most attractive market in this ranking we've developed, but it's losing
- 18:35
- Unidentified speaker (speaker_2): its position as the largest market. So, what do you think happens to these established demand centers like Beijing and what's called the Greater Bay Area in China, which to me sounds like San Francisco, but I know it's not. We're talking China here. What happens to them when all of this hyperscale development starts? moving elsewhere?
- 18:52
- Unidentified speaker (speaker_3): Right. Okay, so Greater Bay Area, yeah, not San Francisco, but it is that Hong Kong, Macau area plus the uh Guangdong area. So Guangzhou, Shenzhen, that area. Now, okay, so let's talk about these existing large uh established data center parts in China. So the Beijing area, and this is where we we look at it as the
- 19:11
- Unidentified speaker (speaker_3): Beijing, Tianjin, Hebei centers, it's still good. going to be a major demand center because this is the capital. Just like Virginia is will always be an important part in the data center world for the US, it's still going to be important. It's a share is basically just what's going to go down. And it's it's it's the
- 19:31
- Unidentified speaker (speaker_3): slow, it's gonna be a slow growing region in terms of uh in terms of capacity, right? It might just expand. a little bit further out to like Hebei, where you have just a little bit less cost, but it's still close enough to Beijing that it can service whatever those capital needs are. In the Greater Bay Area, uh specifically,
- 19:51
- Unidentified speaker (speaker_3): it's kind of adopting a little bit of a two-tier model. So you've got Guangzhou, Shenzhen, In and Hong Kong that uh need to retain that latency and that interconnection together. more sensitive workloads to speed. But then you've actually got the Shaogun area, and that's just further in, and that's starting to
- 20:11
- Unidentified speaker (speaker_3): accommodate these larger facilities. So it's close enough to kind of potentially still serve some of those Hong Kong uh workloads and use some of that to uh border border connectivity, right? They're still gonna be important. It's just that the pipeline of growth that we're seeing is being concentrated in these wider, more untapped,
- 20:31
- Unidentified speaker (speaker_3): untapped areas. And I'll also say, you know, those areas, like the n northwest area, they're large projects, right? Nobody's building a small project there. So it does kind of inflate that capacity number. Like you
- 20:42
- Unidentified speaker (UNKNOWN): throw in a you you
- 20:43
- Unidentified speaker (speaker_3): you throw in a couple of large projects. It's
- 20:45
- Unidentified speaker (UNKNOWN): gonna is make
- 20:45
- Unidentified speaker (speaker_3): up a large portion of that upcoming pipeline, right?
- 20:49
- Unidentified speaker (UNKNOWN): I
- 20:49
- Unidentified speaker (speaker_2): mean in a way it sounds like what you're describing in, say, the Beijing area is a version of this spillover for effect. So you run out of space in the middle, but there's a little more land just a little farther away, and then there's a little more land beyond that. So it's almost like if we drop Beijing in the middle of a pond, this is the ripple effect. We need space to build these. We need it to be relatively close. We can't put it a thousand miles away in the northwest corner of the
- 21:09
- Unidentified speaker (speaker_2): country. But so we're just expanding out
- 21:11
- Unidentified speaker (speaker_3): absolutely that
- 21:12
- Unidentified speaker (speaker_2): ripple.
- 21:13
- Unidentified speaker (speaker_3): And it's you
- 21:13
- Unidentified speaker (UNKNOWN): know
- 21:13
- Unidentified speaker (speaker_3): it's same, the you I
- 21:14
- Unidentified speaker (UNKNOWN): mean
- 21:14
- Unidentified speaker (speaker_3): you
- 21:14
- Unidentified speaker (UNKNOWN): see
- 21:14
- Unidentified speaker (speaker_3): it in Australia as well. Data center hubs are Sydney and Melbourne. You run out of space there. You gotta go further up, but you can't go in the middle of the Outpack with no infrastructure.
- 21:25
- Unidentified speaker (UNKNOWN): Back to that list of issues we had. The
- 21:27
- Unidentified speaker (speaker_2): infrastructure, the ramp up time.
- 21:29
- Unidentified speaker (speaker_3): Right, right.
- 21:29
- Unidentified speaker (speaker_2): As you mentioned at the very beginning of this conversation, China has taken this approach where they're saying, Well, we're gonna going build to these spaces where we have the infrastructure and the power. These, I think you called them the um national computing. hubs that they developed. But I would have to imagine that when there's a nationally supported project or a nationally supported hub, that support comes with
- 21:49
- Unidentified speaker (speaker_2): strings attached. So what requirements do developers face inside these national computing hubs?
- 21:56
- Unidentified speaker (speaker_3): Sure, of course. You know, so governments set up nice areas for you, clusters for you to operate. in. Yes, there are some conditions they're going to put on you, right? Because you benefit from foster timelines, better infrastructure, more coordination, foster energization, all of that. So
- 22:16
- Unidentified speaker (speaker_3): some of the things that uh the government has implemented in these national hubs are to have a PUE target, right? So you need that. Okay, so that is a power usage effectiveness. uh target. Now they've put the target at 1.2. This is a fairly efficient data center. Now,
- 22:35
- Unidentified speaker (speaker_3): most data centers are probably around that range, not too far off, but yeah, it it it it does set that limit. Like we want you to be particularly efficient. And also we wanna want to see 80% come from green power. right? So we do want an element of it to be clean power sources. Oh,
- 22:54
- Unidentified speaker (UNKNOWN): so
- 22:55
- Unidentified speaker (speaker_2): they're mandating that. That's really interesting. And you mentioned that data centers are supposed to have 80% of their power coming from clean sources. But with the electricity demand from data centers increasing so dramatically in the coming years, how are operators expected to meet this requirement?
- 23:11
- Unidentified speaker (speaker_3): So there is direct um clean power procurement, right? So actually procuring directly from your solar, from your solar farm, or any other form of renewable generation. There is also green electricity trading that happens in the country. This is green electricity certificates, basically. If you
- 23:31
- Unidentified speaker (speaker_3): can't actually physically access the green power, you buy a certificate accordingly for it. So where the renewables can be directly connected and have direct lines, you have direct power sourcing. Where you can't, you can offset that in a way through these certificates and through these trading
- 23:51
- Unidentified speaker (speaker_3): mechanisms that are actually in place in China. Now, developers have actually, when we uh did our research and did our interviews with developers, we we talked about, well, really realistically, like how much of the data centers electricity consumption is gonna be able to be covered by this. Every project will be different.
- 24:11
- Unidentified speaker (speaker_3): It will be variable. But uh what we what we found from talking to developers was that direct green power can really only cover a part of the data center's power demand. Just because it's variable with the hour and they need to operate all year round. So then we get to the uh point about okay, how do how do we ensure
- 24:31
- Unidentified speaker (speaker_3): that uh round the clock power? Do you need to put batteries there? Do you need to do all of that? That's the
- 24:36
- Unidentified speaker (UNKNOWN): thing.
- 24:39
- Unidentified speaker (speaker_3): It does start to uh impact the project economics though, right? So those are things to those are things to consider. The developers that B BNEF and EF interviewed and spoke to, uh they expected direct. supply to cover only part of the annual consumption, some of them actually even citing around 50%. And the remainder really had to
- 24:58
- Unidentified speaker (speaker_3): be through green electricity trading or uh certificates of some of some sort. There's a higher direct supply share. This would require if some energy storage deployment.
- 25:10
- Unidentified speaker (speaker_2): And as a final question, because everything you're saying about these. green energy certificates and direct use of green energy and simply the electricity needs of these massive data centers, I have to imagine that this huge build-out of data centers in China is gonna have an impact on the power system and the power markets more
- 25:30
- Unidentified speaker (speaker_2): broadly. So what do you see happening there in the next few years?
- 25:34
- Unidentified speaker (speaker_3): So let's uh let's uh let's think about the numbers a little bit here. Okay, so we've got China's data center power demand is projected to increase 151%
- 25:43
- Unidentified speaker (speaker_3): to about 330 terawatt hours by 2030. So that's going to be big, of course, as um as everything that we've seen with with China and the data center story. Now, uh if I look to 2030, what else is there? Okay, so we've got the north and northwest area, that big open space that we were talking about. It's
- 26:03
- Unidentified speaker (speaker_3): projected to add about half of all the incremental data center power demand. And the that regional consumption, though, just as a region, because of all these data centers, the uh power demand in that region is actually going to go sixfold. So again, huge, a huge amount. Nearly half of China's additional data uh data
- 26:23
- Unidentified speaker (speaker_3): center power demand
- 26:24
- Unidentified speaker (UNKNOWN): is
- 26:24
- Unidentified speaker (speaker_3): therefore gonna going to be concentrated in a region. that's also being planned out for a whole bunch more renewable additions. So we're gonna see these two things maybe pan out in parallel. Um, but we've got China aiming to add another 370 gigawatts of wind and solar in that part of the country over the
- 26:44
- Unidentified speaker (speaker_3): next five years. So there is immense opportunity to coordinate this uh power generation. build-out with this computing capacity build-out. And I think it's going to be a really interesting one, but I'm sure it will be coordinated in uh in the sense that it's going to be in the national computing hubs. It is
- 27:04
- Unidentified speaker (speaker_3): also going to be more calculated to also make sure that all of these things actually do operate and service the demand that is going to be required of all. of this artificial intelligence boom and all of this digital infrastructure that's going to be required for China in the next in the next decade plus.
- 27:24
- Unidentified speaker (speaker_2): This is so interesting. And I feel like right now it's a story of looking down the next few years and just seeing massive, massive growth in the pipeline. But I'd imagine in even just a couple of years, you'll be able to come back and say, you know, here's how this strategy has changed. Here's how things, here's how things are really changing on the ground. So I'm so excited, A, to have this base, this foundation, this conversation with you to watch
- 27:44
- Unidentified speaker (speaker_2): what's happening next, but then also to have you come back in a little while and tell us what exactly has happened.
- 27:48
- Unidentified speaker (speaker_3): All right. Looking forward to
- 27:50
- Unidentified speaker (UNKNOWN): it.
- 27:59
- Unidentified speaker (speaker_0): Today's episode of Switched On was produced by Cam Gray. with production assistance from Kamala Shelling. Bloomberg NAF is a service provided by Bloomberg Finance LP and its affiliates. This recording does not constitute nor should it be construed as investment advice, investment recommendations, or a recommendation as to an investment or other strategy. Bloomberg NEF should not be
- 28:19
- Unidentified speaker (speaker_0): considered as information sufficient upon which to base an investment decision. Neither Bloomberg Finance LP nor any of its affiliates makes any representation. or warranty as to the accuracy or completeness of the information contained in this recording, and any liability as a result of this recording is expressly disclaimed.
- 28:45
- Unidentified speaker (speaker_1): Get the latest headlines from our nation's capital every weekday. Hi, I'm Joe Matthew.
- 28:49
- Unidentified speaker (speaker_2): And I'm Kaylee Lines, inviting you to join us for the Balance of Power Podcast.
- 28:53
- Unidentified speaker (speaker_1): Every weekday, we deliver unbiased insight and analysis on the latest news from the White House and Capitol Hill.
- 28:59
- Unidentified speaker (speaker_2): Along with in-depth conversations with lawmakers and the people making policy and shaping our world.
- 29:04
- Unidentified speaker (speaker_1): Get the straight story without the spin.
- 29:07
- Unidentified speaker (speaker_2): Listen and subscribe to the Balance of Power Podcast on Apple, Spotify, or anywhere you listen.
More from Switched On
Blue Wave Moves Energy to the States: Analyst Reaction
Episode discussion: Midterm election results shift energy policy focus to state-level affordability and data center regulation
Speakers’ claims: Derrick Flakoll argues that the US midterm elections were driven by affordability concerns stemming from global energy crises, including conflicts in Ukraine and Iran. With Democrats controlling Congress and Republicans the White House, major federal legislative changes are unlikely, limiting action to bipartisan bills like the American Affordability and Jobs Act. Democratic gains in key states with large data center pipelines, such as Texas and Georgia, have led to potential regulatory moratoria and stricter permitting rules. State-level policies are increasingly focusing on affordability measures like virtual power plants and carbon markets to fund bill relief, rather than solely on decarbonization. Regional grid integration through entities like the Southwest Power Pool may continue despite divergent state policies.
The Energy Transition Has One Big Metal Problem
Episode discussion: Copper supply gap expected by 2028 due to declining ore quality and long mine development times
Speakers’ claims: Tom Rowlands-Rees and Martin Tengler discuss the BloombergNEF Transition Metals Outlook, noting that while nine of ten transition metals have sufficient supply through 2050, copper is the exception. Demand for copper is projected to rise 60% by 2050, creating a supply gap starting in 2028 driven by declining ore quality and a lack of new mine developments. Tengler highlights that new mines take approximately 17 years to develop, meaning high current prices will not bring new supply online until the early 2040s. The speakers also discuss substitution strategies, such as using aluminum for grid cables, and demand shifts toward Lithium Iron Phosphate (LFP) batteries which reduce cobalt and nickel demand. They conclude that copper remains the defining material constraint of the energy transition, with innovation and substitution offering only temporary mitigation.